Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Manufacturing unit for Ethyl Acetate Plant with capacity of 25 TPD, Formaldehyde plant with capacity of 50 TPD and API manufacturing plant with capacity of 1.2 TPD At Village- Malakpur,Lalru, Tehsil-
(b)Name of the Company / Organisation BANSTAG LIFE SCIENCES PVT LTD
(c)Registered Address H.no. 170, sector 18-A, chandigarh,,Chandigarh,Chandigarh-160018
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant SUNIL BANSAL
(b)Designation (Owner/ Partner/ CEO) DIRECTOR
(c)Address 170 FF, sector-18-A, Chandigarh, Chandigarh,,Chandigarh,Chandigarh,Chandigarh-160018
(d)Pin code 160018
(e)E-mail banstagmalakpur@gmail.com
(f)STD Code. 172(f)Telephone No. 2543036
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
Minor Activity
(b)Category A
(c)Proposal Number IA/PB/IND2/124519/2019
(d)Master Proposal Number(Single Window) SW/124511/2019
(e)EAC concerned (for category A Projects only) Industrial Projects - 2
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. 1580(3-14), 1581(3-14), 1579(5-1)
(b)Pincode 140501
(c)Bounded Latitudes (North)
From
Degree 302825.3
Minutes
Second
From
Degree 302827.5
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 765031.5
Minutes
Second
From
Degree 765039.6
Minutes
Second
(e)Survey of India Topo Sheet No. H43K10 H43K11 H43K14 H43K15
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 287
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 8.5
(j)Seismic Zone 4
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Punjab
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number No.IA-J-11011/158/2019-IA-II(I)
(b)Date of Apply of TOR 12 Apr 2019
(c)Date of Issue of TOR / Standard ToR 17 May 2019
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :17 Aug 2019
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :20 Sep 2019
Distance of Public Hearing Venue from the Proposed Project :0
Project site
State :Punjab
District :SAS Nagar
Tehsil :Derabassi
Village :Malakpur
75The industry should install adequate pollution control devices so that no pollution is generated with the establishment of the unit. The industry shall highlight the benefits the people will get in tOthersAddl. Deputy Commisioner
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Cooling Tower1000 TR, 500 TR1
(2.)Chilling Plant45 TR1
(3.)DG Set320 KVA, 150 KVA, 125 KVA1 each
(4.)ETP20 KL1
(5.)Air Handling Unit20 TR1
(6.)Boiler6 TPH1
(7.)Borewell10 KL/HR1
(8.)Water RO Unit4 KL/HR1
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Dex-lansaprazole104OthersKilogramsRoad
(2.)Moxifloxacin200OthersKilogramsRoad
(3.)Cloxacillin Sodium457OthersKilogramsRoad
(4.)Letrozole500OthersKilogramsRoad
(5.)Temozolomide500OthersKilogramsRoad
(6.)Ethyl Acetate25OthersTonnes per dayRoad
(7.)Formaldehyde50OthersTonnes per dayRoad
(8.)Levofloxacin180.5OthersKilogramsRoad
(9.)Amoxicillin Trihydrate209OthersKilogramsRoad
(10.)Pentaprazole Sodium211OthersKilogramsRoad
(11.)Esomeprazole Magnesium205OthersKilogramsRoad
(12.)Ofloxacin180.5OthersKilogramsRoad
(13.)Di-Cloxacillin Capacity492OthersKilogramsRoad
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 7.52
(b) Funds Allocated for Environment Management (Capital) (in Crores) 1.755
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.15
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.325
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? Yes
d)Inter-State boundaries and international boundaries Yes
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 32.09
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 32.09
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Methanol22.75Kilo Litre per DayPunjabRoad50 MoUCopy of Linkage
(2.)Acetic Acid17.25Kilo Litre per DayPunjabRoad50 MoUCopy of Linkage
(3.)Ethanol17.5Kilo Litre per DayPunjabRoad50 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Mar 2019 To 31 May 2019
(b)Season Pre-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube93.566.292.45100
(2.)PM2.5Micro Gram per Meter Cube50.425.448.8960
(3.)SO2Micro Gram per Meter Cube11.24.210.7580
(4.)NOxMicro Gram per Meter Cube31.416.131.480
    14.2.     No. of Ground Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)TSSmg/l132385002000
(2.)TDSmg/l5703845002000
(3.)Total Hardnessmg/l328.61198.54200600
(4.)Chloridesmg/l121.3268.962501000
(5.)pHNA7.987.136.58.5
(6.)Fluoridemg/l0.790.5711.5
(7.)Heavy MetalsCdmg/l0.0010.00010.0030.01
    14.3.     No. of Surface Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA7.857.16A
(2.)DOmg/l6.65.6A
(3.)BODmg/l186.1B
(4.)CODmg/l55.2112.84B
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))42.5738.1070
(2.)Leq(Day)A-weighted decibels(dB(A))52.6347.275
    14.5.     No. of Soil Sample Monitored locations : 8
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)N(Nitrogen)Kilogram per hectare268248
(2.)pH7.717.01
(3.)Electric ConductivityOthersMicro seimens0.4540.214
(4.)P(Phosphorus)Kilogram per hectare21.0813.85
(5.)K(Potassium)Kilogram per hectare234149.63
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 2.14 To 32.24
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 2.61 To 33.37
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater49.20Copy of Permission LetterPipelineTube Well21-4/5314/PB/IND/201904 Apr 201949.2
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)ETP1620ZLD, RO, MEEReuse within the Plant & Recycling16
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 16
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 16
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)ETP DRIED SLUDGEIndustrial Waste1.2Tons5RoadTreatment, Storage and Disposal Facility(TSDF)
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube93.52.40.7820994.5153100
(2.)PM2.5Microgram per Meter Cube50.42.20.2916950.761960
(3.)SO2Microgram per Meter Cube30.52.61.177831.8890480
(4.)NOxMicrogram per Meter Cube31.42.11.4689132.988180
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)DG SET 125 KVAHSD42.0PM100.000402
(2.)DG SET 125 KVAHSD42.0SO20.01007
(3.)DG SET 150 KVAHSD4.02.0NOx0.002083
(4.)DG SET 320 KVAHSD4.02.0PM100.00103
(5.)DG SET 320 KVAHSD4.02.0SO20.02577
(6.)DG SET 320 KVAHSD4.02.0NOx0.002083
(7.)DG SET 150 KVAHSD4.02.0SO20.01208
(8.)DG SET 125 KVAHSD4.02.0NOx0.002083
(9.)DG SET 150 KVAHSD4.02.0PM100.00048
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 600
(b)Source PUNJAB STATE POWER CORPORATION LIMITED
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 3 D.G. sets of capacity 325 KVA, 175 KVA, 125 KVA
(e)Stack Height (in m) 4.0
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 1.045
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 1.045
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 10726.6
(b)Waste/Barren Land (ha.) 319.2
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 86.5
(e)Settlements (ha.) 0
(f)Industrial (ha.) 565.8
(g)Forest (ha.) 97.5
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : FELLOW LAND 9920.5
    Total (ha.) 21716.1
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Green belt0.48
(2.)Built Up Area0.1238
(3.)OthersROAD AND OPEN AREA0.4411
Total (ha.) 1.0449
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)ESAsNA00
(2.)ESZsNA00
(3.)WLSNA00
(4.)NPANA00
(5.)CorridorsNA00
(6.)Wildlife CorridorsNA00
(7.)Critically Polluted AreaNA00
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestNA00
(2.)Archaeological SitesNA00
(3.)Defence InstallationsNIL00
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 1.045
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired 0
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? Yes
(i)Details of Schedule-I Species pavo cristatus
(b)Whether conservation plan for Schedule-I Species has been prepared ? Yes
(i)Uploaded copy of conservation plan Copy of conservation plan
(ii)Fund Provision made 19 lakhs
(iii)Period of Implementation 3 years
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Ghagghar River
(ii)Direction of Water Bodies in Buffer Area West
(iii)Distance of Water Bodies in Buffer Area 6.8
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 92
(c)Temporary Employment- During Construction 25
(d)Temporary Employment- During Operation 0
(e)No. of working days 300
(f)Total Manpower 117
32.
Green Belt in Ha:
(a)Total Area of Green Belt 0.48
(b)Percentage of Total Project Area 45.93
(c)No. of Plants to be Planted 1500
(d)Funds Allocated for Plantation 600000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)EnvironmentalPlanting of trees groves in surrounding area and Promotion of agro forest in villages planting fruits trees will costs Rs 6 Lakhs.
(2.)FinancialThe project comes under the Greenfield Project and an indicative estimated capital cost of the proposed Plant is around Rs. 752 Lakhs which comes under the section of = 100 Crores so the percentage of Additional Capital Investment of 752 Lakhs shall be about 2% of the total project cost i.e approximately 15 lakhs must be invested in Corporate Environment Responsibility (CER).
(3.)SocialDuring construction phase approx. 25 persons will be required. Whereas it is estimated that total 117 persons will be required for the proposed project during operation phase
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1619/SA 077
(ii)Name of the EIA Consultant VARDAN ENVIRONET
(iii)Address PLOT 82A, SECTOR 5, IMT MANESAR, GURUGRAM, HARYANA
(iv)Mobile No. 9971684812
(v)Landline No. 4343752
(vi)Email Id INDUSTRY@VARDANENVIRONET.COM
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 08 Feb 2020
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File NA
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
      Essential Detail Sought : NIL
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantSUNIL BANSAL
DesignationDIRECTOR
Name of Company (Applicant Name should not be given here)BANSTAG LIFE SCIENCES PVT LTD
AddressH.no. 170, sector 18-A, chandigarh