Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Shirguppi Sugar Works Ltd.
(b)Name of the Company / Organisation M/S. SHIRAGUPPI SUGAR WORKS LIMITED
(c)Registered Address M/s Shiraguppi Sugar Works Ltd Kagwad village,Athani Tq.Belgaum Dist.karnataka,,Belgaum,Karnataka-590016
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Dr Ramesh P Doddannavar
(b)Designation (Owner/ Partner/ CEO) Managing Director
(c)Address M/s Shiraguppi Sugar works Ltd Doddannavar Trade links, Near Fort, Old Pune -Bangalore Road,,,Athni,Belgaum,Karnataka-590016
(d)Pin code 590016
(e)E-mail hra@sswlsugars.com
(f)STD Code. 0(f)Telephone No. 2461231
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity5(g) Distilleries
5(j) Sugar Industry
Minor Activity1(d) Thermal Power Plants
(b)Category A
(c)Proposal Number IA/KA/IND2/119111/2018
(d)Master Proposal Number(Single Window) SW/119109/2019
(e)EAC concerned (for category A Projects only) Industrial Projects - 2
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. S. No. 23/A, 36/1A,4A, 40/1, 40/2B, 48/2A+B, 48/1E
(b)Pincode 591223
(c)Bounded Latitudes (North)
From
Degree 164232.01
Minutes
Second
From
Degree 164251.99
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 744255.80
Minutes
Second
From
Degree 744324.74
Minutes
Second
(e)Survey of India Topo Sheet No. 47L9, 47L10, 47L13 & 47L14
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 560
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 2.6
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Karnataka
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number IA-J-11011/299/2018-IA-II(I)
(b)Date of Apply of TOR 05 Oct 2018
(c)Date of Issue of TOR / Standard ToR 09 Nov 2018
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :23 May 2019
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :24 Jun 2019
Distance of Public Hearing Venue from the Proposed Project :0.1
Industrial Site - S. No. 23/A, 36/1A,4A, 40/1, 40/2B, 48/2A+B, 48/1E+P+G+2A+2B, 49/1+2A/3, 49/2B+3A, 49/3B, 49/4, 50/1,2,3,4,5, 52/1+2A/1, 53/1+2+3, 54/1A, 54/2B & 54/1B+2A, Kagwad,
State :Karnataka
District :Belgaum
Tehsil :Athni
Village :Kagwad
104Employment to local people, grampanchayat taxOthersAdditional Deputy Commissioner & Additional District Magistrate
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Sugar Factory10000 TCDExpansion from 4000 TCD to 10000 TCD
(2.)Distillery120 KLPDEstablishment of molasses based distillery
(3.)Cogeneration60 MWExpansion from 15 MW to 60 MW
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Ethanol/RS/ENA3600OthersKL/MonthRoad
(2.)Pressmud12000OthersMT/MonthRoad
(3.)CO22850OthersMT/MonthOthersCyllinders
(4.)Sugar32700OthersMT/MonthRoad
(5.)Molasses12000OthersMT/MonthRoad
(6.)Bagasse90000OthersMT/MonthRoad
(7.)Electricity1800OthersMW/MonthOthersGrid
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 20 Mar 2017
(iv)Valid Upto 30 Jun 2021
(v)File No. AW-302308
(vi)Application No. e-outwardno 4470--20/03/2017
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 300
(b) Funds Allocated for Environment Management (Capital) (in Crores) 25.31
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 2.93
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 1.31
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? Yes
d)Inter-State boundaries and international boundaries Yes
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 0
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 0
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Sugar cane300000OthersMT/MonthNearby farmsRoad50 Open MarketCopy of Linkage
(2.)Sulphur200OthersMT/MonthLocal SupplierRoad25 OthersAgreementCopy of Linkage
(3.)Molasses13350OthersMT/MonthOwn sugar factory/ outside purchaseRoad25 CaptiveCopy of Linkage
(4.)Urea4OthersMT/Monthoutside purchaseRoad25 Open MarketCopy of Linkage
(5.)De-Foaming Oil12OthersMT/Monthoutside purchaseRoad25 Open MarketCopy of Linkage
(6.)Bagasse60480OthersMT/MonthOwn sugar factoryRoad0.5 CaptiveCopy of Linkage
(7.)Lime600OthersMT/MonthLocal vendorsRoad25 OthersAgreementCopy of Linkage
(8.)Yeast8OthersMT/Monthself propagatedRoad0.5 CaptiveCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Oct 2018 To 31 Dec 2018
(b)Season Post-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM2.5Micro Gram per Meter Cube31.114.526.560
(2.)PM10Micro Gram per Meter Cube68.251.462.45100
(3.)SO2Micro Gram per Meter Cube29.812.425.6480
(4.)NOxMicro Gram per Meter Cube38.425.435.280
(5.)OthersCOMili Gram per Meter Cube0.180.030.132 (8 Hr)
    14.2.     No. of Ground Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA7.77.46.58.5
(2.)TSSmg/l51.2824.57100100
(3.)Chloridesmg/l84.545.1250250
(4.)OthersBoronmg/l0.340.080.50.5
(5.)Fluoridemg/l1.350.5711
(6.)TDSmg/l625.1409500500
(7.)Total Hardnessmg/l443.6299.2200200
(8.)Heavy MetalsZincmg/l1.090.3455
    14.3.     No. of Surface Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA7.917.4A
(2.)BODmg/l21.939.0E
(3.)DOmg/l5.51.9E
(4.)CODmg/l44.9631E
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))66.637.370
(2.)Leq(Day)A-weighted decibels(dB(A))685275
    14.5.     No. of Soil Sample Monitored locations : 8
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pH7.947.1
(2.)N(Nitrogen)Milligram per Kilogram374.60.015
(3.)Electric ConductivityMillisiemens per Centimetre168.4121.6
(4.)P(Phosphorus)Milligram per Kilogram571.611.24
(5.)K(Potassium)Milligram per Kilogram90.815.12
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 0.89 To 18.35
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 0.81 To 12.78
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)Surface3303Copy of Permission LetterPipelineJack WellBelgaum/ C2/17-18/376212 Sep 20174052
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Other effluent (Distillery)9911000Treated in proposed Condensate Polishing Unit (CPU)Reuse within the Plant & Recycling991
(2.)Domestic Effluent - Sugar, Cogen & Distillery2130In proposed STPReuse within the Plant & RecyclingUsed for flushing21
(3.)Raw Spentwash (Distillery)8951000Concentrated in MEE & incineratedOthersConcentration followed by Incineration8950
(4.)Industrial effluent - Sugar & Cogen7511450Primary, secondary & tertiary treatmentOthersused for irrigation purpose7510
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 2658
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 2658
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Boiler Ash (Coal+Spentwash)Bottom Ash17160Tons0.5RoadOthersbrick/cement manufacturers
(2.)ETP sludgeIndustrial Waste126Tons0.5RoadOthersManure
(3.)Yeast SludgeIndustrial Waste8910Tons0.5RoadOthersManure
(4.)Boiler Ash (Bagasse)Industrial Waste9072Tons1Conveyor BeltOthersManure/brick manufacturers
(5.)CPU SludgeIndustrial Waste220Tons0.5RoadOthersManure
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube62.451.740.0362.481100
(2.)PM2.5Microgram per Meter Cube26.581.40.0126.59160
(3.)SO2Microgram per Meter Cube25.641.830.826.44180
(4.)NOxMicrogram per Meter Cube35.21.20.1335.33180
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)Proposed 100 TPH Boiler (sugar & cogen expansion)Bagasse-1008 MT/D903.3PM1065 micro gram/cubic meter
(2.)Proposed Incineration Boiler-40TPHCoal/Bagasse+Spent wash-75 MT/D+243 MT/D702.5SO2230 Kg/Hr
(3.)Existing 100 TPH BoilerBagasse-1008 MT/D (common stack will be provided)903.3PM1065 micro gram/cubic meter
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 20500
(b)Source Own Cogen Plant - 60 MW
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) Two DG Sets of 1010 KVA
(e)Stack Height (in m) 7
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 49.74
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 49.74
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 18020
(b)Waste/Barren Land (ha.) 10260
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 291
(e)Settlements (ha.) 910
(f)Industrial (ha.) 0
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : Grass land with open scrub 1934
    Total (ha.) 31415
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Built Up Area4.56
(2.)Green belt16.99Existing & proposed green belt
(3.)OthersOpen Space/ area28.17
Total (ha.) 49.72
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)WLSNot Applicable0There is no presence of WLS in 10Km radius of Project
(2.)ESZsNot Applicable0There is no presence of ESZ in 10Km radius of Project
(3.)Wildlife CorridorsNot Applicable0There is no presence of wildlife corridors in 10Km radius of Project
(4.)Critically Polluted AreaNot Applicable0There is no presence of CPA's in 10 Km radius of Project
(5.)CorridorsNot Applicable0There is no presence of Corridors in 10 Km radius of Project
(6.)NPANot Applicable0There is no presence of NPA's in 10Km radius of Project
(7.)ESAsNot Applicable0There is no presence of ESAs in 10Km radius of Project
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Defence InstallationsNot Applicable0There is no presence of defence installations in 10 Km radius of Project
(2.)ForestNot Applicable0There is no presence of forest land in 10 Km radius of Project
(3.)Archaeological SitesNot Applicable0There is no presence of notified archaeological sites in 10 Km radius of Project
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 49.47
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired 0
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? Yes
(i)Details of Schedule-I Species Marsh crocodile, Indian monitor lizard, Indian flap-shell turtle, Indian peafowl
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? Yes
(i)Details of Water Bodies in Core Area Krishna river - 3.1 Km
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? Yes
(i)Uploaded copy of permission Copy of permission
(ii)Letter No. Belgaum/C2/17-18/3762
(iii)Date of issue 12 Sep 2017
(iv)Recommendation NA
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? No
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 80
(b)Permanent Employment-During Operation 330
(c)Temporary Employment- During Construction 50
(d)Temporary Employment- During Operation 30
(e)No. of working days 330
(f)Total Manpower 490
32.
Green Belt in Ha:
(a)Total Area of Green Belt 16.69
(b)Percentage of Total Project Area 33.55
(c)No. of Plants to be Planted 20000
(d)Funds Allocated for Plantation 2500000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialIn order to run the existing and expansion projects, all about 490 nos. of skilled and unskilled workers would be employed. Out of these total workers, about 275 workers have already been hired from local areas. Local persons shall be given preference while appointing for expansion project
(2.)Environmental• Industry shall adopt the rain water harvesting systems that will improve the ground water table in surrounding area. • Augmentation of existing green belt and plantation of additional trees in the industrial area and its surrounding shall help in improving the aesthetic beauty of the surrounding environment giving a pleasant look and improvising the air quality. Also green belt will help in arresting dust emissions as well as noise.
(3.)Financial• Due to expansion, the frequency of the local transportation will increase in this area. This will help shorten the time reaching destination and utilize it for some fruitful productive work. After expansion of the industry, the industry will meet the national interest of economical growth through sustainable development, as alcohol has been a great source of revenue through excise duty levied by the Government.
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/ 1821/ RA 0135
(ii)Name of the EIA Consultant Equinox Environments India Pvt. Ltd.
(iii)Address F-11, Namdev Nest, 1160 B, E Ward, Sykes Extension, Opposite Kamla College, Kolhapur
(iv)Mobile No. 9657865122
(v)Landline No. 0231253123
(vi)Email Id projects@equinoxenvi.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 21 Oct 2021
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
      Essential Detail Sought : NIL
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantDr Ramesh P Doddannavar
DesignationManaging Director
Name of Company (Applicant Name should not be given here)M/S. SHIRAGUPPI SUGAR WORKS LIMITED
AddressM/s Shiraguppi Sugar Works Ltd Kagwad village,Athani Tq.Belgaum Dist.karnataka
Print