Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) ‘Lakhpat Cement Works’ (An Integrated Cement Project - Cement Plant Clinkerization Plant,each of 10 MTPA production capacity with Captive Power Plant of 99MW, Limestone Mine for 12MTPA with lease are
(b)Name of the Company / Organisation ADANI CEMENTATION LIMITED
(c)Registered Address Adani House, 56 Srimali Society, Navrangpura,Ahmedabad,Ahmedabad,Gujarat-380009
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Sanjay Prasad
(b)Designation (Owner/ Partner/ CEO) AGM
(c)Address Adani Cementation Limited, Ground Floor, South Wing, Adani Coporate House,Shantigram, S.G. Highway, Ahmedabad,,Ahmedabad,Gujarat-382421
(d)Pin code 382421
(e)E-mail sanjay.prasad@adani.com
(f)STD Code. 79(f)Telephone No. 25558623
(g)Fax No. 07925557401
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity1(a) Mining of minerals
Minor Activity
(b)Category A
(c)Proposal Number IA/GJ/MIN/70787/2017
(d)Master Proposal Number(Single Window) SW/121094/2019
(e)EAC concerned (for category A Projects only) Non-Coal Mining
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Pvt. Land: 8P/1, 8P/2, 8P/9, 18P/3, 26P/7, 26P/8,
(b)Pincode 370627
(c)Bounded Latitudes (North)
From
Degree 2622387.757
Minutes
Second
From
Degree 2624886.005
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 469188.168
Minutes
Second
From
Degree 470578.944
Minutes
Second
(e)Survey of India Topo Sheet No. 41A/10
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 27
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 5
(j)Seismic Zone 5
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Gujarat
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)GujaratkutchLakhpat
(2.)Madhya PradeshChhindwaraSausarKhapakarimwar
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number IA-J-11015/121/2017-IA-II(M)
(b)Date of Apply of TOR 12 Nov 2017
(c)Date of Issue of TOR / Standard ToR 09 Jan 2018
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :22 Apr 2019
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :28 May 2019
Distance of Public Hearing Venue from the Proposed Project :2
Village Koriyani
State :Gujarat
District :kutch
Tehsil :Lakhpat
Village :Koriyani
553Related to public health, hospital facility, women empowerment, problem of air pollution and water pollution and employment and land compensationDistrict Collector
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Limestone MineProduction 12MTPA and Area 251.9 haLimestone Mining
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Limestone12OthersMTPAConveyor Belt
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 7525
(b) Funds Allocated for Environment Management (Capital) (in Crores) 107
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 46
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 12
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 0
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 0
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)NA0OthersNANAOthersNA0 OthersNACopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Dec 2017 To 28 Feb 2018
(b)Season Winter
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 9
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM2.5Micro Gram per Meter Cube32.920.232.960
(2.)PM10Micro Gram per Meter Cube75.257.475.1100
(3.)SO2Micro Gram per Meter Cube18.85.318.780
(4.)NOxMicro Gram per Meter Cube19.97.119.980
(5.)OthersCOMili Gram per Meter Cube0.850.480.852
    14.2.     No. of Ground Water monitoring locations : 7
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)TSSNA0000
(2.)Chloridesmg/l5482532501000
(3.)pHNA7.47.16.58.5
(4.)Total Hardnessmg/l600.6309.7300600
(5.)Fluoridemg/l0.480.2911.5
(6.)TDSmg/l15708305002000
    14.3.     No. of Surface Water monitoring locations : 6
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)DOmg/l6.44.3C
(2.)BODmg/l2.40.8C
(3.)pHNA8.17.5C
(4.)CODmg/l38.420.3C
    14.4.     No. of Ambient Noise monitoring locations : 9
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))50.441.465
(2.)Leq(Night)A-weighted decibels(dB(A))42.932.755
    14.5.     No. of Soil Sample Monitored locations : 8
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pH7.847.34
(2.)Electric ConductivityOthersmicrosiemens per Centimeter985732
(3.)P(Phosphorus)Kilogram per hectare42.321.8
(4.)K(Potassium)Kilogram per hectare79.548.2
(5.)N(Nitrogen)Kilogram per hectare14587
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 10 To 5
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 10 To 5
(c)Whether Ground Water Intersection will be there ? Yes
(d)Upload Copy of Central Ground Water Authority Letter Copy of Central Ground Water Authority Letter
(e)Letter No. CGWA/NOC/MIN/ORIG/2019/5864
(f)Date of Issue 13 Aug 2019
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)Sea25012Copy of Permission LetterPipelineIntake Well126 Nov 201830000
15.1.
(a)Whether Desalination is proposed Yes
(b)Desalination Capacity (KLD) 9000
(c)Quantity of Brine (KLD) 21000
(d)Mode of Disposal of Brine Brine would return to the designated outfall point
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic use1515MBBR TechnologyGreen Belt Renewal Plant15
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 15
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 15
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)OverburdenOthersOverburden3000000Tons2OthersBy road within mining lease areaOthersConcurrent Reclamation
(2.)Top SoilOthersTop Soil48000Tons2OthersBy road within mining lease areaOthersFor afforestation
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM2.5Microgram per Meter Cube0000.00160
(2.)PM10Microgram per Meter Cube64.70108.6173.4100
(3.)NOxMicrogram per Meter Cube0000.00180
(4.)SO2Microgram per Meter Cube0000.00180
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)NANA00OthersNA0
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 1000
(b)Source Captive Power Plant/ Grid Power from Dayapar
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) Not Required
(e)Stack Height (in m) 0
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 91.2762
(c)Government Land (ha.) 160.6238
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 251.9
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 8794.58
(b)Waste/Barren Land (ha.) 5400.67
(c)Grazing/ Community Land (ha.) 18835.90
(d)Surface Water Bodies (ha.) 11401.96
(e)Settlements (ha.) 434.39
(f)Industrial (ha.) 95.25
(g)Forest (ha.) 3332.33
(h)Mangroves (ha.) 1493.24
(i)Marine Area (ha.) 769.30
(j)Others (ha.) : Mining Activities, sandy area and mud land 12873.78
    Total (ha.) 63431.4
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)OthersLimestone Mining251.9Mining of Limestone
Total (ha.) 251.9
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)WLSNarayan Sarovar Wildlife Sanctuary3.4South from Mining Lease Area
(2.)Critically Polluted AreaNA0NA
(3.)NPANA0NA
(4.)Wildlife CorridorsNA0NA
(5.)CorridorsNA0NA
(6.)ESAsNA0NA
(7.)ESZsESZ of Narayan Sarovar Wildlife Sanctuary2.4South from Mining Lease Area
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)OthersWaterbodyKapurasi Nadi2Direction- W
(2.)Archaeological SitesLakhpat Fort12.2Towards NE beyond 10Km from Mining Block
(3.)ForestMudhvay RF0.05Direction- S & E
(4.)Defence InstallationsBSF Camp9.0West of Mining Lease Area
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? Yes
(a)Forests Clearance Status Application for Forest Clearance yet to be submitted
(b)Legal Status of Forest Land Not in Mining Lease Area
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 512
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 23
(b)Land yet to be acquired(Ha) 228.9
(c)Status of Land acquisition if not acquired Government land acquisition is under process at Co
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 3
(b)No. of Households 131
(c)No. of PDFs (Project Displaced Families) 17
(d)No. of PAFs (Project Affected Families) 154
(e)Funds Allocated for R&R(in INR) (in Lacs) 992.863
(f)Status of R&R In-Progress
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? Yes
(i)Details of Schedule-I Species Black shoulder kite, Indian Peafowl, Montagu's Harrier, Pallid Harrier and Shikra
(b)Whether conservation plan for Schedule-I Species has been prepared ? Yes
(i)Uploaded copy of conservation plan Copy of conservation plan
(ii)Fund Provision made 5.25 crore
(iii)Period of Implementation 10 years
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Kapurasi Nadi
(ii)Direction of Water Bodies in Buffer Area West
(iii)Distance of Water Bodies in Buffer Area 5
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 30
(b)Permanent Employment-During Operation 150
(c)Temporary Employment- During Construction 600
(d)Temporary Employment- During Operation 450
(e)No. of working days 300
(f)Total Manpower 1230
32.
Green Belt in Ha:
(a)Total Area of Green Belt 83.5
(b)Percentage of Total Project Area 33.15
(c)No. of Plants to be Planted 125250
(d)Funds Allocated for Plantation 140000000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)EnvironmentalAt the conceptual stage, out of the total mining lease area (i.e. 251.9 ha), total mined-out area will be 163.5 ha which will be reclaimed & rehabilitated by converting into water reservoir. At end of life of mine, about, 83.5 ha area will be under greenbelt & plantation which will be beneficial to the environment & will provide an aesthetic look. Hence conceptual land use will be better than present land use. The water reservoir will be helpful for recharge of ground water. About 64 ha. Sparse
(2.)FinancialThe project has positive employment and income effects, both direct as well as indirect. Manpower is required for mining operations, plant operations, jetty operations and manning of ships as well as other related activities such as transportation for day to day operations etc. The impact of the project on the economic aspects can be clearly observed.
(3.)SocialThe company has undertaken and will continue undertake activities for the upliftment of the social community through community development. The CSR (Adani Foundation) arm operates in four chosen areas of Education, Healthcare, Rural Infrastructure and Sustainable Livelihood to bring about progress and prosperity in the communities we impact
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For Non-Coal Mining
S. No.Item Details
     1.       No. of Mineral(s) to be Mined : 1
S. No.Mineral(s) to be Mined Major or Minor Mineral
(1.)LimestoneMajor
2.
Mine Capacity in ROM (Run of Mine) 12 MTPA
3.
Uploaded 500 meters Cluster Certificate from State Mines and Geology in case of minor minerals Copy of 500 meters Cluster Certificate from State Mines and Geology
4.
Mining Plan:
(a)Approval Letter No. 684 (4)(1)/MP-84
(b)Date of Approval 03 Jan 2018
(c)Approved Letter Copy of Approved Letter
(d)Approved By State Mining and Geology Department IBM
(e)Approved Mining Lease Area 251.9
(f)Approved Capacity 12
5.
Technical Details:
(a)Total Geological Reserves (Million Ton) 292.5
(b)Mineable Reserves (Million Ton) 101.763
(c)Extractable Reserves(Million Ton) 101.763
(d)Percent(%) of Extraction 100
(e)Grade of Coal /Ore /Mineral Cement Grade Limestone
(f)Stripping Ratio 1 : 0.42
(g)Category of Gaseousness (Only for Coal Mining, Others may Write NA) NA
(h)Average Gradient(Degree) NA
(i)Mining Method Opencast
(j)Life of Mine (Years) 15
6.
Details of Beneficiations:
(a)Whether it is proposed to install beneficiation plant/Coal washery within the mining lease area No
(b)Whether it is proposed to install crusher within the mining lease area No
7.
Details of Seams:
(a)Whether details of seam applicable No
8.
Details of Mining Lease:
(a)Mining Lease Area (in Hectare) 251.9
(b)Whether obtained Letter of Intent (LOI) from the state government ? Yes
(i)Copy of Letter of Intent Copy of Letter of Intent
(ii)Date of issue of LOI 21 Jun 2017
(iii)Validity of LOI 3
(iv)Reference No. of LOI MCR-102016-2146-CHH
(c)Whether Lease Deed Executed ? No
(i)Reason thereof New Project
(d)Whether Lease Deed Renewed ? No
(i)Reason thereof New Project
9.
OB (Over Burden) Management:
(a) Details of External Dumps:
(i)No. of OB Dumps 0
(ii)Total Area (in Hectare) 0
(iii)Height (in meter) 0
(iv)Quantity (in Million Cubic meter) 0
(v)No. of year back fill up 0
(b) Details of Internal Dumps:
(i)No. of Internal Dumps 0
(ii)Total Area (in Hectare) 0
(iii)Height (in meter) 0
(iv)Quantity (in Million Cubic meter) 0
10.
Details of Topsoil Management:
(a)Quantity of Topsoil excavated during the entire life of the mine (in Million Cubic metre) 0.32
(b)Quantity of Topsoil proposed for utilization for reclamation during the entire life of the mine (in Million Cubic metre) 0.32
(c)Quantity of Topsoil proposed for utilization for other activities during the entire life of the mine (in Million Cubic metre) 0
11.
Details of Final Mine Void:
(a)Area (in Hectare) 0
(b)Depth (in meter) 0
(c)Volume (in Million Cubic meter) 0
12.
Details of Quarry:
(a)Final Void of 112.3 (hectare) at a Depth of 57 meter which is Proposed to be Converted into a Water Body.
(b)Total Quarry Area (ha) 112.3
13.
Details of Transportation:
(a)In Pit/Underground to Surface Haul Road within Pit area
(b)Surface to Siding/Loading Tipper/Dumpers
(c)Transportation / Conveyor Details Surface Belt Conveyor from mine to Cement Plant
     14.      Details of Land Usage (Pre-Mining)
S. No.LAND USE Other LAND USEWITHIN ML AREA (Hectare)OUTSIDE ML AREA (Hectare)TOTAL (Hectare)
(1.)WASTE LAND160.62380160.6238
(2.)SURFACE WATER BODIES000
(3.)GRAZING LAND000
(4.)SETTLEMENTS000
(5.)OTHERS(Specify)Santhani Land91.2762091.2762
(6.)FOREST LAND000
(7.)AGRICULTURE LAND000
TOTAL251.90251.9
     15.      Details of Land Usage (Post-Mining)
S. No.LAND USE Other LAND USEPlantation (ha)Water Body (ha)Public Use (ha)Undisturbed (ha)Total
(1.)EXCAVATION/QUARRY78.533.80112.3
(2.)INTERNAL OB DUMPS0000
(3.)VIRGIN AREA0000
(4.)ROADS0066
(5.)OtherUndisturbed area00128.5128.5
(6.)TOP SOIL STORAGE0000
(7.)EXTERNAL OB DUMPS0000
(8.)BUILT UP AREA (COLONY/OFFICE)000.10.1
(9.)GREEN BELT5005
TOTAL83.533.8134.60251.9
16.
Details of Reclamation:
Total Afforestation Plan shall be Implemented Covering of Mining.
This will Include:
(a)External OB Dump(in hectare) 0
(b)Internal Dump(in hectare) 0
(c)Quarry(in hectare) 112.3
(d)Safety Zone(in hectare) 5
(e)Final Void of 33.8 (hectare) at a Depth of 30 meter which is Proposed to be Converted into a Water Body.
(f)Density of Tree Plantation per ha (in no.) 1000
(g)Others in ha (such as Excavation Area along ML Boundary, along Roads and Infrastructure, Embankment Area and in Township Located Outside the Lease etc) 0
(h)Total afforestation plant (in hectare) 83.5
17.
Status of progressive Mining Closure Plan:
Details Not Applicable
     18.      Details of Actual Coal/ ORE Production vis-a-vis Sanctioned Capacity since the Inception:
S. No.Financial Year Sanctioned Capacity as per EC (MTPA)Sanctioned Capacity as per CTOSanctioned Capacity as per approved mining planActual Production Excess Production Beyond the EC / CTO/ Mining Plan Sanctioned Capacity (MTPA)
(1.)000000
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1619/RA 0058
(ii)Name of the EIA Consultant Greencindia Consulting Private Limited
(iii)Address 608-611, Shopprix Mall, Sector-5, Vaishali, National Capital Region, Ghaziabad- 201010 (U.P.)
(iv)Mobile No. 9891906015
(v)Landline No. 0120429653
(vi)Email Id information@greencindia.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Non-Coal Mining
(ix)Validity of Accreditation 27 Oct 2019
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NA1. Form-2 is not properly filled 2. Whether mine lease area consist of forest land. 3. Public hearing also completed integrated plant. 4. Mining plan not uploaded 5. Copy of accreditation certificate for consultant. 6. Letter of authorization/power of attorney for the project. 7. Validity of mine lease and copy of valid lease document 8. Copy of affidavit needs to be submitted by PP in compliance of the Ministry’s OM no. 3-50/2017-IA.III (Pt.), dated 30th May 2018 9. Past production details duly authenticated by State mines and Geology 10. Status of mine whether working or not. 11. Copy of Previous EC documents, if any 08 Nov 2019
2.NAThe correction have been made as per the instruction received 12 Dec 2019
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1. ADS Reply LetterPoint wise reply to the requisite information raised by MoEFCC vide letter no. J-11015/121/2017-IA.II dated 6th March 2020 with respect to proposal no. IA/GJ/MIN/70787/2017 and ADS raised by MOEFCC dated 25.04.2020 Kindly consider the proposal for appraisal to recommend Environment Clearance at earliest. 30 Apr 2020
2.NA

deferred

25 Apr 2020
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantSanjay Prasad
DesignationAGM
Name of Company (Applicant Name should not be given here)ADANI CEMENTATION LIMITED
AddressAdani House, 56 Srimali Society, Navrangpura
Print