Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) M/s Damodar Valley Corporation for Tubed Coal Mines Project (6.0 MTY) Villages: Tubed, Mangra, Dihi, Ambajharan, Dhobiajharam, Nawari, Tehsil: Latehar, District: Latehar (Jharkhand)
(b)Name of the Company / Organisation MS DAMODAR VALLEY CORPORATION
(c)Registered Address D.V.C. Tower,V.I.P Road, Kolkata,,Kolkata,West Bengal-700054
(d)Legal Status of the Company Others
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Damodar Valley Corporation
(b)Designation (Owner/ Partner/ CEO) Ferm
(c)Address Near Villages Tubed, mangra, dihi, ambajharan, dhobiajharan, nawari, Tehsil Latehar, District Latehar, State Jharkhand,,No Data,Latehar,Jharkhand-829204
(d)Pin code 829204
(e)E-mail tubedcoal460@gmail.com
(f)STD Code. 141(f)Telephone No. 2744509
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity1(a) Mining of minerals
Minor Activity
(b)Category A
(c)Proposal Number IA/JH/CMIN/65302/2017
(d)Master Proposal Number(Single Window) SW/121833/2019
(e)EAC concerned (for category A Projects only) Coal Mining
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Village Khasra No. Mangra 330 Tubed 333 Dihi 334 A
(b)Pincode 700054
(c)Bounded Latitudes (North)
From
Degree 234917.30
Minutes
Second
From
Degree 23501.35
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 84341.99
Minutes
Second
From
Degree 8435.015
Minutes
Second
(e)Survey of India Topo Sheet No. F45A9
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 412
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 0
(j)Seismic Zone 2
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Jharkhand
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)JharkhandLateharNo Data
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number IA-J-11015/54/2017-IA-II(M)
(b)Date of Apply of TOR 03 Jan 2018
(c)Date of Issue of TOR / Standard ToR 16 Mar 2018
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :08 Dec 2018
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :10 Jan 2019
Distance of Public Hearing Venue from the Proposed Project :9.52
Latehar Stadium (Near Boys High School
State :Jharkhand
District :Latehar
Tehsil :Latehar
Village :Tubed, Mangra, Dihi, Ambajharan, Dhobiajharan, Nawari
629Regarding compensation, employment and environment managementOthersAdditional Collector
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Open cast Coal Mining Project6 million Tons per annum
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)4606000000Tons per AnnumRail
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 1300
(b) Funds Allocated for Environment Management (Capital) (in Crores) 42.89
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 12.24
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 2.49
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 0
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 0
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Diesel2310Kilo Litre per DayNear by petrol pumpsRoad2.6 OthersBY ROADCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Mar 2018 To 31 May 2018
(b)Season Pre-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 10
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM2.5Micro Gram per Meter Cube26.2611.2425.2360
(2.)SO2Micro Gram per Meter Cube9.524.129.3980
(3.)NOxMicro Gram per Meter Cube15.146.5214.5480
(4.)PM10Micro Gram per Meter Cube44.2832.2944.27100
    14.2.     No. of Ground Water monitoring locations : 10
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA7.926.826.58.5
(2.)TSSmg/l3210.500
(3.)Total Hardnessmg/l2601920600
(4.)Fluoridemg/l0.660.3611.5
(5.)TDSmg/l5104105002000
(6.)Chloridesmg/l110880100
(7.)Heavy Metalsironmg/l0.680.260.301
    14.3.     No. of Surface Water monitoring locations : 4
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHmg/l8.126.78A
(2.)DOmg/l8.27.4A
(3.)CODmg/l00A
(4.)BODmg/l7.24.8A
    14.4.     No. of Ambient Noise monitoring locations : 9
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))64.662.4475
(2.)Leq(Night)A-weighted decibels(dB(A))50.638.5675
    14.5.     No. of Soil Sample Monitored locations : 10
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pH8.147.54
(2.)P(Phosphorus)Kilogram per hectare44.6236.24
(3.)K(Potassium)Kilogram per hectare16288.64
(4.)N(Nitrogen)Kilogram per hectare0.080.0.64
(5.)Electric ConductivityMillisiemens per Centimetre410290
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 15 To 18
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 10 To 12
(c)Whether Ground Water Intersection will be there ? NA
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater406Copy of Permission LettermodeOthersWater TankerOthersBore wellCGWA/NOC/MIN/ORIG/2019/587614 Aug 201940
(2.)Surface7101Copy of Permission LettermodeOthersWater TankerOthersby Water pumpsCGWA/NOC/MIN/ORIG/2019/587614 Aug 2019770
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Service Facilities101000septic tankOthersReuse for Mining porpose100
(2.)HEMM washing and workshop451000Septic TankOtherswashing the machinery450
(3.)CHP and coal stock pile1501000Septic TankOthersReuse to develop the green belt area1500
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 205
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 205
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Mine wasteOthersOver burden40.65Tons0OthersdumperOthersOB will be back filled in pit
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM2.5Microgram per Meter Cube26.2654.931.1760
(2.)PM10Microgram per Meter Cube44.28516.460.70100
(3.)SO2Microgram per Meter Cube9.9251.2311.1680
(4.)NOxMicrogram per Meter Cube15.1452.1317.2880
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)0000PM100
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 1000
(b)Source Jharkhand State Electricity board
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 0
(e)Stack Height (in m) 0
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 162.39
(b)Private Land (ha.) 235.24
(c)Government Land (ha.) 62.37
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 460
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 112.98
(b)Waste/Barren Land (ha.) 21.21
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 73.06
(e)Settlements (ha.) 24.23
(f)Industrial (ha.) 0
(g)Forest (ha.) 186.7
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : Fallow land 41.82
    Total (ha.) 460
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Green belt63
(2.)Othersroad, undistubed area , area excavated397
Total (ha.) 460
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)WLS000
(2.)Corridors000
(3.)Critically Polluted Area000
(4.)NPA000
(5.)ESAsNA00
(6.)ESZsNA00
(7.)Wildlife CorridorsNA00
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestTubed RF0.23NW direction
(2.)Othersp.fMangra PF0.12SSE direction
(3.)Archaeological SitesBishrampur PF0.21SW direction
(4.)Defence InstallationsUbar PF2.5SSW direction
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? Yes
(a)Forests Clearance Status Application for Forest Clearance yet to be submitted
(b)Legal Status of Forest Land Protected
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 460
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired 0
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 6
(b)No. of Households 164
(c)No. of PDFs (Project Displaced Families) 201
(d)No. of PAFs (Project Affected Families) 418
(e)Funds Allocated for R&R(in INR) (in Lacs) 3543
(f)Status of R&R Yet To Start
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? Yes
(i)Uploaded copy of conservation plan Copy of conservation plan
(ii)Fund Provision made 650 LAKHS
(iii)Period of Implementation 10
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? Yes
(i)Uploaded copy of approval Copy of approval
(ii)Letter No. 911
(iii)Date of issue 23 May 2018
(iv)Recommendation 0
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? Yes
(i)Details of Water Bodies in Core Area Sukri River
(b)Whether there is Diversion Required ? Yes
(i)Details of Diversion Required A river named sukri is a tributary of auranga flows in western direction and passes through the tubed coal block.
(ii)Details of Study Conducted Assessment study for diversion of river Sukri pass
(c)Whether permission has been obtained from competent authority ? Yes
(i)Uploaded copy of permission Copy of permission
(ii)Letter No. SE/canal/304/plan/2019/1045
(iii)Date of issue 13 Nov 2019
(iv)Recommendation The diversion plan has been accepted ‘In principal
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Bhugbhug nala Ekchatia nala Bhaimanda nala
(ii)Direction of Water Bodies in Buffer Area West
(iii)Distance of Water Bodies in Buffer Area 6.2
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 800
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 400
(e)No. of working days 330
(f)Total Manpower 1200
32.
Green Belt in Ha:
(a)Total Area of Green Belt 427.67
(b)Percentage of Total Project Area 92.97
(c)No. of Plants to be Planted 684272
(d)Funds Allocated for Plantation 23318160
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialIt becomes important for the region to operate the mine to generate employment opportunities for local people and improves livelihood as well as lifestyle of people. Besides this, the project of Tubed Coal Mine by M/s Damodar Valley Corporation will prove beneficial in terms of socio-economic development as it will provide employment to locals. Further, the average income level, which is the indicator of socio – economic status of households is expected to increase, which will result in better s
(2.)FinancialCoal is one of the major mineral deposits occurring in the Indian sub-continent. It has played a great role in development of civilization and industrialization. The occurrence of coal in proposed area is proved by the way of exploration and its production has important role in the local industries
(3.)EnvironmentalThe environment management plan is prepared with a view to facilitate effective environmental management of the project, in general and implementation of the mitigation measures in particular. The EMP provides a delivery mechanism to address potential adverse impacts and to introduce standards of good practice to be adopted for all project works.
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For Coal Mining
S. No.Item Details
     1.       No. of Mineral(s) to be Mined : 1
S. No.Mineral(s) to be Mined Major or Minor Mineral
(1.)COALMajor
2.
Mine Capacity in ROM (Run of Mine) 6.0 Million TPA
3.
Uploaded 500 meters Cluster Certificate from State Mines and Geology in case of minor minerals Copy of 500 meters Cluster Certificate from State Mines and Geology
4.
Mining Plan:
(a)Approval Letter No. No.13016/19/2009-CA-I
(b)Date of Approval 12 Oct 2009
(c)Approved Letter Copy of Approved Letter
(d)Approved By State Mining and Geology Department Coal
(e)Approved Mining Lease Area 460
(f)Approved Capacity 6000000
5.
Technical Details:
(a)Total Geological Reserves (Million Ton) 189.82
(b)Mineable Reserves (Million Ton) 170.83
(c)Extractable Reserves(Million Ton) 139.65
(d)Percent(%) of Extraction 0.81
(e)Grade of Coal /Ore /Mineral F
(f)Stripping Ratio 2.15m3 : 1 T
(g)Category of Gaseousness (Only for Coal Mining, Others may Write NA) NA
(h)Average Gradient(Degree) 1 in 9
(i)Mining Method Opencast
(j)Life of Mine (Years) 30
6.
Details of Beneficiations:
(a)Whether it is proposed to install beneficiation plant/Coal washery within the mining lease area No
(b)Whether it is proposed to install crusher within the mining lease area No
7.
Details of Seams:
(a)Whether details of seam applicable Yes
(b)No. of seams 12
(c)Thickness of seams to be worked on 12
(d)Maximum Thickness of Seams (metres) NA
8.
Details of Mining Lease:
(a)Mining Lease Area (in Hectare) 460
(b)Whether obtained Letter of Intent (LOI) from the state government ? Yes
(i)Copy of Letter of Intent Copy of Letter of Intent
(ii)Date of issue of LOI 07 Oct 2016
(iii)Validity of LOI 30
(iv)Reference No. of LOI 103/04/2016/NA
(c)Whether Lease Deed Executed ? Yes
(i)Copy of Executed Lease deed valid as on Date Copy of Executed Lease deed
(ii)Provide area in Hectare as per executed lease deed (initial) document 460
(iii)Validity of the lease deed From : 07 Oct 2016 To : 06 Oct 2046
(iv)Date of Execution of Mining Lese 28 Aug 2018
(v)Reference Number F. No. 43015/34/2017–LA & IR
(d)Whether Lease Deed Renewed ? No
(i)Reason thereof land acquisition done under CBA act 1957
9.
OB (Over Burden) Management:
(a) Details of External Dumps:
(i)No. of OB Dumps
(ii)Total Area (in Hectare)
(iii)Height (in meter)
(iv)Quantity (in Million Cubic meter)
(v)No. of year back fill up
(b) Details of Internal Dumps:
(i)No. of Internal Dumps
(ii)Total Area (in Hectare)
(iii)Height (in meter)
(iv)Quantity (in Million Cubic meter)
10.
Details of Topsoil Management:
(a)Quantity of Topsoil excavated during the entire life of the mine (in Million Cubic metre) 0.5
(b)Quantity of Topsoil proposed for utilization for reclamation during the entire life of the mine (in Million Cubic metre) 0.5
(c)Quantity of Topsoil proposed for utilization for other activities during the entire life of the mine (in Million Cubic metre) 0
11.
Details of Final Mine Void:
(a)Area (in Hectare)
(b)Depth (in meter)
(c)Volume (in Million Cubic meter)
12.
Details of Quarry:
(a)Final Void of 4 (hectare) at a Depth of 40 meter which is Proposed to be Converted into a Water Body.
(b)Total Quarry Area (ha) 350
13.
Details of Transportation:
(a)In Pit/Underground to Surface By Dumper
(b)Surface to Siding/Loading By Dumper
(c)Transportation / Conveyor Details Transport by Road upto nearest available Railway s
     14.      Details of Land Usage (Pre-Mining)
S. No.LAND USE Other LAND USEWITHIN ML AREA (Hectare)OUTSIDE ML AREA (Hectare)TOTAL (Hectare)
(1.)AGRICULTURE LAND235.240235.24
(2.)WASTE LAND62.37062.37
(3.)GRAZING LAND000
(4.)SETTLEMENTS000
(5.)FOREST LAND162.390162.39
(6.)SURFACE WATER BODIES000
TOTAL4600460
     15.      Details of Land Usage (Post-Mining)
S. No.LAND USE Other LAND USEPlantation (ha)Water Body (ha)Public Use (ha)Undisturbed (ha)Total
(1.)EXCAVATION/QUARRY330128350
(2.)ROADS3047
(3.)VIRGIN AREA0000
(4.)Othersafety zone160016
(5.)TOP SOIL STORAGE0000
(6.)BUILT UP AREA (COLONY/OFFICE)70310
(7.)INTERNAL OB DUMPS0000
(8.)EXTERNAL OB DUMPS630063
(9.)GREEN BELT410014
TOTAL42322150460
16.
Details of Reclamation:
Total Afforestation Plan shall be Implemented Covering of Mining.
This will Include:
(a)External OB Dump(in hectare) 30
(b)Internal Dump(in hectare) 350
(c)Quarry(in hectare) 350
(d)Safety Zone(in hectare) 16
(e)Final Void of 4 (hectare) at a Depth of 40 meter which is Proposed to be Converted into a Water Body.
(f)Density of Tree Plantation per ha (in no.) 1600
(g)Others in ha (such as Excavation Area along ML Boundary, along Roads and Infrastructure, Embankment Area and in Township Located Outside the Lease etc) 0
(h)Total afforestation plant (in hectare) 427.67
17.
Status of progressive Mining Closure Plan:
Details Not Applicable
     18.      Details of Actual Coal/ ORE Production vis-a-vis Sanctioned Capacity since the Inception:
S. No.Financial Year Sanctioned Capacity as per EC (MTPA)Sanctioned Capacity as per CTOSanctioned Capacity as per approved mining planActual Production Excess Production Beyond the EC / CTO/ Mining Plan Sanctioned Capacity (MTPA)
(1.)000000
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1720/RA 0091
(ii)Name of the EIA Consultant Overseas Min-Tech Consultants
(iii)Address 501, 5th Floor, apex tower, Tonk road, Jaipur
(iv)Mobile No. 9460221084
(v)Landline No. 0141274450
(vi)Email Id arun.omtc@gmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Coal Mining
(ix)Validity of Accreditation 31 Jul 2020
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAPls clarify and comments on the following a. status for forest land of 162.39as in form-2 - it is written as FC yet to be applied b. Kindly provide list of attendees with signature during PH and advertisement deatils in english newspaper c. QCI Accredition certificate of EIA/EMP Consultant d. Conservation plan for schedule-I species has no clarity (not properly visible). Kindly provide the conservation plan report with approval letter with clarity e. River passing through the coal block- Any plan for diversion and approval for the same (if any)- what is the distant from quarry and OB dump f. In Form-2 Sr. 21- details of total land is not similar (as mentioned in EIA report). pls correct g. In Form-2 Details of OB , Final mine void, are not filled h. Mine Plan is approved for M/s Tubed coal mine limited not M/s DVC. Pls justify i. permission from ground water authority for extraction of ground water 21 Nov 2019
2.NAThe correction have been made as per the instruction received 28 Nov 2019
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantDamodar Valley Corporation
DesignationFerm
Name of Company (Applicant Name should not be given here)MS DAMODAR VALLEY CORPORATION
AddressD.V.C. Tower,V.I.P Road, Kolkata
Print