1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | Lepro Herbals Pvt Ltd | (b)Name of the Company / Organisation | LEPRO HERBALS PVT LTD | (c)Registered Address | GT ROAD, VILLAGE- JATTIPUR,HARYANA,,Panipat,Haryana-132101 | (d)Legal Status of the Company | Private | (e)Joint Venture | No | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | SUNIL MALIK | (b)Designation (Owner/ Partner/ CEO) | VP | (c)Address | 311,313,315,317 EMPIRE PLAZA,M.G. ROAD,SULTANPUR, NEW DEHLI,,Vasant Vihar,South West,Delhi-110030 | (d)Pin code | 110030 | (e)E-mail | maliksunil1169@gmail.com | (f)STD Code. | 129(f)Telephone No. | 26809882 | (g)Fax No. | | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a.I)Project/Activity | 5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
| Minor Activity | | (b)Category | A | (c)Proposal Number | IA/HR/IND2/74345/2018 | (d)Master Proposal Number(Single Window) | SW/124621/2019 | (e)EAC concerned (for category A Projects only) | Industrial Projects - 2 | (f)Project Type | Fresh EC |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | 6/1, 10/1, 10/2, 11, 12, 12/1,12/2, 13, 13/1, 14, | (b)Pincode | 132101 | (c)Bounded Latitudes (North) | | From | | Degree | 291753.26 | Minutes | | Second | | From | | Degree | 291757.22 | Minutes | | Second | | (d)Bounded Longitudes (East) | | From | | Degree | 765944.14 | Minutes | | Second | | From | | Degree | 770001.34 | Minutes | | Second | | (e)Survey of India Topo Sheet No. | 53C/15, 53G/3 | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 237 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 50 | (j)Seismic Zone | 3 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Haryana | |
|
|
Details of State(s) of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
(1.) | Haryana | Panipat | Samalkha | | |
|
6. | Details of Terms of Reference (ToR): | (a)MoEF&CC / SEIAA File Number | IA-J-11011/138/2018-IA-II(I) | (b)Date of Apply of TOR | 12 Apr 2018 | (c)Date of Issue of TOR / Standard ToR | 01 Jun 2018 | (d)Previous TOR Letter | Copy of Previous TOR letter | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | No | (b)Whether details of Public Hearing available? | Yes | (c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above | Yes | |
|
7.1. Details of Public Hearing |
---|
|
S. No. | Details of Advertisement | Details of Public Hearing | Venue | Location Details | No. of People Attended | Issues Raised | Designation of Presiding Officer | Other Designation of Presiding Officer |
---|
(1.) | | Copy of Public Hearing : | Copy of Public Hearing | Date : | 20 Sep 2019 | Distance of Public Hearing Venue from the Proposed Project : | 0 |
| At project site of Lepro Herbals Pvt Ltd G T road, village-Jhattipur,Tehsil-Samalkha,District-Panipat (Haryana.). | State : | Haryana | District : | Panipat | Tehsil : | Samalkha | Village : | Jhattipur |
| 111 | Issue of groundwater and prevention of air pollution, Noise and smoke, Maintenance of ZLD and treatment of effluent | Others | Additional Deputy Commissioner | (2.) | | Copy of Public Hearing : | Copy of Public Hearing | Date : | 20 Sep 2019 | Distance of Public Hearing Venue from the Proposed Project : | 0 |
| At project site of Lepro Herbals Pvt Ltd G T road, village-Jhattipur,Tehsil-Samalkha,District-Panipat (Haryana.). | State : | Haryana | District : | Panipat | Tehsil : | Samalkha | Village : | Jhattipur |
| 111 | Issue of groundwater and prevention of air pollution, Noise and smoke, Maintenance of ZLD and treatment of effluent | Others | Additional Deputy Commissioner | |
8. | Details of Project Configuration/Product: | |
|
8.1. Project Configuration |
---|
S. No. | Plant/Equipment/Facility | Configuration | Remarks |
---|
(1.) | DG Set | 1820kVA | | (2.) | Semi- Synthetic (Alkaloids) | 2.0 TPA | NA | (3.) | Pure Herbal(Alkaloids) | 39.0 TPA | NA | |
8.2. Product |
---|
S. No. | Product/Activity (Capacity/Area) | Quantity | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | Boswelia Gum | 10 | Tons per Annum | | Road | | (2.) | Kalmeg | 5 | Tons per Annum | | Road | | (3.) | Passiflora Leaves | 5 | Tons per Annum | | Road | | (4.) | Ginger Roots | 2 | Tons per Annum | | Road | | (5.) | Nutmeg Seeds | 8 | Tons per Annum | | Road | | (6.) | Butchers Broom | 20 | Tons per Annum | | Road | | (7.) | Humulus lupulus | 0.5 | Tons per Annum | | Road | | (8.) | Sugar cane Wax (Mud) | 1 | Tons per Annum | | Road | | (9.) | Turmeric Roots | 2 | Tons per Annum | | Road | | (10.) | Grape Seeds | 2 | Tons per Annum | | Road | | (11.) | Prunus Africana | 20 | Tons per Annum | | Road | | (12.) | Japanese Atractylodes | 60 | Tons per Annum | | Road | | (13.) | Centella Leaves | 250 | Tons per Annum | | Road | | (14.) | Cardace Seeds | 10 | Tons per Annum | | Road | | (15.) | Coleus Roots | 80 | Tons per Annum | | Road | | (16.) | Anogessius Seeds | 3 | Tons per Annum | | Road | | (17.) | Valerian Roots | 13 | Tons per Annum | | Road | | (18.) | Horse Chest Nut | 129 | Tons per Annum | | Road | | (19.) | Pomegranate Peels | 2 | Tons per Annum | | Road | | (20.) | Tobacco Dust | 125 | Tons per Annum | | Road | | (21.) | Glycrrihizia Glabra | 1124 | Tons per Annum | | Road | | (22.) | Euphorbia Prostrata | 30 | Tons per Annum | | Road | | (23.) | Olive leaves | 6.5 | Tons per Annum | | Road | | (24.) | Red Clover | 2 | Tons per Annum | | Road | | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | Details Not Applicable | |
|
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | 10 Aug 2018 | (iv)Valid Upto | 30 Sep 2020 | (v)File No. | HSPCB/Consent/: 313106018PITCTO5464354 | (vi)Application No. | 5464354 | (vii)Copy of Consent to operate valid as on date | Copy of Consent to Operate | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in Crores) | 44.08 | (b) Funds Allocated for Environment Management (Capital) (in Crores) | 0.81 | (c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) | 0.087 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) | 0.25 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | No | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 1747 | (b)Existing quantity of raw material/fuel | N/A | (c)Total quantity of raw material/fuel | 1747 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | diesel | 282.82 | Tons per Annum | | Nearby pump | Road | | 1.5 | Linkage | | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 03 Oct 2018 To 31 Dec 2018 | (b)Season | Post-Monsoon | |
|
14.1. No. of ambient Air Quality (AAQ) monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | PM10 | | Micro Gram per Meter Cube | 71.6 | 44.6 | 70.9 | 100 | (2.) | NOx | | Micro Gram per Meter Cube | 15.3 | 6.0 | 14.9 | 80 | (3.) | Others | CO | Micro Gram per Meter Cube | 916 | 458 | 916 | 2000 | (4.) | PM2.5 | | Micro Gram per Meter Cube | 46.6 | 24.1 | 46.1 | 60 | (5.) | SO2 | | Micro Gram per Meter Cube | 12.1 | 6.0 | 12.0 | 80 | |
14.2. No. of Ground Water monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | Chlorides | | | mg/l | | 421.87 | 15.99 | 250 | 1000 | (2.) | Fluoride | | | mg/l | | 1.7 | 0.38 | 1.0 | 1.5 | (3.) | Heavy Metals | | mercury | mg/l | | 0.001 | 0.001 | 0.001 | 0 | (4.) | pH | | | NA | | 8.08 | 6.86 | 6.5 | 8.5 | (5.) | TSS | | | mg/l | | 0 | 0 | 0 | 0 | (6.) | TDS | | | mg/l | | 4064 | 396 | 500 | 2000 | (7.) | Total Hardness | | | mg/l | | 1836 | 144 | 200 | 600 | |
14.3. No. of Surface Water monitoring locations : 2 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | pH | | NA | | 7.66 | 7.57 | C | (2.) | BOD | | mg/l | | 3.0 | 2.8 | C | (3.) | COD | | mg/l | | 10.0 | 8.0 | C | (4.) | DO | | mg/l | | 5.3 | 5.2 | C | |
14.4. No. of Ambient Noise monitoring locations : 8 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Day) | A-weighted decibels(dB(A)) | 66.4 | 41.5 | 75 | (2.) | Leq(Night) | A-weighted decibels(dB(A)) | 60.4 | 39.5 | 70 | |
14.5. No. of Soil Sample Monitored locations : 8 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | P(Phosphorus) | Milliequivalents per 100 Gram | | 20.23 | 1.33 | (2.) | Electric Conductivity | Others | mho/cm | 1210 | 215 | (3.) | pH | | | 8.60 | 7.43 | (4.) | N(Nitrogen) | Milliequivalents per 100 Gram | | 100 | 34 | (5.) | K(Potassium) | Milliequivalents per 100 Gram | | 34 | 5 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 30 To 35 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 25 To 30 | (c)Whether Ground Water Intersection will be there ? | No | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity (Kilolitre per Day (Kld)) | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | GroundWater | | 108 | 0 | Copy of Permission Letter | Pipeline | | Tube Well | | 0 | 30 May 2017 | 108 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | Domestic | 10 | 15 | STP | Green Belt Renewal Plant | | 10 | | (2.) | Industrial | 29 | 35 | ETP | Reuse within the Plant & Recycling | | 29 | | |
|
16.1. | (a)Total Waste Water Generation (Kilolitre per Day) | 39 | (b)Total Discharged Water (Kilolitre per Day) | 0 | (c)Total Reused Water (Kilolitre per Day) | 39 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | ETP Sludge | Industrial Waste | | 3000 | Tons | 150 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | (2.) | Off Specification Product | Industrial Waste | | 0.2 | Tons | 150 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | (3.) | Expiry Drugs/ Medicines | Industrial Waste | | 0.2 | Tons | 150 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | (4.) | Process Residue and Waste Process Oil | Industrial Waste | | 30 | Tons | 150 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | (5.) | Spent Carbon | Industrial Waste | | 0.7 | Tons | 150 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | (6.) | Spent Solvent | Industrial Waste | | 18 | Kilolitre | 150 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | (7.) | Empty Barrels and Containers | Industrial Waste | | 450 | Tons | 150 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | (8.) | Used Oil and Spent Oil | Industrial Waste | | 1 | Kilolitre | 150 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | (9.) | Domestic | Municipal Solid Waste | | 21 | Tons | 10 | Road | | Others | Municipal Corporation Panipat- Disposal Sites | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | Others(Specify) | CO | Microgram per Meter Cube | 916 | 0 | 1.3 | 917.4 | 2000 | (2.) | NOx | | Microgram per Meter Cube | 15.3 | 0 | 1.7 | 17.1 | 80 | (3.) | PM10 | | Microgram per Meter Cube | 0 | 0 | 0 | 0.01 | 100 | (4.) | SO2 | | Microgram per Meter Cube | 0 | 0 | 0 | 0.01 | 80 | (5.) | PM2.5 | | Microgram per Meter Cube | 0 | 0 | 0 | 0.01 | 60 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | 0 | 0 | 0 | 0 | PM10 | | 0 | (2.) | 0 | 0 | 0 | 0 | NOx | | 0 | (3.) | 0 | 0 | 0 | 0 | Others | CO | 0 | (4.) | 0 | 0 | 0 | 0 | SO2 | | 0 | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 1012.5 | (b)Source | Dakshin Haryana Bijli Vitran Nigam, Haryana | (c)Uploaded Copy of Agreement | Not Applicable | (d)Standby Arrangement (Details of DG Sets) | Existing - DG set 500kVA- 3 Nos., 320kVA(1nos.), P | (e)Stack Height (in m) | 15 | |
|
20. | Land Ownership Pattern: | (a)Forest Land (ha.) | 0 | (b)Private Land (ha.) | 3.3254 | (c)Government Land (ha.) | 0 | (d)Revenue Land (ha.) | 0 | (e)Other Land (ha.) | 0 | Total Land (ha.) | 3.3254 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area (ha.) | 0 | (b)Waste/Barren Land (ha.) | 0 | (c)Grazing/ Community Land (ha.) | 0 | (d)Surface Water Bodies (ha.) | 0 | (e)Settlements (ha.) | 0 | (f)Industrial (ha.) | 3.3254 | (g)Forest (ha.) | 0 | (h)Mangroves (ha.) | 0 | (i)Marine Area (ha.) | 0 | (j)Others (ha.) : 0 | 0 | Total (ha.) | 3.3254 | |
|
22. Land requirement for various activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement (ha.) | Remarks |
---|
(1.) | Green belt | | 0.67 | | (2.) | Main Plant | | 2.6554 | | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | WLS | None | 98 | None within 10 km from the project site | (2.) | ESAs | None | 97 | None within 10 km from the project site | (3.) | ESZs | None | 97 | None within 10 km from the project site | (4.) | Critically Polluted Area | Panipat | 8.0 | 8.0km from the project site | (5.) | NPA | None | 100 | None within 10 km from the project site | (6.) | Corridors | None | 97 | None within 10 km from the project site | (7.) | Wildlife Corridors | None | 97 | None within 10 km from the project site | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Forest | | None | 15 | None within 10 km from the project site | (2.) | Archaeological Sites | | None | 15 | None within 10 km from the project site | (3.) | Defence Installations | | None | 15 | None within 10 km from the project site | |
|
23.3. | (a)Whether Noc / Permission from the competent authority is required? | No | (b)Whether NBWL recommendation is required? | No | |
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
25. | Tree Cutting: | (a)No. of Trees Cut for the Project (if Forest Land not Involved) | 0 | (b)Details of Tree Cutting and Planting of Trees | Not Applicable | |
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 3.3254 | (b)Land yet to be acquired(Ha) | 0 | (c)Status of Land acquisition if not acquired | 0 | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | 0 | (b)No. of Households | 0 | (c)No. of PDFs (Project Displaced Families) | 0 | (d)No. of PAFs (Project Affected Families) | 0 | (e)Funds Allocated for R&R(in INR) (in Lacs) | 0 | (f)Status of R&R | Completed | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | No | (b)Whether conservation plan for Schedule-I Species has been prepared ? | No | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | No | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | No | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | Yes | (i)Details of Water Bodies in Buffer Area | Western Yamuna Canal | (ii)Direction of Water Bodies in Buffer Area | West | (iii)Distance of Water Bodies in Buffer Area | 3.29 | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 0 | (b)Permanent Employment-During Operation | 198 | (c)Temporary Employment- During Construction | 34 | (d)Temporary Employment- During Operation | 0 | (e)No. of working days | 300 | (f)Total Manpower | 232 | |
|
32. | Green Belt in Ha: | (a)Total Area of Green Belt | 0.67 | (b)Percentage of Total Project Area | 20.15 | (c)No. of Plants to be Planted | 250 | (d)Funds Allocated for Plantation | 260000 | (e)Uploaded Green Belt plan | Copy of Green Belt Plan | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Environmental | Increase in green cover. Implementations of RWH system. Treatment of domestic waste water in sewage treatment
plant. Leak detection and control system. Fire fighting facilities as per OISD Norms. Provision of acoustic enclosures of DG set. PUC certified vehicle for transportation. | (2.) | Social | Improvements in physical infrastructure. Improvements in social Infrastructure. Increase in employment potential. Contribution to the exchequer. | (3.) | Financial | Increase government revenue. Employment will also be generated for local persons. It will help in bringing prosperity to the area. | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details : NOT APPLICABLE |
35. Sector Specific Details For Industrial Projects - 2 |
|
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | No | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | No | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | 46 | (ii)Name of the EIA Consultant | Enkay Enviro Services Pvt. Ltd. | (iii)Address | # 92, Heera Nagar - A, Near Shalimar Bagh, Ajmer Road, Jaipur (Raj.). -, Pin Code:- 302021 | (iv)Mobile No. | 9314363996 | (v)Landline No. | 0141492077 | (vi)Email Id | info@enkayenviro.com | (vii)Category of Accreditation | A | (viii)Sector of Accreditation | Industrial Projects - 2 | (ix)Validity of Accreditation | 07 Feb 2020 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Detail Sought: |
---|
Sno. | EDS Letter | Remarks | Date of EDS |
---|
1. | NA | (i) EIA report to be revised as per the terms of reference granted for the project, and shall conform to Appendix III of the EIA Notification, 2006. The EIA report contains 11 chapters in place of 12 Chapters.
(ii) The onsite emergency plan needs to be submitted as per MSIHC Rules, layout plan of the plant need to be revised.
(iii) Detailed Plan for Corporate Environmental Responsibility and its implementable schedule with budgetary provisions needs to be resubmitted.
(iv) Issues raised during the public hearing has not been properly addressed in the EIA/EMP report. The details of action plan on the issues raised during PH along with budgetary provisions & timelines needs to be submitted. Also, the uploaded copy of public hearing is not clearly visible. Please again upload. | 05 Dec 2019 | 2. | NA | The correction have been made as per the instruction received | 24 Jan 2020 | |
Additional Detail Sought : NIL |
| Undertaking |
| I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. |
| Name of Applicant | SUNIL MALIK | Designation | VP | Name of Company (Applicant Name should not be given here) | LEPRO HERBALS PVT LTD | Address | GT ROAD, VILLAGE- JATTIPUR,HARYANA |
|