1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | Suliyari Coal Mine | (b)Name of the Company / Organisation | AP MINERAL DEVELOPMENT CORPORATION | (c)Registered Address | The Andhra Pradesh Mineral Development Corporation Ltd,(A State Govt. of A.P. Undertaking), Door No. 294/1D,100 Feet Road (Tadigadapa to Enikepadu Road) Kanuru,Vijayawada,Krishna,Andhra Pradesh-521137 | (d)Legal Status of the Company | State PSU | (e)Joint Venture | No | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | KEDARANATH REDDY | (b)Designation (Owner/ Partner/ CEO) | GM MINING | (c)Address | The Andhra Pradesh Mineral Development Corporation Limited,A State Govt of AP undertaking , Door no.294/1D, 100 Feet Road,Tadigadapa to Enikepadu Road Kanuru, Vijayawada,Vijayawada (Urban),Krishna,Andhra Pradesh-521137 | (d)Pin code | 521137 | (e)E-mail | coalsuliyari@gmail.com | (f)STD Code. | 866(f)Telephone No. | 2429999 | (g)Fax No. | 08662429977 | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a.I)Project/Activity | 1(a) Mining of minerals
| Minor Activity | | (b)Category | A | (c)Proposal Number | IA/MP/CMIN/73904/2018 | (d)Master Proposal Number(Single Window) | SW/124000/2019 | (e)EAC concerned (for category A Projects only) | Coal Mining | (f)Project Type | Fresh EC |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | Toposheet No. 64I/5 Forest division: Singrauli, R | (b)Pincode | 486881 | (c)Bounded Latitudes (North) | | From | | Degree | 23.92138 | Minutes | | Second | | From | | Degree | 23.92498 | Minutes | | Second | | (d)Bounded Longitudes (East) | | From | | Degree | 82.31254 | Minutes | | Second | | From | | Degree | 82.3142 | Minutes | | Second | | (e)Survey of India Topo Sheet No. | 64 I/5 (OSM NO F44E5) | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 438 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 3.5 | (j)Seismic Zone | 2 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Madhya Pradesh | |
|
|
Details of State(s) of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
(1.) | Madhya Pradesh | Singrouli | No Data | | |
|
6. | Details of Terms of Reference (ToR): | (a)MoEF&CC / SEIAA File Number | IA-J-11015/35/2018-IA-II(M) | (b)Date of Apply of TOR | 04 Apr 2018 | (c)Date of Issue of TOR / Standard ToR | 03 Jul 2018 | (d)Previous TOR Letter | Copy of Previous TOR letter | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | No | (b)Whether details of Public Hearing available? | Yes | (c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above | Yes | |
|
7.1. Details of Public Hearing |
---|
|
S. No. | Details of Advertisement | Details of Public Hearing | Venue | Location Details | No. of People Attended | Issues Raised | Designation of Presiding Officer | Other Designation of Presiding Officer |
---|
(1.) | | Copy of Public Hearing : | Copy of Public Hearing | Date : | 30 Aug 2019 | Distance of Public Hearing Venue from the Proposed Project : | 0 |
| Playground of Govt. High School, Majhaulipath | State : | Madhya Pradesh | District : | Singrouli | Tehsil : | Singrauli | Village : | Jhalari |
| 1400 | (1) Land Acquisition and R&R
(2) Employment to locals
(3) Plantation, Green belt development.
(4) Compensatory Afforestation
(5) Cons. of bio-diversity
(6) Wildlife conservation
(7) Air Poll | Others | A.D.M. | |
8. | Details of Project Configuration/Product: | |
|
8.1. Project Configuration |
---|
S. No. | Plant/Equipment/Facility | Configuration | Remarks |
---|
(1.) | Open Cast Coal Mine | 5.0 Million TPA | Use of Surface Miner for coal removal | |
8.2. Product |
---|
S. No. | Product/Activity (Capacity/Area) | Quantity | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | coal | 5000000 | Tons per Annum | | Road | | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | Details Not Applicable | |
|
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | N/A | (iv)Valid Upto | N/A | (v)File No. | NA | (vi)Application No. | NA | (vii)Copy of Consent to operate valid as on date | NA | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in Crores) | 854.27 | (b) Funds Allocated for Environment Management (Capital) (in Crores) | 1.65 | (c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) | 8.54 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) | 1.0 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | No | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 0 | (b)Existing quantity of raw material/fuel | N/A | (c)Total quantity of raw material/fuel | 0 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | Explosives | 5590 | Tons per Annum | | Approved supplier | Road | | 60 | Others | Contract | Copy of Linkage | (2.) | Lubes/ Greases | 10.5 | Kilo Litre per Day | | Supplier | Road | | 60 | Fuel Supply Agreement | | Copy of Linkage | (3.) | HSD | 105 | Kilo Litre per Day | | Supplier | Road | | 60 | Fuel Supply Agreement | | Copy of Linkage | (4.) | Power | 9 | Mega Watt(MW) | | MPPTCL | Others | HT Line | 3 | LOA | | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 01 Apr 2018 To 30 Jun 2018 | (b)Season | Summer | |
|
14.1. No. of ambient Air Quality (AAQ) monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | PM2.5 | | Micro Gram per Meter Cube | 39 | 20 | 38.1 | 60 | (2.) | SO2 | | Micro Gram per Meter Cube | 22 | 12 | 21 | 80 | (3.) | NOx | | Micro Gram per Meter Cube | 34 | 14 | 31 | 80 | (4.) | Others | CO | Micro Gram per Meter Cube | 0.8 | 0.1 | 0.7 | 4000 (1 HOURLY) | (5.) | PM10 | | Micro Gram per Meter Cube | 87 | 62 | 83.7 | 100 | |
14.2. No. of Ground Water monitoring locations : 6 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | TDS | | | mg/l | | 390 | 280 | 500 | 2000 | (2.) | Total Hardness | | | mg/l | | 185 | 165 | 200 | 600 | (3.) | Fluoride | | | mg/l | | 0.83 | 0.51 | 1.0 | 1.5 | (4.) | Heavy Metals | | Lead | mg/l | | 0.001 | 0.001 | 0.01 | 0.01 | (5.) | Others | Arsenic | | mg/l | | 0.001 | 0.001 | 0.01 | 0.05 | (6.) | TSS | | | NA | | 0 | 0 | 0 | 0 | (7.) | pH | | | NA | | 7.4 | 7.1 | 8.5 | 8.5 | (8.) | Chlorides | | | mg/l | | 26 | 15 | 250 | 1000 | |
14.3. No. of Surface Water monitoring locations : 4 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | DO | | mg/l | | 7.2 | 4.8 | A | (2.) | COD | | mg/l | | 0 | 0 | B | (3.) | pH | | NA | | 7.9 | 7.1 | A | (4.) | BOD | | mg/l | | 4.2 | 1 | D | (5.) | Others | Total dissolved solids | Others | MPN/ 100ml | 130 | 110 | B | |
14.4. No. of Ambient Noise monitoring locations : 8 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Night) | A-weighted decibels(dB(A)) | 45.7 | 35.2 | 70 | (2.) | Leq(Day) | A-weighted decibels(dB(A)) | 60.7 | 36.7 | 75 | |
14.5. No. of Soil Sample Monitored locations : 5 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | K(Potassium) | Kilogram per hectare | | 221 | 0.016 | (2.) | pH | | | 6.4 | 4.5 | (3.) | Electric Conductivity | Millisiemens per Centimetre | | 214 | 43.2 | (4.) | N(Nitrogen) | Kilogram per hectare | | 1450 | 228 | (5.) | P(Phosphorus) | Kilogram per hectare | | 498 | 99.9 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 13.60 To 9.76 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 6.51 To 9.41 | (c)Whether Ground Water Intersection will be there ? | Yes | (d)Upload Copy of Central Ground Water Authority Letter | Copy of Central Ground Water Authority Letter | (e)Letter No. | 21-4/843/MP/MIN/2019 (Application has already been | (f)Date of Issue | 26 Apr 2019 | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity (Kilolitre per Day (Kld)) | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | Others | Mine water (Reused) | 2310 | 0 | Not Appliacble | Pipeline | | Others | Mine water discharge | Application has already been made | 26 Apr 2019 | 3015 | (2.) | GroundWater | | 1330 | 0 | Not Appliacble | Pipeline | | Others | Borewell | 21-4/843/MP/MIN/2019 (Application already made) | 26 Apr 2019 | 1560 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | Pit head bath | 20 | 100 | ETP | Others | Dust suppression at mines | 20 | 0 | (2.) | Potable water for township | 1450 | 2000 | STP | Discharge into Surface Water Body,Others | Afforestation/Green belt development | 120 | 1330 | (3.) | Equipment and vehicle washing | 40 | 100 | ETP | Others | Dust suppression at mines | 40 | 0 | |
|
16.1. | (a)Total Waste Water Generation (Kilolitre per Day) | 1510 | (b)Total Discharged Water (Kilolitre per Day) | 1330 | (c)Total Reused Water (Kilolitre per Day) | 180 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | Over Burden/ Inter Burden | Others | Mining Waste | 80108182 | Tons | 0 | Road | | Others | Will be used for backfilling | (2.) | Top Soil | Others | Mining Waste | 288000 | Tons | 0 | Road | | Others | Making Embankment & avenue plantation/reclamation | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | PM10 | | Microgram per Meter Cube | 68.3 | 0 | 8 | 77.3 | 100 | (2.) | PM2.5 | | Microgram per Meter Cube | 0 | 0 | 0 | 0.0001 | 60 | (3.) | SO2 | | Microgram per Meter Cube | 0 | 0 | 0 | 0.0001 | 80 | (4.) | NOx | | Microgram per Meter Cube | 0 | 0 | 0 | 0.0001 | 80 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | None | None | 0 | 0 | NOx | | N/A | (2.) | None | None | 0 | 0 | PM10 | | N/A | (3.) | None | None | 0 | 0 | SO2 | | N/A | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 9000 | (b)Source | MPPTCL | (c)Uploaded Copy of Agreement | Copy of Agreement | (d)Standby Arrangement (Details of DG Sets) | None | (e)Stack Height (in m) | 0 | |
|
20. | Land Ownership Pattern: | (a)Forest Land (ha.) | 259.239 | (b)Private Land (ha.) | 344.121 | (c)Government Land (ha.) | 396.720 | (d)Revenue Land (ha.) | 251.860 | (e)Other Land (ha.) | 46.060 | Total Land (ha.) | 1298 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area (ha.) | 251.860 | (b)Waste/Barren Land (ha.) | 396.720 | (c)Grazing/ Community Land (ha.) | 0 | (d)Surface Water Bodies (ha.) | 46.060 | (e)Settlements (ha.) | 51.990 | (f)Industrial (ha.) | 0 | (g)Forest (ha.) | 259.239 | (h)Mangroves (ha.) | 0 | (i)Marine Area (ha.) | 0 | (j)Others (ha.) : Barren Tenancy land | 292.131 | Total (ha.) | 1298 | |
|
22. Land requirement for various activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement (ha.) | Remarks |
---|
(1.) | Township | | 5.0 | Outside Lease Area | (2.) | Others | Road | 23.069 | | (3.) | Quarry Area | | 1171.896 | Including backfilled area and void | (4.) | Built Up Area | | 0.697 | | (5.) | Safety Zone | | 78.864 | includes 10.654 ha of greenbelt along ML boundary | (6.) | Water Reservoir | | 23.474 | Diverted nala | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Critically Polluted Area | None | 0 | None | (2.) | ESZs | None | 0 | None | (3.) | WLS | None | 0 | None | (4.) | NPA | None | 0 | None | (5.) | ESAs | None | 0 | None | (6.) | Corridors | None | 0 | None | (7.) | Wildlife Corridors | None | 0 | None | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Forest | | Mohanban R.F. & Langhadol P.F. | 7.3 | Mohanban is in core zone | (2.) | Archaeological Sites | | None | 0 | None | (3.) | Defence Installations | | None | 0 | None | |
|
23.3. | (a)Whether Noc / Permission from the competent authority is required? | No | (b)Whether NBWL recommendation is required? | No | |
|
24. | Forest Land: | Whether any Forest Land involved? | Yes | (a)Forests Clearance Status | Application for Forest Clearance yet to be submitted | (b)Legal Status of Forest Land | Reserved | |
|
25. | Tree Cutting: | (a)No. of Trees Cut for the Project (if Forest Land not Involved) | Not Applicable | (b)Details of Tree Cutting and Planting of Trees | Not Applicable | |
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 0 | (b)Land yet to be acquired(Ha) | 1298 | (c)Status of Land acquisition if not acquired | R&R scheme has already been formulated by district | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | 10 | (b)No. of Households | 1386 | (c)No. of PDFs (Project Displaced Families) | 1386 | (d)No. of PAFs (Project Affected Families) | 0 | (e)Funds Allocated for R&R(in INR) (in Lacs) | 13645 | (f)Status of R&R | In-Progress | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | Yes | (i)Details of Schedule-I Species | Mammals Indian Porcupine, Spotted Deer, Bandicoot Rat, jackal, Indian Wolf, Striped Hyena, Indian Porcupine Reptiles Indian Python, Monitor Lizard, Green Vine Snake, Russel’s Viper, Indian Cobra, Yell | (b)Whether conservation plan for Schedule-I Species has been prepared ? | Yes | (i)Uploaded copy of conservation plan | Copy of conservation plan | (ii)Fund Provision made | 35.45 crore | (iii)Period of Implementation | 10 years | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | Yes | (i)Uploaded copy of approval | Copy of approval | (ii)Letter No. | 6348 | (iii)Date of issue | 16 Sep 2019 | (iv)Recommendation | NA | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | Yes | (i)Details of Water Bodies in Core Area | Hurdul Nala | (b)Whether there is Diversion Required ? | Yes | (i)Details of Diversion Required | 5.3 km inside ML | (ii)Details of Study Conducted | Annexure 7.2 of EIA report | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | Yes | (i)Details of Water Bodies in Buffer Area | Hurdul Nala Amta nala Chhtraha nala Bibiao nala Jhana nala Sulkhia Nala | (ii)Direction of Water Bodies in Buffer Area | South West | (iii)Distance of Water Bodies in Buffer Area | 3.1 | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 25 | (b)Permanent Employment-During Operation | 341 | (c)Temporary Employment- During Construction | 150 | (d)Temporary Employment- During Operation | 641 | (e)No. of working days | 330 | (f)Total Manpower | 1157 | |
|
32. | Green Belt in Ha: | (a)Total Area of Green Belt | 52.643 | (b)Percentage of Total Project Area | 4.06 | (c)No. of Plants to be Planted | 84500 | (d)Funds Allocated for Plantation | 5000000 | (e)Uploaded Green Belt plan | Copy of Green Belt Plan | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Environmental | (1)Revenue generation to the Govt. (2)To meet the rising demand of coal for power generation | (2.) | Social | (1) Peripheral development and CSR activities
(2)Employment generation and improvement in social infrastructures | (3.) | Financial | (1)Provision of about 8.54 crores towards CER
(2)More than 5.45 lakhs plantation till the end of the project | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details For Coal Mining |
|
1. No. of Mineral(s) to be Mined : 1 |
---|
S. No. | Mineral(s) to be Mined | Major or Minor Mineral |
---|
(1.) | Coal | Major | |
|
2. | Mine Capacity in ROM (Run of Mine) | 5.0 million tonnes | |
|
|
4. | Mining Plan: | (a)Approval Letter No. | F.No. 34011-14-2017-CPAM | (b)Date of Approval | 08 Jul 2019 | (c)Approved Letter | Copy of Approved Letter | (d)Approved By State Mining and Geology Department | Coal | (e)Approved Mining Lease Area | 1298 | (f)Approved Capacity | 5.0 | |
|
5. | Technical Details: | (a)Total Geological Reserves (Million Ton) | 142.36 | (b)Mineable Reserves (Million Ton) | 113.08 | (c)Extractable Reserves(Million Ton) | 107.43 | (d)Percent(%) of Extraction | 100 | (e)Grade of Coal /Ore /Mineral | G7 | (f)Stripping Ratio | 7.29 : 1 | (g)Category of Gaseousness (Only for Coal Mining, Others may Write NA) | OPENCAST MINING | (h)Average Gradient(Degree) | 5 | (i)Mining Method | Opencast | (j)Life of Mine (Years) | 23 | |
|
6. | Details of Beneficiations: | (a)Whether it is proposed to install beneficiation plant/Coal washery within the mining lease area | No | (b)Whether it is proposed to install crusher within the mining lease area | No | |
|
7. | Details of Seams: | (a)Whether details of seam applicable | Yes | (b)No. of seams | 15 | (c)Thickness of seams to be worked on | 0.5 | (d)Maximum Thickness of Seams (metres) | 5.82 | |
|
8. | Details of Mining Lease: | (a)Mining Lease Area (in Hectare) | 1298 | (b)Whether obtained Letter of Intent (LOI) from the state government ? | Yes | (i)Copy of Letter of Intent | Copy of Letter of Intent | (ii)Date of issue of LOI | 31 Oct 2019 | (iii)Validity of LOI | 0 | (iv)Reference No. of LOI | F.NO. CBA2-13016/32018-CBA2 | (c)Whether Lease Deed Executed ? | No | (i)Reason thereof | PRIOR EC AND FC CLEARANCE REQUIRED | (d)Whether Lease Deed Renewed ? | No | (i)Reason thereof | NEW MINE | |
|
9. | OB (Over Burden) Management: | (a) Details of External Dumps: | (i)No. of OB Dumps | | (ii)Total Area (in Hectare) | | (iii)Height (in meter) | | (iv)Quantity (in Million Cubic meter) | | (v)No. of year back fill up | | (b) Details of Internal Dumps: | (i)No. of Internal Dumps | | (ii)Total Area (in Hectare) | | (iii)Height (in meter) | | (iv)Quantity (in Million Cubic meter) | | |
|
10. | Details of Topsoil Management: | (a)Quantity of Topsoil excavated during the entire life of the mine (in Million Cubic metre) | 3.52 | (b)Quantity of Topsoil proposed for utilization for reclamation during the entire life of the mine (in Million Cubic metre) | 3.41 | (c)Quantity of Topsoil proposed for utilization for other activities during the entire life of the mine (in Million Cubic metre) | 0.11 | |
|
11. | Details of Final Mine Void: | (a)Area (in Hectare) | | (b)Depth (in meter) | | (c)Volume (in Million Cubic meter) | | |
|
12. | Details of Quarry: | (a)Final Void of 173.881 (hectare) at a Depth of 270 meter which is Proposed to be Converted into a Water Body. | (b)Total Quarry Area (ha) | 1171.896 | |
|
13. | Details of Transportation: | (a)In Pit/Underground to Surface | Dumper/trucks | (b)Surface to Siding/Loading | Dumper/trucks | (c)Transportation / Conveyor Details | The ROM coal produced from the mine shall be trans | |
|
|
14. Details of Land Usage (Pre-Mining) |
---|
S. No. | LAND USE | Other LAND USE | WITHIN ML AREA (Hectare) | OUTSIDE ML AREA (Hectare) | TOTAL (Hectare) |
---|
(1.) | WASTE LAND | | 396.720 | 0 | 396.72 | (2.) | GRAZING LAND | | 0 | 0 | 0 | (3.) | SETTLEMENTS | | 51.990 | 0 | 51.99 | (4.) | AGRICULTURE LAND | | 251.860 | 0 | 251.86 | (5.) | FOREST LAND | | 259.239 | 0 | 259.239 | (6.) | OTHERS(Specify) | Barren Tenancy Land | 292.131 | 0 | 292.131 | (7.) | SURFACE WATER BODIES | | 46.060 | 0 | 46.06 | |
TOTAL | 1298 | 0 | 1298 | |
|
15. Details of Land Usage (Post-Mining) |
---|
S. No. | LAND USE | Other LAND USE | Plantation (ha) | Water Body (ha) | Public Use (ha) | Undisturbed (ha) | Total |
---|
(1.) | Other | Diversion below nala | 0 | 23.474 | 0 | | 23.474 | (2.) | TOP SOIL STORAGE | | 0 | 0 | 0 | | 0 | (3.) | EXCAVATION/QUARRY | | 651.987 | 268.049 | 251.860 | | 1171.896 | (4.) | BUILT UP AREA (COLONY/OFFICE) | | 0 | 0 | 0.697 | | 0.697 | (5.) | VIRGIN AREA | | 52.643 | 0 | 26.221 | | 78.864 | (6.) | INTERNAL OB DUMPS | | 0 | 0 | 0 | | 0 | (7.) | GREEN BELT | | 0 | 0 | 0 | | 0 | (8.) | EXTERNAL OB DUMPS | | 0 | 0 | 0 | | 0 | (9.) | ROADS | | 0 | 0 | 23.069 | | 23.069 | |
TOTAL | 704.63 | 291.523 | 301.847 | 0 | 1298 | |
16. | Details of Reclamation: | Total Afforestation Plan shall be Implemented Covering of Mining.This will Include: | (a)External OB Dump(in hectare) | 0 | (b)Internal Dump(in hectare) | 0 | (c)Quarry(in hectare) | 638.209 | (d)Safety Zone(in hectare) | 52.643 | (e)Final Void of 13.778 (hectare) at a Depth of 250 meter which is Proposed to be Converted into a Water Body. | (f)Density of Tree Plantation per ha (in no.) | 1600 | (g)Others in ha (such as Excavation Area along ML Boundary, along Roads and Infrastructure, Embankment Area and in Township Located Outside the Lease etc) | 0 | (h)Total afforestation plant (in hectare) | 704.630 | |
|
17. | Status of progressive Mining Closure Plan: | Details Not Applicable | |
|
18. Details of Actual Coal/ ORE Production vis-a-vis Sanctioned Capacity since the Inception: |
---|
S. No. | Financial Year | Sanctioned Capacity as per EC (MTPA) | Sanctioned Capacity as per CTO | Sanctioned Capacity as per approved mining plan | Actual Production | Excess Production Beyond the EC / CTO/ Mining Plan Sanctioned Capacity (MTPA) |
---|
(1.) | 0 | 0 | 0 | 0 | 0 | 0 | |
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | No | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | No | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | NABET/EIA/ACO/19/1073 | (ii)Name of the EIA Consultant | MECON Limited | (iii)Address | MECON Limited Vivekananda Path PO. Doranda, Dist – Ranchi, Jharkhand – 834002 | (iv)Mobile No. | 9431101160 | (v)Landline No. | 2480651364 | (vi)Email Id | mining@mecon.co.in | (vii)Category of Accreditation | A | (viii)Sector of Accreditation | Coal Mining | (ix)Validity of Accreditation | 29 Mar 2020 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Detail Sought : NIL |
Additional Detail Sought : NIL |
| Undertaking |
| I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. |
| Name of Applicant | KEDARANATH REDDY | Designation | GM MINING | Name of Company (Applicant Name should not be given here) | AP MINERAL DEVELOPMENT CORPORATION | Address | The Andhra Pradesh Mineral Development Corporation Ltd |
|