Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Proposed Expansion of pesticide specific intermediate and synthetic organic chemicals manufacturing Facility by Deepak Nitrite Limited Plot No 1 to 8, 26 to 34, MIDC Roha, Dist Raigad, Maharashtra.
(b)Name of the Company / Organisation DEEPAK NITRITE LTD
(c)Registered Address Plot No.1-8, 26-34, MIDC Dhatav, Tal Roha, Dist. Raigad,,Raigad,Maharashtra-402116
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Sunil Desai
(b)Designation (Owner/ Partner/ CEO) SiteHeadOperation
(c)Address Plot No.1-8, 26-34, MIDC Dhatav, Tal Roha, Dist. Raigad,,Roha,Raigad,Maharashtra-402116
(d)Pin code 402116
(e)E-mail gadeshpande@godeepak.com
(f)STD Code. 2194(f)Telephone No. 263550
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity5(b) Pesticides industry and pesticide specific intermediates (excluding formulations)
Minor Activity5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
(b)Category A
(c)Proposal Number IA/MH/IND2/63448/2016
(d)Master Proposal Number(Single Window) SW/120778/2019
(e)EAC concerned (for category A Projects only) Industrial Projects - 2
(f)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Plot No 1-8, 26-34
(b)Pincode 402116
(c)Bounded Latitudes (North)
From
Degree 18.25
Minutes
Second
From
Degree 18.25
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 73.9
Minutes
Second
From
Degree 73.9
Minutes
Second
(e)Survey of India Topo Sheet No. E43H2 E43H3
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 12
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 1
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Maharashtra
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)MaharashtraRaigadRoha
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number J- 11011/363/2016-IA.II(I)
(c)Date of Issue of TOR 28 Feb 2017
(f)Previous TOR Letter Copy of Previous TOR letter
(b)Date of Apply of EC 27 Apr 2017
(c)Date of Issue of EC 03 Jan 2018
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason project within notified industrial area
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Nagpur
(iii)Letter No. EC-696/RON/2018-NGP/5722
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit Sep 5 2019 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)2,3NXL or 2,4NXL or 3,4NXL or 2,6NXL013301330OthersTon per monthRoad
(2.)PNC or PC or ONC or OC0300300OthersTon per monthRoad
(3.)2ABTF or 3ABTF or 2NBTF or 3NBTF or 4NBTF0400400OthersTon per monthRoad
(4.)OA or TMHQ0100100OthersTon per monthRoad
(5.)Aniline01010OthersTon per monthRoad
(6.)sodium acetate0150150OthersTon per monthRoad
(7.)CMAA05050OthersTon per monthRoad
(8.)3 AAP04848OthersTon per monthRoad
(9.)CL BTF or OHBTF or OA BTF02525OthersTon per monthRoad
(10.)2,3 or 2,4 or 2,5 Xylenol0120120OthersTon per monthRoad
(11.)OT04646OthersTon per monthRoad
(12.)Adenine or PMPA or S alcohol or DBTZ or TMP03030OthersTon per monthRoad
(13.)2- cyanophenol0150150OthersTon per monthRoad
(14.)PPO0150150OthersTon per monthRoad
(15.)PAR or MMDPA0100100OthersTon per monthRoad
(16.)3 NAP06060OthersTon per monthRoad
(17.)3 HAP03030OthersTon per monthRoad
(18.)2MePPDA or DBPPDA or 1,3 CHD0100100OthersTon per monthRoad
(19.)SMIA02525OthersTon per monthRoad
(20.)ChlorophenesinorMMePPDAor 2AFor MABFor NMBAor NMDO03030OthersTon per monthRoad
(21.)Pilot plant01010OthersTon per monthRoad
(22.)1,2,4 Triazinone or TCH or DCP0100100OthersTon per monthRoad
(23.)TFMAP0200200OthersTon per monthRoad
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)Reactors vessels tanks ColumnsyesyesyesNo
(2.)Cooling tower boiler TFHyesyesyesNo
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 01 Mar 2018
(iv)Valid Upto 30 Jun 2019
(v)File No. 1803000099
(vi)Application No. 31393
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 156
(b) Funds Allocated for Environment Management (Capital) (in Crores) 15
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 1.17
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 5.37
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 1
(b)Existing quantity of raw material/fuel 1
(c)Total quantity of raw material/fuel 2
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Methanol7525OthersTonnearbyRoad0 LinkageCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Mar 2019 To 31 May 2019
(b)Season Summer
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube79.261.278.7100
(2.)SO2Micro Gram per Meter Cube18.511.61880
(3.)OthersCOMili Gram per Meter Cube0.440.20.442
(4.)PM2.5Micro Gram per Meter Cube37.529.437.460
(5.)NOxMicro Gram per Meter Cube32.819.532.580
    14.2.     No. of Ground Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)Heavy MetalsManganesemg/l000.10.1
(2.)pHNA6.626.628.58.5
(3.)TSSmg/l0000
(4.)TDSmg/l9090500500
(5.)Fluoridemg/l0011
(6.)OthersCalciummg/l20207575
(7.)Total Hardnessmg/l7474200200
(8.)Chloridesmg/l2424150150
    14.3.     No. of Surface Water monitoring locations : 12
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)DOmg/l6.16.1E
(2.)pHNA7.567.56E
(3.)BODmg/l88E
(4.)CODmg/l00E
(5.)OthersTDSmg/l7070E
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))61.461.470
(2.)Leq(Day)A-weighted decibels(dB(A))67.167.175
    14.5.     No. of Soil Sample Monitored locations : 8
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)P(Phosphorus)Kilogram per hectare19.319.3
(2.)Electric ConductivityMillisiemens per Centimetre830.3830.3
(3.)pH7.17.1
(4.)N(Nitrogen)Kilogram per hectare10201020
(5.)K(Potassium)Kilogram per hectare8282
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 0.95 To 7.7
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 1.1 To 4.05
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)Othersfrom MIDC16470 Not Appliacble PipelineOthersfrom MIDC pipeline0007 Oct 20191164
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic, Process, washing, Utilities777880ETP, RO, MEE, stripperOtherspartly recycle and partly discharge530247
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 777
(b)Total Discharged Water (Kilolitre per Day) 247
(c)Total Reused Water (Kilolitre per Day) 530
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Insulation MaterialIndustrial Waste4Tons0RoadOthersSale to Authorized party
(2.)Iron Sludge/ Iron OxideHazardous Waste (as per Hazardous and Other Waste Management rules 2016)1488Tons0RoadOthersSale to Authorized party or TSDF
(3.)Charcoal SludgeHazardous Waste (as per Hazardous and Other Waste Management rules 2016)260Tons0RoadOthersSale to Authorized party or TSDF
(4.)Filter pad or bagHazardous Waste (as per Hazardous and Other Waste Management rules 2016)24Tons0RoadOthersSale to Authorized party
(5.)E wasteOthersE waste0.6Tons0RoadOthersSale to Authorized party
(6.)Distillation ResiduesHazardous Waste (as per Hazardous and Other Waste Management rules 2016)3922Tons0RoadOthersCoprocessing or TSDF
(7.)MEE saltsHazardous Waste (as per Hazardous and Other Waste Management rules 2016)564Tons0RoadTreatment, Storage and Disposal Facility(TSDF)
(8.)MS/SS scrapIndustrial Waste84Tons0RoadOthersSale to Authorized party
(9.)Boiler ashBottom Ash3630Tons0RoadOthersSale to Authorized party
(10.)Canteen wasteOtherscanteen waste8.4Tons0RoadOthersVermicomposting
(11.)Used/spent oilHazardous Waste (as per Hazardous and Other Waste Management rules 2016)116Tons0RoadAuthorized Recyclers
(12.)Wastes or residues containing oilHazardous Waste (as per Hazardous and Other Waste Management rules 2016)12Tons0RoadOthersAuth Recycler or CHWTSDF
(13.)Spent ChemicalsHazardous Waste (as per Hazardous and Other Waste Management rules 2016)1092Tons0RoadOtherssale to user
(14.)Sludge from wastewaterHazardous Waste (as per Hazardous and Other Waste Management rules 2016)4288Tons0RoadTreatment, Storage and Disposal Facility(TSDF)
(15.)Discarded containers/ barrels/ linersHazardous Waste (as per Hazardous and Other Waste Management rules 2016)1800Tons0RoadAuthorized Recyclers
(16.)Discarded containers/ barrels/ linersHazardous Waste (as per Hazardous and Other Waste Management rules 2016)1800Tons0RoadOthersrecycler
(17.)Discarded containers/ barrels/ linersHazardous Waste (as per Hazardous and Other Waste Management rules 2016)1800Tons0RoadOthersrecycler
(18.)Discarded containers/ barrels/ linersHazardous Waste (as per Hazardous and Other Waste Management rules 2016)1800Tons0RoadAuthorized Recyclers
(19.)Spent or Mix solventHazardous Waste (as per Hazardous and Other Waste Management rules 2016)2496Tons0RoadOthersSale to Authorized party
(20.)Lead acid batteryOthersE waste in nos20Tons0RoadOthersSale to Authorized party
(21.)Glass ware/ broken/discarded glassIndustrial Waste24Tons0RoadOthersSale to Authorized party
(22.)Discarded containers/ barrels/ linersHazardous Waste (as per Hazardous and Other Waste Management rules 2016)1800Tons0RoadOthersrecycler
(23.)Discarded containers/ barrels/ linersHazardous Waste (as per Hazardous and Other Waste Management rules 2016)1800Tons0RoadAuthorized Recyclers
(24.)ETP sludgeHazardous Waste (as per Hazardous and Other Waste Management rules 2016)1200Tons0RoadTreatment, Storage and Disposal Facility(TSDF)
(25.)Dilute Sulfuric AcidHazardous Waste (as per Hazardous and Other Waste Management rules 2016)35652Tons0RoadOtherssale to actual user
(26.)Wood, Paper, PVC, rubber, plastic etcIndustrial Waste84Tons0RoadOthersSale to Authorized party
(27.)Thermo pack AshBottom Ash24Tons0RoadOthersSale to Authorized party
(28.)Discarded containers/ barrels/ linersHazardous Waste (as per Hazardous and Other Waste Management rules 2016)1800Tons0RoadOthersrecycler
(29.)Spent CatalystHazardous Waste (as per Hazardous and Other Waste Management rules 2016)172Tons0RoadOthersSale to Authorized party or TSDF
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube71.31.90.4871.79100
(2.)PM2.5Microgram per Meter Cube37.51.9037.660
(3.)NOxMicrogram per Meter Cube26.11.92.5328.780
(4.)Others(Specify)CONA00010
(5.)SO2Microgram per Meter Cube15.31.94.2219.680
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)8 TPH Boiler & 6 Lakh Thermopackcoal 32.83 TPD341.2PM100
(2.)2 750 KVA DG & 1 500 KVA DGHSD 562 Lit/ Hr3.50.4PM100
(3.)2 DG set of 1000 KVA500 Lit/ Hr3.50.4PM100
(4.)4 Lakh kcal Hot oil unitFO 20.83 kg/Hr200.6PM100
(5.)20 TPH Boiler & 10 Lakh kcal ThermopackCoal 75 TPD361.25PM100
(6.)3 nos. of NOx, SOx & HCl scrubber each08.50.3PM100
(7.)8 TPH Boiler & 4 Lakh Hot oil unitcoal 4 TPD, FO 11.25 KLD24.51PM100
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 5000
(b)Source MSEDCL
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 2 nos. of 1000 KVA, 2 nos. of 750 KVA, 1 no. of 50
(e)Stack Height (in m) 8.5
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 3.4816
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 3.4816
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 1358.36
(b)Waste/Barren Land (ha.) 8850.2
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 367.54
(e)Settlements (ha.) 81.76
(f)Industrial (ha.) 216.19
(g)Forest (ha.) 2154.01
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : NA 0
    Total (ha.) 13028.060000000003
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Green belt0.3676
(2.)Main Plant3.114
(3.)OthersNA0
Total (ha.) 3.4816
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Wildlife CorridorsNA0NA
(2.)ESAsVillage Dhatav as per WG draft notification0NA
(3.)NPANA0NA
(4.)Critically Polluted AreaNA0NA
(5.)CorridorsNA0NA
(6.)WLSNA0NA
(7.)ESZsNA0NA
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Defence InstallationsNA0NA
(2.)OthersNANA0NA
(3.)ForestReserve forest1.5reserve forest
(4.)Archaeological SitesAvchitgad6.46notified
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 0
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired 0
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Kundalika river
(ii)Direction of Water Bodies in Buffer Area North
(iii)Distance of Water Bodies in Buffer Area 0.8
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 50
(c)Temporary Employment- During Construction 50
(d)Temporary Employment- During Operation 0
(e)No. of working days 6
(f)Total Manpower 100
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt00.36760.3676
(2.)No. of Plants100400500
(3.)Percentage of Total Project Area03333
(4.)Funds Allocated01010
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialSocial upliftment through CER
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1720/RA 0117 rev 01
(ii)Name of the EIA Consultant Aditya Environmental Services Pvt. Ltd
(iii)Address 107 Hiren Light Industrial estate Mumbai
(iv)Mobile No. 9821513367
(v)Landline No. 0224212750
(vi)Email Id rajiv@aespl.co.in
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 24 Nov 2020
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File NA
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
      Essential Detail Sought : NIL
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1. ADS Reply LetterReply letter to ADS 17 Dec 2019
2.NA

The EAC, during deliberations noted that the project details mentioned in the EIA report were not consistent with that presented during the meeting. The EAC, after detailed deliberations has asked for clarification/inputs, in respect of the

10 Dec 2019
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantSunil Desai
DesignationSiteHeadOperation
Name of Company (Applicant Name should not be given here)DEEPAK NITRITE LTD
AddressPlot No.1-8, 26-34, MIDC Dhatav, Tal Roha, Dist. Raigad