Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Proposed Change In Plant Configuration for Proposed Expansion of Integrated Steel Plant from 5.0 MTPA to 10.0 MTPA by revising the production capacities of Sinter Plant (8 to 4 MTPA) and Pelletization
(b)Name of the Company / Organisation JSW STEEL LTD.
(c)Registered Address JSW Steel Ltd., Dolvi, Village - Wadkhal, Taluka - Pen, Raigad District, Maharashtra,India,Raigad,Maharashtra-402107
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Vitthal Waghchaure
(b)Designation (Owner/ Partner/ CEO) General Manager
(c)Address JSW Steel Ltd. Dolvi, Village - Wadkhal, Taluka - Pen, District Raigad. Maharashtra,,Pen,Raigad,Maharashtra-402107
(d)Pin code 402107
(e)E-mail vitthal.waghchaure@jsw.in
(f)STD Code. 0(f)Telephone No. 277501
(g)Fax No. 02143277533
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity3(a) Metallurgical industries (ferrous & non ferrous)
Minor Activity
(b)Category A
(c)Proposal Number IA/MH/IND/117746/2012
(d)Master Proposal Number(Single Window) SW/117745/2019
(e)EAC concerned (for category A Projects only) Industrial Projects - 1
(f)Project Type Modernization
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Khar Karavi village:6-92, 94-132, 134-146, 148-156
(b)Pincode 402170
(c)Bounded Latitudes (North)
From
Degree 184038.7
Minutes
Second
From
Degree 184214.3
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 730140.9
Minutes
Second
From
Degree 730420.74
Minutes
Second
(e)Survey of India Topo Sheet No. E43G13, E43H1, E43G14, E43 H2
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 1.7
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 0
(j)Seismic Zone 4
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Maharashtra
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number J-11011/76/2013-IA.II(I)
(c)Date of Issue of TOR 28 May 2013
(f)Previous TOR Letter Copy of Previous TOR letter
(b)Date of Apply of EC 12 Oct 2019
(c)Date of Issue of EC 16 Jun 2020
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason Public Hearing for this project has been exempted
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Nagpur
(iii)Letter No. 5-71/2015(ENV)/5695
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit Oct 12 2018 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Integrated Steel Plant5510Tons per Annum(TPA)OthersSea/Road/Rail
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)Pellet Plant II459this project is for Proposed Change In Plant Configuration for Pellet Plant (4 to 9 MTPA)
(2.)Sinter Plant III044this project is for Proposed Change In Plant Configuration for Sinter Plant (8 to 4 MTPA)
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 02 Nov 2018
(iv)Valid Upto 30 Sep 2022
(v)File No. 1811000098
(vi)Application No. 0000045570
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 17242
(b) Funds Allocated for Environment Management (Capital) (in Crores) 2327
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 118
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 455.85
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 13350555
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 13350555
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Iron Ore fines11968614Tons per AnnumImportedOthersSea2 MoUCopy of Linkage
(2.)Limestone750441Tons per AnnumRajasthan/ImportedRoad,Otherssea1168 Open MarketCopy of Linkage
(3.)Dolomite251500Tons per AnnumRajasthan/Karnataka & EgyptRoad,Otherssea1168 MoUCopy of Linkage
(4.)Iron ore lump (BF grade)380000Tons per AnnumimportedOtherssea2 MoUCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Nov 2018 To 31 Jan 2019
(b)Season Post-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM2.5Micro Gram per Meter Cube295.228.6294.560
(2.)NOxMicro Gram per Meter Cube50.50.949.880
(3.)SO2Micro Gram per Meter Cube14.50.313.780
(4.)PM10Micro Gram per Meter Cube812.970.7810.3100
    14.2.     No. of Ground Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)TSSmg/l227..
(2.)pHNA7.66.86.58.5
(3.)TDSmg/l5281465002000
(4.)Total Hardnessmg/l280100200600
(5.)Chloridesmg/l189202501000
(6.)Fluoridemg/l..11.5
(7.)Heavy MetalsAsmg/l0.0400.010.05
    14.3.     No. of Surface Water monitoring locations : 17
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)CODmg/l25248E
(2.)pHmg/l8.37.1A
(3.)DOmg/l5.72.2E
(4.)BODmg/l45964E
    14.4.     No. of Ambient Noise monitoring locations : 9
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))96.455.8IA-75, RA-55. CA-65
(2.)Leq(Night)A-weighted decibels(dB(A))97.241.7IA-70, RA-45, CA-55
    14.5.     No. of Soil Sample Monitored locations : 13
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pHMilligram per Litre7.55.8
(2.)N(Nitrogen)Kilogram per hectare329.150.6
(3.)K(Potassium)Kilogram per hectare396.555.1
(4.)Electric ConductivityMillisiemens per Centimetre23.30.2
(5.)P(Phosphorus)Kilogram per hectare18417
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 0.9 To 7.1
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 0 To 0
(c)Whether Ground Water Intersection will be there ? NA
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)Surface11512323Copy of Permission LetterPipelineOthersPump house from Nagothane Dam at Amba River2015/44/1517 Nov 201646660
(2.)Surface115.12323 Not Appliacble PipelineOthersPump house from Nagothane Dam at Amba River2019/(44/15)28 May 201955000
(3.)Surface115.12323Copy of Permission LetterPipelineOthersPump house from Nagothane Dam at Amba RiverW.N.RID/Office-3/2507/201803 Aug 20185000
(4.)Surface11512323 Not Appliacble PipelineOthersPump house from Nagothane Dam at Amba RiverW.N.SID/Office-4/566/201606 Feb 20167000
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Soft/DM water330025370Biological/Reverse OsmosisReuse within the Plant & Recycling,Otherslosses3110190
(2.)DCW36025370Biological/Reverse OsmosisReuse within the Plant & Recycling,Otherslosses34020
(3.)Drinking water500500STPGreen Belt Renewal Plant500
(4.)ICW2171025370Biological /Reverse OsmosisReuse within the Plant & Recycling,Otherslosses204101300
(5.)Miscellaneous Township12001200STPGreen Belt Renewal Plantsludge1200
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 27070
(b)Total Discharged Water (Kilolitre per Day) 1510
(c)Total Reused Water (Kilolitre per Day) 25560
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Sinter FinesIndustrial Waste1748445Tons0OthersInternal movement within the plant by TippersOthersReused in Steel Plant
(2.)ESP & Bag Filter DustIndustrial Waste790784Tons0OthersInternal movements from TippersOthersReused In Plant
(3.)ESP DustIndustrial Waste68630Tons0OthersInternal movements from TippersOthersReused in Sinter Plant
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube23711.3238.4100
(2.)NOxMicrogram per Meter Cube1012.3312.3480
(3.)PM2.5Microgram per Meter Cube0000.10
(4.)SO2Microgram per Meter Cube9111.620.780
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)Pellet Plant II, ESP 1 Exhaust 1NA10010.6PM108.3
(2.)Pellet Plant II, ESP 1 Exhaust 2NA10010.6PM108.4
(3.)Pellet Plant 2, ESP 3 Hood ExhaustNA10010.6PM107.5
(4.)Pellet Plant II, ESP 4 Plant DedustingNA553.2PM101.7
(5.)Pellet Plant II, Product Bin Bag FilterNA451.8PM100.2
(6.)Sinter Plant III - Main ESPFuel Gas - COG/BF129.4512.6PM106.8
(7.)Sinter Plant III, Product Screening, Bag FilterNA652.5PM103
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 638000
(b)Source MSEB Grid
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) NA
(e)Stack Height (in m) .
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 615.135
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 615.135
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 0
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 0
(e)Settlements (ha.) 0
(f)Industrial (ha.) 615.135
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : 0 0
    Total (ha.) 615.135
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Green belt101.17
(2.)Township60.70
(3.)OthersOpen Area27.93Open Area
(4.)Main Plant425.33Main Plant with Sinter Plant & Pellet Plant
Total (ha.) 615.13
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)WLSNA..
(2.)ESAsNA..
(3.)NPANA..
(4.)Wildlife CorridorsNA..
(5.)Critically Polluted AreaNA..
(6.)ESZsNA..
(7.)CorridorsNA..
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Defence InstallationsNA..
(2.)Forest6 RFs.Adjacent to 6.5 km away in E, NE, SE, WSW, SSE & in SW direction
(3.)Archaeological SitesNA..
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 615.135
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired 615.135
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 3
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? Yes
(i)Details of Water Bodies in Core Area Small sub creek passes through the plant area
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? Yes
(i)Uploaded copy of permission Copy of permission
(ii)Letter No. ...
(iii)Date of issue 04 Sep 2019
(iv)Recommendation NA
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Amba River (other than this, Bhogeswari river, Nigade Nadi & Konjar Nala also found in study area
(ii)Direction of Water Bodies in Buffer Area West
(iii)Distance of Water Bodies in Buffer Area 0
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 1000
(b)Permanent Employment-During Operation 1000
(c)Temporary Employment- During Construction 1000
(d)Temporary Employment- During Operation 2000
(e)No. of working days 330
(f)Total Manpower 5000
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Percentage of Total Project Area29.2138.0167.22
(2.)Funds Allocated300000003000000060000000
(3.)No. of Plants130515131810262325
(4.)Total Area of Green Belt180.898233.91414.808
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)EnvironmentalGreenery of the area will be increased
(2.)FinancialRevenue generation for State and Centre in terms of taxes etc.
(3.)SocialEmployment generation and upliftment of the nearby villagers through CER
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 1
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? Yes
(b)Name of the Court NGT
(c)Name of the Sub Court NGT Western Zone
(d)Case No. Before NGT Pune (WZ) Appeal No. 59 of 2015, Civil
(e)Orders/Directions of the court ,if any and its relevance with the proposed project NA
(f)Case Details Civil Writ Pending - Proceedings before NGT stayed
(g)Uploaded Court Order Copy of Court Order
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET / EIA / 1619 / RA 0069.
(ii)Name of the EIA Consultant J.M. Environet Pvt. Ltd.
(iii)Address 202-A, ABW Tower, M.G. Road, IFFCO Chowk, Sector-25, Gurugram-122001 (Haryana).
(iv)Mobile No. 9829068775
(v)Landline No. 0124482415
(vi)Email Id jmenviron@hotmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 1
(ix)Validity of Accreditation 07 Feb 2020
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File NA
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
      Essential Detail Sought : NIL
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantVitthal Waghchaure
DesignationGeneral Manager
Name of Company (Applicant Name should not be given here)JSW STEEL LTD.
AddressJSW Steel Ltd., Dolvi, Village - Wadkhal, Taluka - Pen, Raigad District, Maharashtra