1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | Onshore Oil and Gas Exploration and Appraisal in the Block CB-ONHP-2017/3 in Bharuch district of Gujarat | (b)Name of the Company / Organisation | M/s Vedanta Limited(Division Cairn Oil & Gas) | (c)Registered Address | DLF Atria, Phase 2, Jacaranda Marg, DLF City,Gurugram,Gurgaon,Haryana-122002 | (d)Legal Status of the Company | Private | (e)Joint Venture | No | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | Khitish kumar Nayak | (b)Designation (Owner/ Partner/ CEO) | Head, HSE & Compliance | (c)Address | DLF Atria, Phase 2, Jacaranda Marg, DLF City,Gurugram,Gurgaon,Gurgaon,Haryana-122002 | (d)Pin code | 122002 | (e)E-mail | kk.nayak@cairnindia.com | (f)STD Code. | 0(f)Telephone No. | 4593082 | (g)Fax No. | | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a.I)Project/Activity | 1(b) Offshore and onshore oil and gas exploration, development & production
| Minor Activity | 1(b) Offshore and onshore oil and gas exploration, development & production
| (b)Category | A | (c)Proposal Number | IA/GJ/IND2/99849/2019 | (d)Master Proposal Number(Single Window) | SW/123154/2019 | (e)EAC concerned (for category A Projects only) | Industrial Projects - 2 | (f)Project Type | Fresh EC |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | 46B16, 46C13 | (b)Pincode | 392110 | (c)Bounded Latitudes (North) | | From | | Degree | 21.57 | Minutes | | Second | | From | | Degree | 22.05 | Minutes | | Second | | (d)Bounded Longitudes (East) | | From | | Degree | 72.49 | Minutes | | Second | | From | | Degree | 72.57 | Minutes | | Second | | (e)Survey of India Topo Sheet No. | F43N1, F43H4, F43G16, F43G12, 46C9, 46C13 | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 210 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 0.8 | (j)Seismic Zone | 3 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Gujarat | |
|
|
Details of State(s) of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
(1.) | Gujarat | Bharuch | Jambusar | | (2.) | Gujarat | Bharuch | Amod | | |
|
6. | Details of Terms of Reference (ToR): | (a)MoEF&CC / SEIAA File Number | IA-J-11011/100/2019-IA-II(I) | (b)Date of Apply of TOR | 19 Mar 2019 | (c)Date of Issue of TOR / Standard ToR | 20 Apr 2019 | (d)Previous TOR Letter | Copy of Previous TOR letter | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | No | (b)Whether details of Public Hearing available? | Yes | (c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above | Yes | |
|
7.1. Details of Public Hearing |
---|
|
S. No. | Details of Advertisement | Details of Public Hearing | Venue | Location Details | No. of People Attended | Issues Raised | Designation of Presiding Officer | Other Designation of Presiding Officer |
---|
(1.) | | Copy of Public Hearing : | Copy of Public Hearing | Date : | 18 Oct 2019 | Distance of Public Hearing Venue from the Proposed Project : | 1 |
| BRC Bhavan, infront of GEB office, Near veterinary clinic, Amod, Tal: Amod, District –Bharuch, Gujarat | State : | Gujarat | District : | Bharuch | Tehsil : | Amod | Village : | Amod |
| 44 | Employments | Others | Resident Additional Collector and Additional District Magistrate | |
8. | Details of Project Configuration/Product: | |
|
8.1. Project Configuration |
---|
S. No. | Plant/Equipment/Facility | Configuration | Remarks |
---|
(1.) | Well Pad | 90 days | For exploitation of Hydrocarbons | |
8.2. Product |
---|
S. No. | Product/Activity (Capacity/Area) | Quantity | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | Drilling of Exploratory & Appraisal wells | 17 | Others | Nos. | Others | Not Applicable | (2.) | Associated Natural Gas | 1.2 | Others | MMSCFD | Others | Captive consumption as fuel in GEG | (3.) | Crude Oil | 8000 | Others | BOPD | Others | Oil Tanker | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | Details Not Applicable | |
|
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | N/A | (iv)Valid Upto | N/A | (v)File No. | NA | (vi)Application No. | NA | (vii)Copy of Consent to operate valid as on date | NA | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in Crores) | 315.42 | (b) Funds Allocated for Environment Management (Capital) (in Crores) | 0.1 | (c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) | 4.73 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) | 0.1 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | No | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 102 | (b)Existing quantity of raw material/fuel | N/A | (c)Total quantity of raw material/fuel | 102 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | Water | 102 | Kilo Litre per Day | | Tanker Supply | Road | | 0 | Open Market | | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 13 Mar 2019 To 06 Jun 2019 | (b)Season | Summer | |
|
14.1. No. of ambient Air Quality (AAQ) monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | PM10 | | Micro Gram per Meter Cube | 60.5 | 38.5 | 60.2 | 100 | (2.) | PM2.5 | | Micro Gram per Meter Cube | 28.9 | 17.2 | 28.9 | 60 | (3.) | SO2 | | Micro Gram per Meter Cube | 9.5 | 5.1 | 9.2 | 80 | (4.) | NOx | | Micro Gram per Meter Cube | 19.9 | 8.4 | 19.8 | 80 | (5.) | Others | Carbon Monoxide | Mili Gram per Meter Cube | 0.29 | 0.11 | 0.28 | 4 | |
14.2. No. of Ground Water monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | Total Hardness | | | mg/l | | 780 | 240 | 200 | 600 | (2.) | Others | Sulphate | | mg/l | | 208 | 34 | 200 | 400 | (3.) | pH | | | NA | | 8.05 | 7.41 | 6.5 | 8.5 | (4.) | TSS | | | mg/l | | 1 | 1 | 1 | 1 | (5.) | TDS | | | mg/l | | 1741 | 522 | 500 | 2000 | (6.) | Chlorides | | | mg/l | | 707 | 162 | 250 | 1000 | (7.) | Fluoride | | | mg/l | | 0.91 | 0.36 | 1 | 1.5 | (8.) | Heavy Metals | | Lead | mg/l | | 0.003 | 0.003 | 0.003 | 0.003 | (9.) | Others | Iron | | mg/l | | 0.05 | 0.05 | 0.3 | 0.3 | |
14.3. No. of Surface Water monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | DO | | mg/l | | 6.1 | 4.6 | C | (2.) | BOD | | mg/l | | 5.1 | 2.5 | C | (3.) | Others | TDS | mg/l | | 978 | 219 | C | (4.) | Others | Nitrate | mg/l | | 15 | 2 | C | (5.) | pH | | NA | | 8.36 | 7.88 | C | (6.) | COD | | mg/l | | 32 | 18 | C | (7.) | Others | Chloride | mg/l | | 336 | 48 | C | |
14.4. No. of Ambient Noise monitoring locations : 8 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Day) | A-weighted decibels(dB(A)) | 52.6 | 47.8 | 55 | (2.) | Leq(Night) | A-weighted decibels(dB(A)) | 44.1 | 39.9 | 45 | |
14.5. No. of Soil Sample Monitored locations : 8 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | pH | | | 8.23 | 7.56 | (2.) | N(Nitrogen) | Kilogram per hectare | | 561 | 280 | (3.) | Electric Conductivity | Millisiemens per Centimetre | | 0.687 | 0.089 | (4.) | K(Potassium) | Parts per Million | | 463 | 216 | (5.) | P(Phosphorus) | Kilogram per hectare | | 52.8 | 19.7 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 25 To 5 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 15 To 6 | (c)Whether Ground Water Intersection will be there ? | No | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity (Kilolitre per Day (Kld)) | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | Others | Tanker Supply | 102 | 2 | Copy of Permission Letter | modeOthers | Tanker | Others | Not Applicable | xyz | 25 Oct 2019 | 102 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | Wastewater - produced water | 223 | 250 | Mobile Effluent treatment plant | Others | As per CPCB standard | 170 | 53 | (2.) | Effluent from drilling operation | 40 | 50 | Mobile Effluent treatment plant | Others | As per CPCB standard | 10 | 30 | (3.) | Domestic waste water | 25 | 30 | mobile sewage treatment plant | Reuse within the Plant & Recycling | | 25 | 0 | |
|
16.1. | (a)Total Waste Water Generation (Kilolitre per Day) | 288 | (b)Total Discharged Water (Kilolitre per Day) | 83 | (c)Total Reused Water (Kilolitre per Day) | 205 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | Domestic Waste | Municipal Solid Waste | | 0.03 | Tons | 0 | Road | | Others | Compost pits | (2.) | Drill cuttings associate with WBM | Industrial Waste | | 750 | Tons | 0 | Road | | Others | HDPE lined collection pit | (3.) | Drill cuttings associated with SBM | Industrial Waste | | 1500 | Tons | 0 | Road | | Others | HDPE lined collection pit | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | NOx | | Microgram per Meter Cube | 19.9 | 1.3 | 2.94 | 22.85 | 80 | (2.) | PM2.5 | | Microgram per Meter Cube | 28.9 | 1.1 | 0.18 | 29.09 | 60 | (3.) | SO2 | | Microgram per Meter Cube | 9.5 | 1.2 | 0.003 | 9.504 | 80 | (4.) | PM10 | | Microgram per Meter Cube | 60.5 | 1.1 | 0.18 | 60.681 | 100 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | EPU Flare Stack | NG | 30 | 0.3 | NOx | | 2.52 | (2.) | Test flare Stack | NG | 30 | 0.21 | SO2 | | 0.063 | (3.) | 1000 KVA DG Set | HSD | 10 | 0.2 | NOx | | 0.687 | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 2450 | (b)Source | 1 x 350 KVA DG Sets (camp site) 1 x 100 KVA DG Set | (c)Uploaded Copy of Agreement | Not Applicable | (d)Standby Arrangement (Details of DG Sets) | 1X1000 KVA (drilling site) –(1Stand by )or 1X1850 | (e)Stack Height (in m) | 10 | |
|
20. | Land Ownership Pattern: | (a)Forest Land (ha.) | 0 | (b)Private Land (ha.) | 9 | (c)Government Land (ha.) | 0 | (d)Revenue Land (ha.) | 0 | (e)Other Land (ha.) | 0 | Total Land (ha.) | 9 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area (ha.) | 49000 | (b)Waste/Barren Land (ha.) | 5901 | (c)Grazing/ Community Land (ha.) | 3200 | (d)Surface Water Bodies (ha.) | 10200 | (e)Settlements (ha.) | 7700 | (f)Industrial (ha.) | 0 | (g)Forest (ha.) | 0 | (h)Mangroves (ha.) | 0 | (i)Marine Area (ha.) | 0 | (j)Others (ha.) : Road, rail etc | 13600 | Total (ha.) | 89601 | |
|
22. Land requirement for various activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement (ha.) | Remarks |
---|
(1.) | Others | Well pad | 9 | Each well pad | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Critically Polluted Area | None | 0 | Not Applicable | (2.) | ESZs | None | 0 | Not Applicable | (3.) | WLS | None | 0 | Not Applicable | (4.) | NPA | None | 0 | Not Applicable | (5.) | ESAs | None | 0 | Not Applicable | (6.) | Corridors | None | 0 | Not Applicable | (7.) | Wildlife Corridors | None | 0 | Not Applicable | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Defence Installations | | None | 0 | Not Applicable | (2.) | Others | Water Bodies | Rupa Khadi & Rohad Lake | 0.75 | From well no. 8 & 9 | (3.) | Forest | | None | 0 | Not Applicable | (4.) | Archaeological Sites | | None | 0 | Not Applicable | |
|
23.3. | (a)Whether Noc / Permission from the competent authority is required? | No | (b)Whether NBWL recommendation is required? | No | |
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
25. | Tree Cutting: | (a)No. of Trees Cut for the Project (if Forest Land not Involved) | 0 | (b)Details of Tree Cutting and Planting of Trees | Not Applicable | |
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 0 | (b)Land yet to be acquired(Ha) | 9 | (c)Status of Land acquisition if not acquired | Land will be taken on lease | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | 0 | (b)No. of Households | 0 | (c)No. of PDFs (Project Displaced Families) | 0 | (d)No. of PAFs (Project Affected Families) | 0 | (e)Funds Allocated for R&R(in INR) (in Lacs) | 0 | (f)Status of R&R | Yet To Start | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | Yes | (i)Details of Schedule-I Species | Pea Fowl (Pavo cristatus) | (b)Whether conservation plan for Schedule-I Species has been prepared ? | No | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | No | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | Yes | (i)Details of Water Bodies in Core Area | Dhadhar River (Vishwamitri) | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | Yes | (i)Details of Water Bodies in Buffer Area | Dhadhar River (Vishwamitri) | (ii)Direction of Water Bodies in Buffer Area | South West | (iii)Distance of Water Bodies in Buffer Area | 0 | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 0 | (b)Permanent Employment-During Operation | 0 | (c)Temporary Employment- During Construction | 0 | (d)Temporary Employment- During Operation | 80 | (e)No. of working days | 90 | (f)Total Manpower | 80 | |
|
32. | Green Belt in Ha: | (a)Total Area of Green Belt | 2.8 | (b)Percentage of Total Project Area | 31.11 | (c)No. of Plants to be Planted | 1500 | (d)Funds Allocated for Plantation | 50000 | (e)Uploaded Green Belt plan | Copy of Green Belt Plan | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Social | Employment | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details : NOT APPLICABLE |
35. Sector Specific Details For Industrial Projects - 2 |
|
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | No | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | No | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | NABET/EIA/1619/RA0048 | (ii)Name of the EIA Consultant | ABC Techno Labs India Pvt. Ltd. | (iii)Address | 400, 13th Street, SIDCO Industrial Estate (North Phase) Ambattur – 600 098 | (iv)Mobile No. | 8420642002 | (v)Landline No. | 0442616112 | (vi)Email Id | abc@abctechnolab.com | (vii)Category of Accreditation | A | (viii)Sector of Accreditation | Industrial Projects - 2 | (ix)Validity of Accreditation | 15 Nov 2019 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Detail Sought: |
---|
Sno. | EDS Letter | Remarks | Date of EDS |
---|
1. | NA | (i) Issues raised during public hearing, response by the project proponent, action plan with budgetary allocation. Public hearing proceedings to be forwarded by the Member Secretary, SPCB along with complete public hearing/consultation documents.
(ii) It is noted that there are various deficiencies in Form 2 (viz. S. no. 7.1, 32, 38 etc.) uploaded by the PP and accordingly Revised Form 2 shall be submitted incorporating all the information related to the project.
(iii) The report contains 11 Chapters. TOR compliance is not adequate in EIA/EMP report and need to revise as per the terms of reference granted for the project, and shall conform to Appendix III of the EIA Notification, 2006.
(iv) The onsite emergency plan needs to be submitted as per MSIHC Rules, layout plan of the plant need to be revised.
(v) As per EIA Report schedule I species reported. Please submit approval status of conservation plan for Schedule I species along with budgetary provisions and its approval from CWLW needs to be provided.
(vi) Detailed Plan for Corporate Environmental Responsibility and its implementable schedule with budgetary provisions needs to be resubmitted.
(vii) Details of show cause notice and other violations, if any, needs to be submitted.
(viii) Incremental GLC values in the EIA/Form 2 were reported and needs to be confirmed/rechecked.
(ix) Effluent treatment mechanism with plan for Zero Liquid Discharge needs to be submitted.
(x) Details of Raw material linkage and its mitigation measure during transportation needs to be submitted.
(xi) Consultant accreditation has expired | 05 Dec 2019 | 2. | NA | The correction have been made as per the instruction received | 09 Dec 2019 | |
Additional Detail Sought: |
---|
Sno. | ADS Letter | Remarks | Date of ADS |
---|
1. | ADS Reply Letter | We are pleased to submit the response to the Additional detail Sought (ADS) against Proposal No. IA/GJ/IND2/99849/2019 for your kind consideration and grant of environmental clearance. | 08 May 2020 | 2. | NA | The proposal was accordingly deferred for the needful.
| 06 Feb 2020 | |
| Undertaking |
| I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. |
| Name of Applicant | Khitish kumar Nayak | Designation | Head, HSE & Compliance | Name of Company (Applicant Name should not be given here) | M/s Vedanta Limited(Division Cairn Oil & Gas) | Address | DLF Atria, Phase 2, Jacaranda Marg, DLF City |
|