1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | Proposed Expansion Project for Manufacturing of Ethyl Chloride (From Ethyl Alcohol), Ethyl Chloride (From Mixed Solvent of Existing Process), Methyl Chloride (From Methyl Alcohol) & Hydroxy | (b)Name of the Company / Organisation | ASHA CELLULOSE PRIVATE LIMITED | (c)Registered Address | Asha House, 808/C, Dr. B.A. Road, Dadar T.T., Mumbai.,,Mumbai City,Maharashtra-400014 | (d)Legal Status of the Company | Private | (e)Joint Venture | No | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | K Srinivas | (b)Designation (Owner/ Partner/ CEO) | Director | (c)Address | S.No. 303/2, 302/P, 273/2, 275/1, Near Water Works, Abrama, Valsad.,,Valsad,Valsad,Gujarat-396001 | (d)Pin code | 396001 | (e)E-mail | srini@ashacel.com | (f)STD Code. | 2632(f)Telephone No. | 253665 | (g)Fax No. | 227019 | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a.I)Project/Activity | 5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
| Minor Activity | | (b)Category | A | (c)Proposal Number | IA/GJ/IND2/118582/2019 | (d)Master Proposal Number(Single Window) | SW/118568/2019 | (e)EAC concerned (for category A Projects only) | Industrial Projects - 2 | (f)Project Type | Expansion |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | S. No. 302/P, 303/2, 273/2, 275/1 | (b)Pincode | 396001 | (c)Bounded Latitudes (North) | | From | | Degree | 20.5924 | Minutes | | Second | | From | | Degree | 20.5956 | Minutes | | Second | | (d)Bounded Longitudes (East) | | From | | Degree | 72.9607 | Minutes | | Second | | From | | Degree | 72.9616 | Minutes | | Second | | (e)Survey of India Topo Sheet No. | F43S14 & F43T2 | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 18 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 1 | (j)Seismic Zone | 3 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Gujarat | |
|
|
Details of State(s) of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
(1.) | Maharashtra | Solapur | Mohol | Watwate | |
|
6. | Details of Terms of Reference (ToR)/EC: | (a)MoEF&CC / SEIAA File Number | J-11011/316/2011-IA II (I) | (c)Date of Issue of TOR | 18 Mar 2019 | (f)Previous TOR Letter | Copy of Previous TOR letter | (b)Date of Apply of EC | 11 Dec 2019 | (c)Date of Issue of EC | 23 Sep 2020 | (d)Previous EC Letter | Copy of Previous EC letter | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | No | (b)Whether details of Public Hearing available? | Yes | (c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above | Yes | |
|
7.1. Details of Public Hearing |
---|
|
S. No. | Details of Advertisement | Details of Public Hearing | Venue | Location Details | No. of People Attended | Issues Raised | Designation of Presiding Officer | Other Designation of Presiding Officer |
---|
(1.) | | Copy of Public Hearing : | Copy of Public Hearing | Date : | 20 Aug 2019 | Distance of Public Hearing Venue from the Proposed Project : | 1.25 |
| Shri Saurashtra Kadva Patidar Seva Samaj, Dharampur Chokdi, N.H. 48, Valsad, District - Valsad | State : | Gujarat | District : | Valsad | Tehsil : | Valsad | Village : | Abrama |
| 112 | Clarification regarding water usage and waste water disposal, issues regarding Air Emission | District Collector | | |
8. | Details of Project Configuration/Product: | Details Not Applicable | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | (a)Details of certified report on compliance of earlier environmental clearance condition | (i)Certified Compliance By | Regional | (ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on | Bhopal | (iii)Letter No. | 5-9/2016(ENV)/674 | (iv)Status of Compliance | Compiled | (v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) | Copy of Certified Compliance Report | (vi)Date of site visit | Sep 27 2018 12:00AM | (b)Details of Capacity Expansion | |
|
S. No. | Product/Activity (Capacity/Area) | Quantity From | Quantity To | Total | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | Ethyl Cellulose | 20 | 0 | 20 | Others | TPM | Road | | (2.) | Ethyl Chloride (from Alcohol) | 0 | 322 | 322 | Others | TPM | Road | | (3.) | Ethyl Cellulose (Solvent Process) | 31.72 | 0 | 31.72 | Others | TPM | Road | | (4.) | Methyl Chloride | 0 | 250 | 250 | Others | TPM | Road | | (5.) | Hydroxy Propyl Methyl Cellulose | 0 | 200 | 200 | Others | TPM | Road | | (6.) | Ethyl Cellulose Aqueous- Non plasticized | 20.124 | 0 | 20.124 | Others | TPM | Road | | (7.) | Ethyl Cellulose Aqueous Dispersion-Plasticized | 24.70 | 0 | 24.7 | Others | TPM | Road | | (8.) | Ethyl Chloride(From existing mix solvent) | 0 | 160 | 160 | Others | TPM | Road | | |
| (c)Details of Configuration | |
|
S. No. | Plant / Equipment / Facility | Existing Configuration | Proposed Configuration | Final configuration after expansion | Remarks |
---|
(1.) | Chilling plant, TR | 140 | 100 | 240 | | (2.) | Cooling Tower, TR | 400 | 300 | 700 | | (3.) | Steam Boiler (TPH) | 3 | 0 | 3 | | (4.) | Thermopak (lakhs k cal/h) | 0 | 6 | 6 | | (5.) | Hot Air Generator (lakhs k cal/h) | 0 | 6 | 6 | | (6.) | Steam Boiler(TPH) | 0 | 3.5 | 3.5 | | (7.) | Hot Air Generator (lakhs k cal/h) | 6 | 0 | 6 | | (8.) | Hot Air Generator (lakhs k cal/h) | 6 | 0 | 6 | | (9.) | D G set (kVA) | 110 | 0 | 110 | | (10.) | D G set (kVA) | 35 | 0 | 35 | | |
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | 12 Jul 2017 | (iv)Valid Upto | 31 Mar 2022 | (v)File No. | AWH-87084 | (vi)Application No. | 122307 | (vii)Copy of Consent to operate valid as on date | Copy of Consent to Operate | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in Crores) | 30.5427 | (b) Funds Allocated for Environment Management (Capital) (in Crores) | 4.025 | (c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) | 0.15 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) | 2.14 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | No | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 2571.12 | (b)Existing quantity of raw material/fuel | 420.18 | (c)Total quantity of raw material/fuel | 2991.2999999999997 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | Furnace Oil | 315 | Others | kg/h | Local Market | Road | | 10 | Linkage | | Copy of Linkage | (2.) | HSD Fuel | 60 | Others | kg/h | Local Market | Road | | 10 | Linkage | | Copy of Linkage | (3.) | Natural Gas | 515 | Others | SCM/h | Gujarat Gas Limited | Pipe Conveyor | | 100 | Linkage | | Copy of Linkage | (4.) | Coal as a Fuel for Boiler | 510 | Others | kg/h | Local Market | Road | | 10 | Linkage | | Copy of Linkage | (5.) | Other Raw material | 2991.3 | Others | Ton/M | Local Market | Road | | 10 | Linkage | | Copy of Linkage | (6.) | Caustic Flakes | 163.6 | Others | Ton/M | Local Market | Road | | 100 | Linkage | | Copy of Linkage | (7.) | Ethyl Chloride | 142.2 | Others | Ton/M | Local Market | Road | | 100 | Linkage | | Copy of Linkage | (8.) | Acetic Acid | 19.2 | Others | Ton/M | Local Market | Road | | 100 | Linkage | | Copy of Linkage | (9.) | Toluene | 13 | Others | Ton/M | Local Market | Road | | 100 | Linkage | | Copy of Linkage | (10.) | Plasticizer – Dibutyl Sebacate | 1.3 | Others | Ton/M | Local Market | Road | | 100 | Linkage | | Copy of Linkage | (11.) | Oleic Acid | 1.04 | Others | Ton/M | Local Market | Road | | 100 | Linkage | | Copy of Linkage | (12.) | Wood Pulp | 177.82 | Others | Ton/M | Local Market | Road | | 100 | Linkage | | Copy of Linkage | (13.) | Cetyl Alcohol Powder | 0.62 | Others | Ton/M | Local Market | Road | | 100 | Linkage | | Copy of Linkage | (14.) | LDO | 120 | Others | kg/h | Local Market | Road | | 10 | Linkage | | Copy of Linkage | (15.) | SDS | 6.24 | Others | Ton/M | Local Market | Road | | 100 | Linkage | | Copy of Linkage | (16.) | Sodium Lauryl Sulfate – Powder | 0.31 | Others | Ton/M | Local Market | Road | | 100 | Linkage | | Copy of Linkage | (17.) | Ammonium hydroxide | 1.3 | Others | Ton/M | Local Market | Road | | 100 | Linkage | | Copy of Linkage | (18.) | Ethyl cellulose | 10.4 | Others | Ton/M | Local Market | Road | | 100 | Linkage | | Copy of Linkage | (19.) | Solvent (Ethylene Dichloride, Acetone and Methylene Dichloride) (Fresh) (Recovered) | 17.97 | Others | Ton/M | Local Market | Road | | 100 | Linkage | | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 01 Dec 2018 To 28 Feb 2019 | (b)Season | Winter | |
|
14.1. No. of ambient Air Quality (AAQ) monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | SO2 | | Micro Gram per Meter Cube | 17.8 | 8.6 | 13.88 | 80 | (2.) | PM2.5 | | Micro Gram per Meter Cube | 48.4 | 32.1 | 43.825 | 60 | (3.) | NOx | | Micro Gram per Meter Cube | 23.6 | 13.6 | 19.18 | 80 | (4.) | PM10 | | Micro Gram per Meter Cube | 87.3 | 62.5 | 80.625 | 100 | |
14.2. No. of Ground Water monitoring locations : 7 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | pH | | | Others | pH unit | 7.56 | 7.14 | 7 | 7 | (2.) | Total Hardness | | | mg/l | | 467 | 363 | 200 | 600 | (3.) | Chlorides | | | mg/l | | 286 | 186 | 250 | 1000 | (4.) | Fluoride | | | mg/l | | 0.7 | 0.3 | 1 | 1.5 | (5.) | Heavy Metals | | Zinc | mg/l | | 0.17 | 0.10 | 5 | 15 | (6.) | TSS | | | mg/l | | 1.9 | 1.9 | 1.9 | 1.9 | (7.) | TDS | | | mg/l | | 843 | 664 | 500 | 2000 | |
14.3. No. of Surface Water monitoring locations : 4 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | DO | | mg/l | | 5.2 | 4.7 | C | (2.) | BOD | | mg/l | | 6 | 3 | C | (3.) | COD | | mg/l | | 18 | 12 | C | (4.) | pH | | Others | pH Unit | 7.78 | 7.25 | C | |
14.4. No. of Ambient Noise monitoring locations : 8 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Day) | A-weighted decibels(dB(A)) | 68.8 | 53.6 | 75 | (2.) | Leq(Night) | A-weighted decibels(dB(A)) | 62.3 | 45 | 70 | |
14.5. No. of Soil Sample Monitored locations : 4 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | pH | Others | pH unit | 7.59 | 7.38 | (2.) | Electric Conductivity | Others | dS/m | 2 | 1.11 | (3.) | K(Potassium) | Milliequivalents per 100 Gram | | 1.7 | 1.2 | (4.) | N(Nitrogen) | Percent | | 0.073 | 0.052 | (5.) | P(Phosphorus) | Others | mg/100g | 18.7 | 16.8 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 15 To 20 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 10 To 5 | (c)Whether Ground Water Intersection will be there ? | No | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity (Kilolitre per Day (Kld)) | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | GroundWater | | 244.9 | 0.5 | Copy of Permission Letter | Pipeline | | Others | Bore well | 21-4(928)/WCR/CGWA/2011-3446 | 19 Apr 2012 | 52.7 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | Industrial Effluent | 216.05 | 220 | ETP,RO,MEE | Reuse within the Plant & Recycling,Others | reused in process | 207.5 | 8.55 | (2.) | Domestic waste water | 2 | 2 | Septic tank | Others | septic tank | 0 | 2 | |
|
16.1. | (a)Total Waste Water Generation (Kilolitre per Day) | 218.05 | (b)Total Discharged Water (Kilolitre per Day) | 10.55 | (c)Total Reused Water (Kilolitre per Day) | 207.5 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | Salt from process | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 1703 | Tons | 134 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | (2.) | MEE waste | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 948 | Tons | 134 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | (3.) | Mixed solvent from process | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 1787.44 | Tons | 2 | Road | | Co-Processing | | (4.) | Mixed solvent from the process | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 61.9 | Tons | 10 | Road | | Others | to actual diatillator | (5.) | Distillation residue/& laboratory organic waste | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 4.22 | Tons | 134 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | (6.) | Spent filter cloth and filter material | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 1 | Tons | 134 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | (7.) | Spent carbon from ETP & chimney | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 6 | Tons | 134 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | (8.) | Weak caustic solution | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 4430.4 | Tons | 10 | Road | | Authorized Recyclers | | (9.) | Dust from Air filtration system | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 0.22 | Tons | 10 | Road | | Others | Recycled in process | (10.) | Used Oil | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 0.11 | Tons | 134 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | (11.) | Discarded Container/bag | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 62 | Tons | 20 | Road | | Authorized Recyclers | | (12.) | ETP waste | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 130 | Tons | 134 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | (13.) | Spent resins from DM plant | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 1.2 | Tons | 134 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | (14.) | Fly ash | Others | - | 179 | Tons | 10 | Road | | Others | To brick manufacturer | (15.) | Off-specification material & floor sweeping | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 2 | Tons | 134 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | (16.) | Used hot and cold insulation material | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 0.6 | Tons | 134 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | PM2.5 | | Microgram per Meter Cube | 87 | 0 | 1.14 | 88.15 | 100 | (2.) | SO2 | | Microgram per Meter Cube | 17.7 | 0 | 1.83 | 19.54 | 80 | (3.) | NOx | | Microgram per Meter Cube | 23.4 | 0 | 1.70 | 25.2 | 80 | (4.) | PM10 | | Microgram per Meter Cube | 87 | 0 | 1.14 | 88.15 | 100 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | Thermopak | FO | 15 | 0.4 | SO2 | | 0.10 | (2.) | Hot Air Generator | LDO | 11 | 0.2 | SO2 | | 0.03 | (3.) | Steam Boiler | Coal | 15 | 0.9 | PM10 | | 0.1 | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 1000 | (b)Source | Dakshin Gujarat Veej Co. Ltd. | (c)Uploaded Copy of Agreement | Copy of Agreement | (d)Standby Arrangement (Details of DG Sets) | 2 nos. of D G Set (110 kVA & 35 kVA) | (e)Stack Height (in m) | 11 | |
|
20. | Land Ownership Pattern: | (a)Forest Land (ha.) | 0 | (b)Private Land (ha.) | 3.1874 | (c)Government Land (ha.) | 0 | (d)Revenue Land (ha.) | 0 | (e)Other Land (ha.) | 0 | Total Land (ha.) | 3.1874 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area (ha.) | 11698 | (b)Waste/Barren Land (ha.) | 1566 | (c)Grazing/ Community Land (ha.) | 0 | (d)Surface Water Bodies (ha.) | 5138 | (e)Settlements (ha.) | 4950 | (f)Industrial (ha.) | 0 | (g)Forest (ha.) | 0 | (h)Mangroves (ha.) | 0 | (i)Marine Area (ha.) | 0 | (j)Others (ha.) : range land | 8998 | Total (ha.) | 32350 | |
|
22. Land requirement for various activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement (ha.) | Remarks |
---|
(1.) | Main Plant | | 0.3220 | | (2.) | Built Up Area | | 0.3804 | | (3.) | Area for Solid Waste Management | | 0.1035 | | (4.) | Green belt | | 1.0125 | | (5.) | Others | Open area and road | 1.3690 | | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | NPA | None | 0 | None within 10 km radius | (2.) | Critically Polluted Area | None | 0 | None within 10 km radius | (3.) | WLS | None | 0 | None within 10 km radius | (4.) | ESAs | None | 0 | None within 10 km radius | (5.) | ESZs | None | 0 | None within 10 km radius | (6.) | Corridors | None | 0 | None within 10 km radius | (7.) | Wildlife Corridors | None | 0 | None within 10 km radius | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Archaeological Sites | | None | 0 | None within 10 km radius | (2.) | Defence Installations | | None | 0 | None within 10 km radius | (3.) | Forest | | None | 0 | None within 10 km radius | |
|
23.3. | (a)Whether Noc / Permission from the competent authority is required? | No | (b)Whether NBWL recommendation is required? | No | |
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
25. | Tree Cutting: | (a)No. of Trees Cut for the Project (if Forest Land not Involved) | 0 | (b)Details of Tree Cutting and Planting of Trees | Not Applicable | |
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 3.1874 | (b)Land yet to be acquired(Ha) | 0 | (c)Status of Land acquisition if not acquired | NA | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | 0 | (b)No. of Households | 0 | (c)No. of PDFs (Project Displaced Families) | 0 | (d)No. of PAFs (Project Affected Families) | 0 | (e)Funds Allocated for R&R(in INR) (in Lacs) | 0 | (f)Status of R&R | Completed | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | Yes | (i)Details of Schedule-I Species | Pavo cristatus,Glaucidium radiatum | (b)Whether conservation plan for Schedule-I Species has been prepared ? | Yes | (i)Uploaded copy of conservation plan | Copy of conservation plan | (ii)Fund Provision made | Yes | (iii)Period of Implementation | After Approval from DFO | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | No | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | Yes | (i)Details of Water Bodies in Core Area | River Auranga at 0.24 km in N | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | Yes | (i)Details of Water Bodies in Buffer Area | Arabian Sea | (ii)Direction of Water Bodies in Buffer Area | West | (iii)Distance of Water Bodies in Buffer Area | 9.18 | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 0 | (b)Permanent Employment-During Operation | 50 | (c)Temporary Employment- During Construction | 0 | (d)Temporary Employment- During Operation | 0 | (e)No. of working days | 315 | (f)Total Manpower | 50 | |
|
|
S. No. | Description | Existing | Proposed | Total |
---|
(1.) | Total Area of Green Belt | 0.6325 | 0.3800 | 1.0125 | (2.) | Percentage of Total Project Area | 19.84 | 11.92 | 31.759999999999998 | (3.) | No. of Plants | 1054 | 630 | 1684 | (4.) | Funds Allocated | 5 | 5 | 10 | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Social | Presently there are 110 Nos. of employees. There will be additional 50 Nos. of employees, thus total 160 Nos. of employees after expansion during operational phase. | (2.) | Financial | The project would increase the overall export and also increase the foreign revenue. | (3.) | Environmental | Total 10,125 m2 of greenbelt will be developed after proposed expansion. | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details : NOT APPLICABLE |
35. Sector Specific Details For Industrial Projects - 2 |
|
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | No | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | Yes | (b)Details of Direction Issued Under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act | Water Act | (c)Uploaded Copy of Direction Issued Under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act | Copy of Direction Issued | (d)Compliance status of the directions | Complied | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | NABET/EIA/1720/SA 085 | (ii)Name of the EIA Consultant | ECO CHEM SALES & SERVICES | (iii)Address | Office Floor, Ashoka Pavilion - A New Civil Road, Surat, 395001 | (iv)Mobile No. | 9825123805 | (v)Landline No. | 2612231630 | (vi)Email Id | eco@ecoshripad.com | (vii)Category of Accreditation | A | (viii)Sector of Accreditation | Industrial Projects - 2 | (ix)Validity of Accreditation | 20 Feb 2020 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Detail Sought: |
---|
Sno. | EDS Letter | Remarks | Date of EDS |
---|
1. | NA | May kindly peruse the Certified Compliance report submitted by Regional Officer, Bhopal on the compliance status of your project. There are several observations made by the Regional Officer. Therefore, you are requested to submit the action taken report on the observation made by regional office for further consideration of the proposal | 30 Sep 2019 | 2. | NA | The correction have been made as per the instruction received | 21 Oct 2019 | 3. | NA | (i) It is noted that there are various deficiencies in Form 2 (viz. S. no. 8, 13.1, 32 etc.) uploaded by the PP and accordingly Revised Form 2 shall be submitted incorporating all the information related to the project.
(ii) The onsite emergency plan needs to be submitted as per MSIHC Rules, layout plan of the plant need to be revised.
(iii) As per EIA Report schedule I species reported. Please submit approval status of conservation plan for Schedule I species along with budgetary provisions and its approval from CWLW needs to be provided.
(iv) Detailed Plan for Corporate Environmental Responsibility and its implementable schedule with budgetary provisions needs to be resubmitted.
(v) Details of show cause notice and other violations, if any, needs to be submitted.
(vi) Incremental GLC values in the EIA/Form 2 were reported and needs to be confirmed/rechecked.
(vii) Accurate water balance with details of total water and fresh water requirement, and permission/MoU/NOC from concerned regulatory authority needs to be submitted.
(viii) Effluent treatment mechanism with plan for Zero Liquid Discharge needs to be submitted.
(ix) Details of Raw material linkage and its mitigation measure during transportation needs to be submitted.
(x) Action Plan for non-compliance of earlier EC conditions needs to be submitted.
(xi) PP need to upload the legible documents on parivesh portal
(xii) Proposed Green belt development programe along-with time line and budgetary allocation needs to be provided
(xiii) Issues raised during public hearing, response by the project proponent, action plan with budgetary allocation. Public hearing proceedings to be forwarded by the Member Secretary, SPCB along with complete public hearing/consultation documents. | 05 Dec 2019 | 4. | NA | The correction have been made as per the instruction received | 11 Dec 2019 | |
Additional Detail Sought: |
---|
Sno. | ADS Letter | Remarks | Date of ADS |
---|
1. | ADS Reply Letter | We request you to kindly consider our submission and issue Environmental Clearance. | 26 Jun 2020 | 2. | NA | The EAC, after detailed deliberations decided to defer the proposal for requisite information/inputs
| 06 Feb 2020 | |
| Undertaking |
| I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. |
| Name of Applicant | K Srinivas | Designation | Director | Name of Company (Applicant Name should not be given here) | ASHA CELLULOSE PRIVATE LIMITED | Address | Asha House, 808/C, Dr. B.A. Road, Dadar T.T., Mumbai. |
|