1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | Establishment of Synthetic Organic Chemicals (Bulk Drug and Intermediates) manufacturing unit by Desis Labs | (b)Name of the Company / Organisation | M/S. DESI’S LABS | (c)Registered Address | Sy.No.221,Ramannapalam Village,kakarla Gramapanchayati,Tiruvuru mandal,krishna district,A.P,,Krishna,Andhra Pradesh-521227 | (d)Legal Status of the Company | Private | (e)Joint Venture | No | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | D Kesava Reddy | (b)Designation (Owner/ Partner/ CEO) | Proprietor | (c)Address | Flat No.203,Satya Sai residency,Plot.No.7-1-54/1,beside MCH Park,dharmkaran road,Ameerpet,Hyderabad,Telangana,,Ameerpet,Hyderabad,Telangana-500016 | (d)Pin code | 500016 | (e)E-mail | desislabs@gmail.com | (f)STD Code. | 40(f)Telephone No. | 66464399 | (g)Fax No. | | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a.I)Project/Activity | 5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
| Minor Activity | | (b)Category | A | (c)Proposal Number | IA/AP/IND2/73245/2018 | (d)Master Proposal Number(Single Window) | SW/117681/2019 | (e)EAC concerned (for category A Projects only) | Industrial Projects - 3 | (f)Project Type | Fresh EC |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | Sy. Nos. 221(Part) | (b)Pincode | 521227 | (c)Bounded Latitudes (North) | | From | | Degree | 17.032480 | Minutes | | Second | | From | | Degree | 17.032992 | Minutes | | Second | | (d)Bounded Longitudes (East) | | From | | Degree | 80.371044 | Minutes | | Second | | From | | Degree | 80.371476 | Minutes | | Second | | (e)Survey of India Topo Sheet No. | E44O12 E44U9 (65C12 65D9) | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 110 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 110.5 | (j)Seismic Zone | 3 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Andhra Pradesh | |
|
|
Details of State(s) of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
(1.) | Andhra Pradesh | Krishna | Tiruvuru | | |
|
6. | Details of Terms of Reference (ToR): | (a)MoEF&CC / SEIAA File Number | IA-J-11011/77/2018-IA-II(I) | (b)Date of Apply of TOR | 28 Feb 2018 | (c)Date of Issue of TOR / Standard ToR | 05 Apr 2018 | (d)Previous TOR Letter | Copy of Previous TOR letter | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | No | (b)Whether details of Public Hearing available? | Yes | (c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above | Yes | |
|
7.1. Details of Public Hearing |
---|
|
S. No. | Details of Advertisement | Details of Public Hearing | Venue | Location Details | No. of People Attended | Issues Raised | Designation of Presiding Officer | Other Designation of Presiding Officer |
---|
(1.) | | Copy of Public Hearing : | Copy of Public Hearing | Date : | 12 Jun 2019 | Distance of Public Hearing Venue from the Proposed Project : | 0 |
| At Proposed Project Site | State : | Andhra Pradesh | District : | Krishna | Tehsil : | Tiruvuru | Village : | Ramannapalem |
| 150 | 1. Employement Potential
2. Village Development
3. Pollution Control Measures | Others | Collector & District Magistrate | |
8. | Details of Project Configuration/Product: | |
|
8.1. Project Configuration |
---|
S. No. | Plant/Equipment/Facility | Configuration | Remarks |
---|
(1.) | Bulk Drug and Intermediates Manufacturing Unit | 150 TPM | Campaign base products | |
8.2. Product |
---|
S. No. | Product/Activity (Capacity/Area) | Quantity | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | Bulk Drug and Intermediates | 150 | Others | TPM | Road | | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | Details Not Applicable | |
|
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | N/A | (iv)Valid Upto | N/A | (v)File No. | NA | (vi)Application No. | NA | (vii)Copy of Consent to operate valid as on date | NA | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in Crores) | 25 | (b) Funds Allocated for Environment Management (Capital) (in Crores) | 8.83 | (c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) | 0.5 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) | 8.3 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | Yes | d)Inter-State boundaries and international boundaries | Yes | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 187.5 | (b)Existing quantity of raw material/fuel | N/A | (c)Total quantity of raw material/fuel | 187.5 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | Synthetic Organic and Inorganic Chemicals | 2250 | Tons per Annum | TPM | Indigenous | Road | | 120 | Open Market | | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 01 Mar 2018 To 31 May 2018 | (b)Season | Summer | |
|
14.1. No. of ambient Air Quality (AAQ) monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | PM10 | | Micro Gram per Meter Cube | 49 | 39 | 49 | 100 | (2.) | NOx | | Micro Gram per Meter Cube | 15 | 10 | 15 | 80 | (3.) | PM2.5 | | Micro Gram per Meter Cube | 28 | 18 | 28 | 60 | (4.) | SO2 | | Micro Gram per Meter Cube | 14 | 10 | 14 | 80 | |
14.2. No. of Ground Water monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | pH | | | NA | | 7.55 | 7.1 | 7 | 7 | (2.) | TDS | | | mg/l | | 1129 | 475 | 500 | 500 | (3.) | TSS | | | mg/l | | 18 | 11 | 100 | 100 | (4.) | Total Hardness | | | mg/l | | 675 | 245 | 200 | 200 | (5.) | Chlorides | | | mg/l | | 479 | 71 | 250 | 250 | (6.) | Fluoride | | | mg/l | | 0.36 | 0.24 | 1 | 1 | |
14.3. No. of Surface Water monitoring locations : 3 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | BOD | | mg/l | | 1.4 | 1 | B | (2.) | COD | | mg/l | | 9.6 | 7.4 | B | (3.) | pH | | NA | | 8.31 | 7.77 | B | (4.) | DO | | mg/l | | 6.5 | 5.3 | B | |
14.4. No. of Ambient Noise monitoring locations : 8 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Night) | A-weighted decibels(dB(A)) | 42 | 38 | 45 | (2.) | Leq(Day) | A-weighted decibels(dB(A)) | 49 | 42 | 55 | |
14.5. No. of Soil Sample Monitored locations : 8 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | P(Phosphorus) | Milligram per Kilogram | | 340 | 160 | (2.) | K(Potassium) | Milligram per Kilogram | | 477 | 185 | (3.) | pH | | | 7.37 | 6.02 | (4.) | N(Nitrogen) | Percent | | 0.082 | 0.02 | (5.) | Electric Conductivity | Others | dS/m | 1.056 | 0.094 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 100 To 70 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 30 To 40 | (c)Whether Ground Water Intersection will be there ? | No | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity (Kilolitre per Day (Kld)) | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | GroundWater | | 205.1 | 0.045 | Copy of Permission Letter | Pipeline | | Tube Well | | 1588/Hg-II/2018 | 26 Jul 2019 | 335 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | High TDS and High COD Stream | 121.1 | 200 | Sent to stripper. Stripper condensate is disposed to cement industries for co-processing/TSDF. Stripper bottom is sent to MEE followed by AFTD. Condensate from MEE and ATFD is sent to biological treatment plant followed by RO. RO rejects are sent to MEE and permeate is reused in cooling towers boiler make-up and scrubbers | Reuse within the Plant & Recycling | | 121.1 | | (2.) | Low TDS and Low COD Stream | 25 | 200 | Sent to biological treatment system followed by RO. RO permeate is reused for cooling towers makeup and scrubbers. RO rejects are sent to MEE | Reuse within the Plant & Recycling | | 25 | | (3.) | Domestic Wastewater | 8 | 10 | Sent to sewage treatment plant and treated wastewater is reused for on land irrigation to develop green belt | Green Belt Renewal Plant | | 8 | | |
|
16.1. | (a)Total Waste Water Generation (Kilolitre per Day) | 154.1 | (b)Total Discharged Water (Kilolitre per Day) | 0 | (c)Total Reused Water (Kilolitre per Day) | 154.1 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | Organic Residue | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 3609 | Tons | 100 | Road | | Others | Sent to Cement plants for co-processing or TSDF | (2.) | Inorganic Salts/Residue | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 3034.7 | Tons | 250 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | (3.) | ETP Sludge | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 187.2 | Tons | 250 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | (4.) | Boiler Ash | Bottom Ash | | 6480 | Tons | 60 | Road | | Others | Sent to Brick Manufacturers | (5.) | Spent Mixed Solvents | Industrial Waste | | 2520 | Kilolitre | 140 | Road | | Others | Sent to authorized recovery units | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | PM10 | | Microgram per Meter Cube | 46 | 1.7 | 1.8 | 47.88 | 100 | (2.) | PM2.5 | | Microgram per Meter Cube | 25 | 1.7 | 0.8 | 25.83 | 60 | (3.) | NOx | | Microgram per Meter Cube | 15 | 1.7 | 13.2 | 28.22 | 80 | (4.) | SO2 | | Microgram per Meter Cube | 14 | 1.7 | 11.3 | 25.36 | 80 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | 2 x 2 Lac K.Cal Thermic Fluid Heater | Coal | 10 | 0.4 | PM10 | | 0.06 g/s | (2.) | 8 TPH Boiler | Coal | 30 | 0.9 | PM10 | | 0.6 g/s | (3.) | 8 TPH Boiler | Coal | 30 | 0.9 | SO2 | | 0.7 g/s | (4.) | 8 TPH Boiler | Coal | 30 | 0.6 | NOx | | 0.25 g/s | (5.) | 2 x 2 Lac K.Cal Thermic Fluid Heater | Coal | 10 | 0.4 | NOx | | 0.12 g/s | (6.) | 2 x 2 Lac K.Cal Thermic Fluid Heater | Coal | 10 | 0.4 | SO2 | | 0.08 g/s | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 3560 | (b)Source | AP Transco | (c)Uploaded Copy of Agreement | Not Applicable | (d)Standby Arrangement (Details of DG Sets) | 2 x 1010 kVA and 2 x 500 kVA | (e)Stack Height (in m) | 10 | |
|
20. | Land Ownership Pattern: | (a)Forest Land (ha.) | 0 | (b)Private Land (ha.) | 4.05 | (c)Government Land (ha.) | 0 | (d)Revenue Land (ha.) | 0 | (e)Other Land (ha.) | 0 | Total Land (ha.) | 4.05 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area (ha.) | 0 | (b)Waste/Barren Land (ha.) | 0 | (c)Grazing/ Community Land (ha.) | 0 | (d)Surface Water Bodies (ha.) | 0 | (e)Settlements (ha.) | 0 | (f)Industrial (ha.) | 4.05 | (g)Forest (ha.) | 0 | (h)Mangroves (ha.) | 0 | (i)Marine Area (ha.) | 0 | (j)Others (ha.) : 0 | 0 | Total (ha.) | 4.05 | |
|
22. Land requirement for various activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement (ha.) | Remarks |
---|
(1.) | Green belt | | 1.38 | | (2.) | Others | Roads | 0.75 | | (3.) | Safety Zone | | 0.45 | | (4.) | Area for Solid Waste Management | | 0.09 | | (5.) | Main Plant | | 1.38 | | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | NPA | Not Applicable | 0 | No NPA within 10 km of Study Area | (2.) | Critically Polluted Area | Not Applicable | 0 | No Critically Polluted Area within 10 km of Study Area | (3.) | ESAs | Not Applicable | 0 | No ESAs within 10 km Study Area | (4.) | ESZs | Not Applicable | 0 | No ESZs within 10 km Study Area | (5.) | Corridors | Not Applicable | 0 | No Corridors within 10 km Study Area | (6.) | Wildlife Corridors | Not Applicable | 0 | No Wildlife Corridors within 10 km Study Area | (7.) | WLS | Not Applicable | 0 | No WLS within 10 km of Study Area | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Others | Reserve Forest | Atlapragada and Koduru RF | 8.2 | South Direction | (2.) | Archaeological Sites | | Not Applicable | 0 | No Archaeological Sites within 10 km Study Area | (3.) | Forest | | Kakarla RF | 0.04 | West Direction | (4.) | Defence Installations | | Not Applicable | 0 | No Defence Installations within 10 km Study Area | |
|
23.3. | (a)Whether Noc / Permission from the competent authority is required? | No | (b)Whether NBWL recommendation is required? | No | |
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
25. | Tree Cutting: | (a)No. of Trees Cut for the Project (if Forest Land not Involved) | Not Applicable | (b)Details of Tree Cutting and Planting of Trees | Not Applicable | |
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 4.05 | (b)Land yet to be acquired(Ha) | 0 | (c)Status of Land acquisition if not acquired | Completed | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | 0 | (b)No. of Households | 0 | (c)No. of PDFs (Project Displaced Families) | 0 | (d)No. of PAFs (Project Affected Families) | 0 | (e)Funds Allocated for R&R(in INR) (in Lacs) | 0 | (f)Status of R&R | Completed | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | No | (b)Whether conservation plan for Schedule-I Species has been prepared ? | No | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | No | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | No | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | Yes | (i)Details of Water Bodies in Buffer Area | Edullavagu Stream | (ii)Direction of Water Bodies in Buffer Area | South East | (iii)Distance of Water Bodies in Buffer Area | 2.6 | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 20 | (b)Permanent Employment-During Operation | 160 | (c)Temporary Employment- During Construction | 60 | (d)Temporary Employment- During Operation | 40 | (e)No. of working days | 30 | (f)Total Manpower | 280 | |
|
32. | Green Belt in Ha: | (a)Total Area of Green Belt | 1.38 | (b)Percentage of Total Project Area | 34.07 | (c)No. of Plants to be Planted | 3200 | (d)Funds Allocated for Plantation | 300000 | (e)Uploaded Green Belt plan | Copy of Green Belt Plan | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Financial | Reduce Imports of API Intermediates | (2.) | Social | Employement Potential | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details For Industrial Projects - 3 |
|
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | No | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | No | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | NABET/EIA/1619/RA 0077 | (ii)Name of the EIA Consultant | Team Labs and Consultants | (iii)Address | TEAM Labs and Consultants B-115-117 & 509, Annapurna Block, Aditya Enclave, Ameerpet, Hyderabad-500 038 | (iv)Mobile No. | 0402374855 | (v)Landline No. | 0402374855 | (vi)Email Id | teamlabs@gmail.com | (vii)Category of Accreditation | A | (viii)Sector of Accreditation | Industrial Projects - 3 | (ix)Validity of Accreditation | 01 Dec 2019 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Detail Sought : NIL |
Additional Detail Sought: |
---|
Sno. | ADS Letter | Remarks | Date of ADS |
---|
1. | NA | Deliberations in the EAC:
The EAC, constituted under the provision of the EIA Notification, 2006 and comprising of Experts Members/domain experts in various fields, examined the proposal submitted by the Project Proponent in desired form along with EIA & EMP report prepared and submitted by the Consultant accredited by the QCI/ NABET on behalf of the Project Proponent.
The EAC noted the duration of baseline data collection i.e. March to May,2018 and it was observed during the meeting that on the KML the density of trees around the plant is decreased from 2014 to 2021. In view of this, EAC warned the consultant and advise to read the provisions of the EIA Notification, 2006 before submission of the application on Parivesh portal
The Committee, after detailed deliberations, deferred the proposal and desired for requisite information/inputs in respect of the following:
(i) The EAC (on KML file timeline data) noted that the Industry has cutted many trees and is unable to produce the approval of forest department in this regard. PP shall submit the permission for cutting of trees with the detailed species.
(ii) The Consultant also mentioned that they have not checked it before coming to the EAC.
(iii) The presentation made by the Consultant is also not adequate and not reflecting the mitigation measures on the proposed impact of the project.
(iv) Considering that the baseline data is of March to May, 2018, additional one month (recent) AAQ baseline data to be collected to validate the existing data.
(v) As Kakarla Reserve Forest is present at a distance 0.04 km, PP shall submit the anticipated impacts on RF due to the emission from the industry.
(vi) PP has not submitted the detailed pollution load as per OM dated 28.01.2021.
(vii) EAC noted that the presentation and the Reports made by the Consultant are inadequate and poor and warned the Consultant to rework and resubmit the reports as per provisions of the EIA Notification, 2006.
The proposal was accordingly deferred for the needful.
| 23 Dec 2021 | 2. | ADS Reply Letter | With reference to minutes of EAC meeting held on 27.02.2020 (Agenda Item No. 17.46), we here with submit land conversion document for establishment of synthetic organic chemicals (bulk drug and intermediates) manufacturing unit at Sy. Nos. 221(Part), Ramannapalem village, Tirvuru mandal, Krishna district, Andhra Pradesh. Kindly process our application for Environmental clearance at the earliest and acknowledge the receipt of the same. | 04 Dec 2021 | 3. | NA | |
|