1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | Amrapali OCP | (b)Name of the Company / Organisation | Central Coalfields Limited | (c)Registered Address | DARBHANGA HOUSE, CCL, RANCHI,,Ranchi,Jharkhand-834029 | (d)Legal Status of the Company | Central PSU | (e)Joint Venture | No | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | Devendra Prasad | (b)Designation (Owner/ Partner/ CEO) | PO | (c)Address | Office of Project officer, Amrapali , P.O.- Saradhu, PS- Tandwa, DIst- Chatra,,,Chatra,Jharkhand-825321 | (d)Pin code | 825321 | (e)E-mail | poamrapaliccl@gmail.com | (f)STD Code. | 6531(f)Telephone No. | 236004 | (g)Fax No. | | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a.I)Project/Activity | 1(a) Mining of minerals
| Minor Activity | | (b)Category | A | (c)Proposal Number | IA/JH/CMIN/123390/2019 | (d)Master Proposal Number(Single Window) | SW/123389/2019 | (e)EAC concerned (for category A Projects only) | NIL | (f)Project Type | Expansion under para 7(ii) |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | The block is covered by Survey of India Topo Sheet | (b)Pincode | 825321 | (c)Bounded Latitudes (North) | | From | | Degree | 23.859722 | Minutes | | Second | | From | | Degree | 23.977222 | Minutes | | Second | | (d)Bounded Longitudes (East) | | From | | Degree | 84.981944 | Minutes | | Second | | From | | Degree | 85.035277 | Minutes | | Second | | (e)Survey of India Topo Sheet No. | 73-A/13 & special sheet no: 12 & 13 | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 501 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 1 | (j)Seismic Zone | 3 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Jharkhand | |
|
|
Details of State of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
NIL | |
|
6. | Details of Terms of Reference (ToR)/EC: | Not Applicable | |
|
4. | Whether the Project Exempted from Public Hearing? | Details Not Applicable | |
|
8. | Details of Project Configuration/Product: | Details Not Applicable | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | (a)Details of certified report on compliance of earlier environmental clearance condition | (i)Certified Compliance By | Regional | (ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on | Ranchi | (iii)Letter No. | 103-80/05/EPE2596 | (iv)Status of Compliance | Compiled | (v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) | Copy of Certified Compliance Report | (vi)Date of site visit | Dec 19 2017 12:00AM | (b)Details of Capacity Expansion | |
|
S. No. | Product/Activity (Capacity/Area) | Quantity From | Quantity To | Total | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | Capacity | 12 | 4.8 | 16.8 | Others | MTPA | Road,Rail | | |
| (c)Details of Configuration | |
|
S. No. | Plant / Equipment / Facility | Existing Configuration | Proposed Configuration | Final configuration after expansion | Remarks |
---|
(1.) | Project Area | 619.87 Ha | 619.87 Ha | 619.87 Ha | No change in project area | (2.) | Mineable reserve | 114.59 Mte | 114.59 Mte | 114.59 Mte | No change in reserve | (3.) | Quarry Area | 425.22 Ha | 425.22 Ha | 425.22 Ha | No change in quarry area | |
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | 30 Jun 2019 | (iv)Valid Upto | 30 Jun 2020 | (v)File No. | JSPCB/HO/RNC/CTO-5076029/2019/1230 | (vi)Application No. | 5076029 | (vii)Copy of Consent to operate valid as on date | Copy of Consent to Operate | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in Crores) | 858.11 | (b) Funds Allocated for Environment Management (Capital) (in Crores) | 89 | (c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) | 4.29 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) | 1 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | No | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 0 | (b)Existing quantity of raw material/fuel | N/A | (c)Total quantity of raw material/fuel | 0 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | Explosives | 4439765 | Others | kg/annum | Authorised supplier | Road | | 5 | Others | Authorised supplier | Copy of Linkage | |
|
16. | Baseline Data | Not Applicable | |
|
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 10 To 7.10 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 0.95 To 6.50 | (c)Whether Ground Water Intersection will be there ? | Yes | (d)Upload Copy of Central Ground Water Authority Letter | Copy of Central Ground Water Authority Letter | (e)Letter No. | 21-4/328/JH/MIN/2018 | (f)Date of Issue | 29 Dec 2018 | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity (Kilolitre per Day (Kld)) | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | Others | Mine Discharge | 3357 | 0.8 | Not Appliacble | Pipeline | | Others | Mine Pump | 21-4/328/JH/MIN/2018 | 29 Dec 2018 | 3357 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | Domestic | 336 | 336 | STP Proposed as the colony has not been constructed | Reuse within the Plant & Recycling | | 336 | | (2.) | Industrial | 96 | 96 | Oil & Grease Trap with Sedimentation Pond | Reuse within the Plant & Recycling | | 96 | | |
|
16.1. | (a)Total Waste Water Generation (Kilolitre per Day) | 432 | (b)Total Discharged Water (Kilolitre per Day) | 0 | (c)Total Reused Water (Kilolitre per Day) | 432 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | Overburden | Others | Overburden | 18200000 | Tons | 0.6 | Road | | Others | Backfilling of Quarry | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | PM2.5 | | Microgram per Meter Cube | 36 | 3.2 | 1 | 37.1 | 60 | (2.) | SO2 | | Microgram per Meter Cube | 32.2 | 0 | 1 | 33.3 | 80 | (3.) | NOx | | Microgram per Meter Cube | 44.8 | 3.2 | 1 | 46 | 80 | (4.) | PM10 | | Microgram per Meter Cube | 187 | 0 | 73 | 261 | 300 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | NA | NA | 0 | 0 | PM10 | | 0 | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 50000 | (b)Source | Piparwar 33 KV Switch Station of CCL. | (c)Uploaded Copy of Agreement | Not Applicable | (d)Standby Arrangement (Details of DG Sets) | 0 | (e)Stack Height (in m) | 0 | |
|
20. | Land Ownership Pattern: | (a)Forest Land (ha.) | 531.64 | (b)Private Land (ha.) | 0 | (c)Government Land (ha.) | 0 | (d)Revenue Land (ha.) | 88.23 | (e)Other Land (ha.) | 0 | Total Land (ha.) | 619.87 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area (ha.) | 317.43 | (b)Waste/Barren Land (ha.) | 220.20 | (c)Grazing/ Community Land (ha.) | 0 | (d)Surface Water Bodies (ha.) | 20.91 | (e)Settlements (ha.) | 20.67 | (f)Industrial (ha.) | 0 | (g)Forest (ha.) | 448.89 | (h)Mangroves (ha.) | 0 | (i)Marine Area (ha.) | 0 | (j)Others (ha.) : Mining Land | 271.90 | Total (ha.) | 1300 | |
|
22. Land requirement for various activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement (ha.) | Remarks |
---|
(1.) | Quarry Area | | 425.22 | | (2.) | OB Dump Area | | 89.16 | | (3.) | Safety Zone | | 18.92 | | (4.) | Built Up Area | | 26.75 | Workshop CHP Sub station office | (5.) | Others | Haul road nallah diversion & embankment etc | 59.82 | Haul road nallah diversion & embankment etc | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | WLS | NA | 0 | There are no such protected areas within 10 KM of the Project. | (2.) | ESZs | Na | 0 | There are no such protected areas within 10 KM of the Project. | (3.) | Wildlife Corridors | Na | 0 | There are no such protected areas within 10 KM of the Project. | (4.) | Corridors | NA | 0 | There are no such protected areas within 10 KM of the Project. | (5.) | Critically Polluted Area | NA | 0 | There are no such protected areas within 10 KM of the Project. | (6.) | NPA | NA | 0 | There are no such protected areas within 10 KM of the Project. | (7.) | ESAs | NA | 0 | There are no such protected areas within 10 KM of the Project. | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Archaeological Sites | | NA | 0 | There are no such protected areas within 10 KM of the Project. | (2.) | Forest | | Na | 0 | In the buffer zone banalat protected forest, manata protected forest and several other small patches of protected forest falls | (3.) | Defence Installations | | NA | 0 | There are no such areas within 10 KM of the Project. | |
|
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
25. | Tree Cutting: | (a)No. of Trees Cut for the Project (if Forest Land not Involved) | Not Applicable | (b)Details of Tree Cutting and Planting of Trees | Not Applicable | |
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 619.87 | (b)Land yet to be acquired(Ha) | 0 | (c)Status of Land acquisition if not acquired | NA | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | 5 | (b)No. of Households | 0 | (c)No. of PDFs (Project Displaced Families) | 0 | (d)No. of PAFs (Project Affected Families) | 0 | (e)Funds Allocated for R&R(in INR) (in Lacs) | 0 | (f)Status of R&R | Completed | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | Yes | (i)Details of Schedule-I Species | According to Fauna Study conducted by St. Xavier's College Reasearch Centre, Ranchi Schedule-I species reported were Python, Baaz, Kite and Peacock. | (b)Whether conservation plan for Schedule-I Species has been prepared ? | Yes | (i)Uploaded copy of conservation plan | Copy of conservation plan | (ii)Fund Provision made | Rs. 305 lakhs | (iii)Period of Implementation | 03.01.2006-till date | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | Yes | (i)Uploaded copy of approval | Copy of approval | (ii)Letter No. | J-11015/109/2003-IA.II(M) | (iii)Date of issue | 03 Jan 2006 | (iv)Recommendation | NA | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | Yes | (i)Details of Water Bodies in Core Area | Chundru and Barki rivers flowing west to east and north to south respectively control the drainage of the block. The Chundru River marks the Southern boundary of the block whereas Barki River is the eastern limit of the property. | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | Yes | (i)Details of Water Bodies in Buffer Area | The important drainage controlling the project area and its buffer zone is Garhi nadi and its two major tributaries Barki nala and Chundru nadi. | (ii)Direction of Water Bodies in Buffer Area | North | (iii)Distance of Water Bodies in Buffer Area | 1.5 | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 0 | (b)Permanent Employment-During Operation | 275 | (c)Temporary Employment- During Construction | 0 | (d)Temporary Employment- During Operation | 375 | (e)No. of working days | 365 | (f)Total Manpower | 650 | |
|
|
S. No. | Description | Existing | Proposed | Total |
---|
(1.) | Total Area of Green Belt | 3 | 15.92 | 18.92 | (2.) | Percentage of Total Project Area | 0.48 | 2.56 | 3.04 | (3.) | No. of Plants | 1200 | 39800 | 41000 | (4.) | Funds Allocated | 126000 | 4179000 | 4305000 | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Social | Socioeconomic benefits of the Project will accrue through direct and indirect employment to local population. | (2.) | Environmental | Reclamation activities will be carried out throughout the life of mine and post closure as per progressive and final mine closure plan. | (3.) | Financial | Contribution to exchequer | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details For Coal Mining |
|
1. No. of Mineral(s) to be Mined : 1 |
---|
S. No. | Mineral(s) to be Mined | Major or Minor Mineral |
---|
(1.) | Coal | Major | |
|
2. | Mine Capacity in ROM (Run of Mine) | 16800000 | |
|
|
4. | Mining Plan: | (a)Approval Letter No. | Vide no: 167454 | (b)Date of Approval | 04 Oct 2019 | (c)Approved Letter | Copy of Approved Letter | (d)Approved By State Mining and Geology Department | CCL Board | (e)Approved Mining Lease Area | 619.87 | (f)Approved Capacity | 16.8 | |
|
5. | Technical Details: | (a)Total Geological Reserves (Million Ton) | 698.81 | (b)Mineable Reserves (Million Ton) | 114.59 | (c)Extractable Reserves(Million Ton) | 114.59 | (d)Percent(%) of Extraction | 100 | (e)Grade of Coal /Ore /Mineral | A | (f)Stripping Ratio | 0.69 : 1.08 | (g)Category of Gaseousness (Only for Coal Mining, Others may Write NA) | NA | (h)Average Gradient(Degree) | 5 | (i)Mining Method | Opencast | (j)Life of Mine (Years) | 9 | |
|
6. | Details of Beneficiations: | (a)Whether it is proposed to install beneficiation plant/Coal washery within the mining lease area | No | (b)Whether it is proposed to install crusher within the mining lease area | No | |
|
7. | Details of Seams: | (a)Whether details of seam applicable | Yes | (b)No. of seams | 8 | (c)Thickness of seams to be worked on | 10 | (d)Maximum Thickness of Seams (metres) | 20 | |
|
8. | Details of Mining Lease: | (a)Mining Lease Area (in Hectare) | 619.87 | (b)Whether obtained Letter of Intent (LOI) from the state government ? | No | (i)Reason thereof | Land acquired under CB Act SO No: 1381 dt. 09.05.2 | (c)Whether Lease Deed Executed ? | No | (i)Reason thereof | Land acquired under CB Act SO No: 1381 dt. 09.05.2 | (d)Whether Lease Deed Renewed ? | No | (i)Reason thereof | Land acquired under CB Act SO No: 1381 dt. 09.05.2 | |
|
9. | OB (Over Burden) Management: | (a) Details of External Dumps: | (i)No. of OB Dumps | | (ii)Total Area (in Hectare) | | (iii)Height (in meter) | | (iv)Quantity (in Million Cubic meter) | | (v)No. of year back fill up | | (b) Details of Internal Dumps: | (i)No. of Internal Dumps | | (ii)Total Area (in Hectare) | | (iii)Height (in meter) | | (iv)Quantity (in Million Cubic meter) | | |
|
10. | Details of Topsoil Management: | (a)Quantity of Topsoil excavated during the entire life of the mine (in Million Cubic metre) | 637830 | (b)Quantity of Topsoil proposed for utilization for reclamation during the entire life of the mine (in Million Cubic metre) | 637830 | (c)Quantity of Topsoil proposed for utilization for other activities during the entire life of the mine (in Million Cubic metre) | 0 | |
|
11. | Details of Final Mine Void: | (a)Area (in Hectare) | | (b)Depth (in meter) | | (c)Volume (in Million Cubic meter) | | |
|
12. | Details of Quarry: | (a)Final Void of 153.51 (hectare) at a Depth of 90 meter which is Proposed to be Converted into a Water Body. | (b)Total Quarry Area (ha) | 425.22 | |
|
13. | Details of Transportation: | (a)In Pit/Underground to Surface | Tipping Truck | (b)Surface to Siding/Loading | Tipping Truck | (c)Transportation / Conveyor Details | At present, the coal is being transported by tippi | |
|
|
14. Details of Land Usage (Pre-Mining) |
---|
S. No. | LAND USE | Other LAND USE | WITHIN ML AREA (Hectare) | OUTSIDE ML AREA (Hectare) | TOTAL (Hectare) |
---|
(1.) | OTHERS(Specify) | Non-Forest Land | 88.23 | 0 | 88.23 | (2.) | AGRICULTURE LAND | | 0 | 0 | 0 | (3.) | SURFACE WATER BODIES | | 0 | 0 | 0 | (4.) | SETTLEMENTS | | 0 | 0 | 0 | (5.) | FOREST LAND | | 531.64 | 0 | 531.64 | (6.) | WASTE LAND | | 0 | 0 | 0 | (7.) | GRAZING LAND | | 0 | 0 | 0 | |
TOTAL | 619.87 | 0 | 619.87 | |
|
15. Details of Land Usage (Post-Mining) |
---|
S. No. | LAND USE | Other LAND USE | Plantation (ha) | Water Body (ha) | Public Use (ha) | Undisturbed (ha) | Total |
---|
(1.) | Other | Nala diversion Haul Road Safety Zone Garland Drain | 18.92 | 3.10 | 56.72 | | 78.74 | (2.) | VIRGIN AREA | | 0 | 0 | 0 | | 0 | (3.) | EXCAVATION/QUARRY | | 271.71 | 153.51 | 0 | | 425.22 | (4.) | TOP SOIL STORAGE | | 0 | 0 | 0 | | 0 | (5.) | EXTERNAL OB DUMPS | | 89.16 | 0 | 0 | | 89.16 | (6.) | BUILT UP AREA (COLONY/OFFICE) | | 0 | 0 | 26.75 | | 26.75 | (7.) | INTERNAL OB DUMPS | | 0 | 0 | 0 | | 0 | (8.) | ROADS | | 0 | 0 | 0 | | 0 | (9.) | GREEN BELT | | 0 | 0 | 0 | | 0 | |
TOTAL | 379.79 | 156.61 | 83.47 | 0 | 619.87 | |
16. | Details of Reclamation: | Total Afforestation Plan shall be Implemented Covering of Mining.This will Include: | (a)External OB Dump(in hectare) | 89.16 | (b)Internal Dump(in hectare) | 0 | (c)Quarry(in hectare) | 425.22 | (d)Safety Zone(in hectare) | 18.92 | (e)Final Void of 153.51 (hectare) at a Depth of 90 meter which is Proposed to be Converted into a Water Body. | (f)Density of Tree Plantation per ha (in no.) | 2500 | (g)Others in ha (such as Excavation Area along ML Boundary, along Roads and Infrastructure, Embankment Area and in Township Located Outside the Lease etc) | 0 | (h)Total afforestation plant (in hectare) | 379.79 | |
|
17. | Status of progressive Mining Closure Plan: | Details Not Applicable | |
|
18. Details of Actual Coal/ ORE Production vis-a-vis Sanctioned Capacity since the Inception: |
---|
S. No. | Financial Year | Sanctioned Capacity as per EC (MTPA) | Sanctioned Capacity as per CTO | Sanctioned Capacity as per approved mining plan | Actual Production | Excess Production Beyond the EC / CTO/ Mining Plan Sanctioned Capacity (MTPA) |
---|
(1.) | 2014 | 12 | 12 | 12 | 2.55 | 0 | (2.) | 2015 | 12 | 12 | 12 | 4.79 | 0 | (3.) | 2017 | 12 | 12 | 12 | 6.50 | 0 | (4.) | 2016 | 12 | 12 | 12 | 6.23 | 0 | (5.) | 2018 | 12 | 12 | 12 | 10.2 | 0 | |
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | Yes | (b)Name of the Court | High Courts | (c)Name of the Sub Court | Jharkhand | (d)Case No. | WP(PIL) No. 2775 of 2015 | (e)Orders/Directions of the court ,if any and its relevance with the proposed project | Enclosed | (f)Case Details | Case disposed | (g)Uploaded Court Order | Copy of Court Order | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | Yes | (b)Details of Direction Issued Under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act | Notice under Section (5) of EPA 1986 regarding non-compliance of EC conditions | (c)Uploaded Copy of Direction Issued Under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act | Copy of Direction Issued | (d)Compliance status of the directions | Compliance to the notice was submitted to MOEF&CC | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | NABET/EIA/1720/RA0092 | (ii)Name of the EIA Consultant | CENTRAL MINE PLANNING AND DESIGN INSTITUTE | (iii)Address | KANKE ROAD, RANCHI | (iv)Mobile No. | 8987789101 | (v)Landline No. | 0651279222 | (vi)Email Id | gmenv.cmpdi@gmail.com | (vii)Category of Accreditation | A | (viii)Sector of Accreditation | Coal Mining | (ix)Validity of Accreditation | 01 Oct 2020 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Detail Sought: |
---|
Sno. | EDS Letter | Remarks | Date of EDS |
---|
1. | NA | 1. Total area is forest land, however in form 2 it is mentioned that no forest land (S.no. 24 of form 2) is involved. please update the form 2 and details of Stage 1 and Stage 2 FC needs to be uploaded.\
2.Details of Terms of Reference (ToR)/EC in form 2 at Sno. 6 is mentioned NIL. It seems that PP has not uploaded the EC details as the proposal relates to under 7(ii) of EIA 2006 for expansion. PP need to upload the details of EC and details of expansion sought
3.Details of linkage at SNo. 13.1 of Form 2 has to be submitted adequately
4.Details of Presence of Schedule-I Species mentioned NIL, however total land is forest land. Details of conservation plan alongwith its approval letter needs to be uploaded
5. Notice under Section (5) of EPA 1986 regarding non-compliance of EC condition was issued. what is the compliance status of the direction now??
6. This EC is granted under 1994 notification. How the PP can submit the application under 7(ii) provisions of the EIA Notification, 2006. This provisions is only valid for those projects who got EC under 2006 notification. Kindly clarify and upload relevant documents.
7.Updated form 1 has uploaded without signature. Kindly correct the same
5. | 28 Nov 2019 | 2. | NA | The correction have been made as per the instruction received | 10 Jan 2020 | |
Additional Detail Sought : NIL |
| Undertaking |
| I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. |
| Name of Applicant | Devendra Prasad | Designation | PO | Name of Company (Applicant Name should not be given here) | Central Coalfields Limited | Address | DARBHANGA HOUSE, CCL, RANCHI |
|