1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | Mill Development Plan (MDP) Comprising of augmentation of pulp mill and existing paper machines, installation of Multi-layer Coated Board Machine and installation of 35 MW steam turbine with 135 TPH F | (b)Name of the Company / Organisation | THE WEST COAST PAPER MILLS LIMITED | (c)Registered Address | NIL | (d)Legal Status of the Company | NIL | (e)Joint Venture | No | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | Rajendra Jain | (b)Designation (Owner/ Partner/ CEO) | ED | (c)Address | M/s.West Coast Paper Mills Ltd, Bangur Nagar, Dandeli, Post Box No.5, Uttar Kannada, Karnataka,,Haliyal,Uttara Kannada,Karnataka-581325 | (d)Pin code | 581325 | (e)E-mail | bhrathi@westcoastpaper.com | (f)STD Code. | 8284(f)Telephone No. | 231391 | (g)Fax No. | 08284231249 | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a.I)Project/Activity | 5(i) Pulp & paper industry excluding manufacturing of paper from waste
| Minor Activity | 1(d) Thermal Power Plants
| (b)Category | A | (c)Proposal Number | IA/KA/IND/117479/2018 | (d)Master Proposal Number(Single Window) | SW/117118/2019 | (e)EAC concerned (for category A Projects only) | Industrial Projects - 1 | (f)Project Type | Expansion |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | 3-A (Dandeli), 21- Ambewadi, 22- Kerwad Village | (b)Pincode | 581325 | (c)Bounded Latitudes (North) | | From | | Degree | 15.249603 | Minutes | | Second | | From | | Degree | 15.28836 | Minutes | | Second | | (d)Bounded Longitudes (East) | | From | | Degree | 74.621392 | Minutes | | Second | | From | | Degree | 74.64375 | Minutes | | Second | | (e)Survey of India Topo Sheet No. | 48 I11, 48I12 | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 452 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 1 | (j)Seismic Zone | 2 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Karnataka | |
|
|
Details of State of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
NIL | |
|
6. | Details of Terms of Reference (ToR)/EC: | (a)MoEF&CC / SEIAA File Number | J-11011/408/2006-IA-II(I) | (b)Date of Apply of TOR | 01 Aug 2018 | (c)Date of Issue of TOR / Standard ToR | 09 Oct 2018 | (d)Date of Apply of EC | 13 Nov 2006 | (e)Date of Issue of EC | 19 Jul 2007 | (f)Previous TOR Letter | Copy of Previous TOR letter | (g)Previous EC Letter | Copy of Previous EC letter | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | No | (b)Whether details of Public Hearing available? | Yes | (c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above | Yes | |
|
7.1. Details of Public Hearing |
---|
|
S. No. | Details of Advertisement | Details of Public Hearing | Venue | Location Details | No. of People Attended | Issues Raised | Designation of Presiding Officer | Other Designation of Presiding Officer |
---|
(1.) | | Copy of Public Hearing : | Copy of Public Hearing | Date : | 29 Jul 2019 | Distance of Public Hearing Venue from the Proposed Project : | 0.6 |
| Dr. B.R.Ambedkar Bhavan, Township Dandeli | State : | Karnataka | District : | Uttara Kannada | Tehsil : | Haliyal | Village : | Dandeli |
| 1216 | 1. Discharge of treated wastewater
2. Air and odour emissions
3. employment opportunities to locals
4. Implementation of CSR programs | Others | Additional Deputy Commissioner | |
8. | Details of Project Configuration/Product: | Details Not Applicable | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | (a)Details of certified report on compliance of earlier environmental clearance condition | (i)Certified Compliance By | Regional | (ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on | Bangalore | (iii)Letter No. | EP/12.1/478/Kar | (iv)Status of Compliance | Compiled | (v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) | Copy of Certified Compliance Report | (vi)Date of site visit | Jan 11 2017 12:00AM | (b)Details of Capacity Expansion | |
|
S. No. | Product/Activity (Capacity/Area) | Quantity From | Quantity To | Total | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | paper/board production | 320000 | 130000 | 450000 | Tons per Annum(TPA) | | Road | | (2.) | bleached chemical wood pulp mill | 725 | 119 | 844 | Others | BD tpd | Others | Captive | (3.) | De-Inking plant | 0 | 200 | 200 | Others | BD tpd | Others | Captive | (4.) | Captive power plant | 74.8 | 35 | 109.8 | Mega Watt(MW) | | Others | Captive | |
| (c)Details of Configuration | |
|
S. No. | Plant / Equipment / Facility | Existing Configuration | Proposed Configuration | Final configuration after expansion | Remarks |
---|
(1.) | Paper Machines | 3,20,000 TPA | 25,000 TPA | 3,45,000 TPA | Modernization/upgradation | (2.) | Board Machines | 0 | 1,05,000 TPA | 1,05,000 TPA | Installation of new board machine | (3.) | Bleached Chemical Wood Pulp Mill | 725 BD TPD | 119 BD TPD | 844 BD TPD | Upgradation | (4.) | De-Inking Plant | 0 BD TPD | 200 BD TPD | 200 BD TPD | New DIP will be installed. | (5.) | Captive Power Plant | 74.8 MW | 35 MW | 109.8 MW | New TG of 35 MW will be installed | |
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | 29 Dec 2016 | (iv)Valid Upto | 30 Jun 2021 | (v)File No. | AWH-301773 | (vi)Application No. | 3514-29/12/2016 | (vii)Copy of Consent to operate valid as on date | Copy of Consent to Operate | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in Crores) | 750 | (b) Funds Allocated for Environment Management (Capital) (in Crores) | 20 | (c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) | 3.75 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) | 0.4 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | No | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 243400 | (b)Existing quantity of raw material/fuel | 986500 | (c)Total quantity of raw material/fuel | 1229900 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | Waste Paper | 24000 | Others | AD TPA | Mumbai, Vapi, Pune | Road | | 600 | Open Market | | Copy of Linkage | (2.) | Coal | 445000 | Tons per Annum | | Import and local market | Road | | 600 | Open Market | | Copy of Linkage | (3.) | Market pulp (HWP) | 29600 | Tons per Annum | | Import | Road | | 100 | Open Market | | Copy of Linkage | (4.) | Wood | 1139000 | Tons per Annum | | Procuring from nearby states | Road | | 250 | Others | Social and farm forestry | Copy of Linkage | (5.) | market pulp (SWP) | 14800 | Tons per Annum | | Import | Road | | 100 | Open Market | | Copy of Linkage | (6.) | BCTMP | 22500 | Tons per Annum | | Import | Road | | 100 | Open Market | | Copy of Linkage | (7.) | Furnace oil | 17700 | Others | KL/annum | local | Road | | 100 | Open Market | | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 05 Apr 2017 To 03 Jul 2017 | (b)Season | Pre-Monsoon | |
|
14.1. No. of ambient Air Quality (AAQ) monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | SO2 | | Micro Gram per Meter Cube | 15.2 | 3.1 | 14.6 | 80 | (2.) | PM2.5 | | Micro Gram per Meter Cube | 36.2 | 12.6 | 35.9 | 60 | (3.) | PM10 | | Micro Gram per Meter Cube | 74.9 | 30.1 | 73.9 | 100 | (4.) | NOx | | Micro Gram per Meter Cube | 27.80 | 3.60 | 18.25 | 80 | (5.) | Others | ozone | Micro Gram per Meter Cube | 27.60 | 5.20 | 25.68 | 180 | |
14.2. No. of Ground Water monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | Fluoride | | | mg/l | | 0.31 | 0.14 | 0.3 | 0.3 | (2.) | pH | | | NA | | 8.2 | 7.2 | 7.5 | 8.5 | (3.) | TSS | | | mg/l | | 26 | 0 | 0 | 0 | (4.) | TDS | | | mg/l | | 1384 | 286 | 500 | 2000 | (5.) | Chlorides | | | mg/l | | 357 | 41 | 250 | 1000 | (6.) | Total Hardness | | | mg/l | | 1030 | 192 | 200 | 600 | |
14.3. No. of Surface Water monitoring locations : 2 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | pH | | NA | | 7.5 | 7.2 | C | (2.) | DO | | mg/l | | 7 | 6.9 | C | (3.) | BOD | | mg/l | | 2 | 2 | C | (4.) | COD | | mg/l | | 0 | 0 | C | |
14.4. No. of Ambient Noise monitoring locations : 8 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Day) | A-weighted decibels(dB(A)) | 57.2 | 49.7 | 55 | (2.) | Leq(Night) | A-weighted decibels(dB(A)) | 44.3 | 39.3 | 45 | |
14.5. No. of Soil Sample Monitored locations : 8 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | pH | | | 7.4 | 6 | (2.) | N(Nitrogen) | Milligram per Kilogram | | 104 | 68 | (3.) | Electric Conductivity | Others | microsiemens per centimeter | 480 | 190 | (4.) | P(Phosphorus) | Milligram per Kilogram | | 164 | 102 | (5.) | K(Potassium) | Milligram per Kilogram | | 420 | 140 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 10.6 To 11.8 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 12.4 To 8.4 | (c)Whether Ground Water Intersection will be there ? | No | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity (Kilolitre per Day (Kld)) | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | Surface | | 75800 | 1 | Copy of Permission Letter | Pipeline | | Jack Well | | WRD 98 MBI 2007 | 02 Jun 2008 | 100000 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | Miscellaneous | 1000 | 85885 | Biological Treatment | Reuse within the Plant & Recycling | | 1000 | | (2.) | Wastewater from the mill | 63300 | 85885 | Biological Treatment | Discharge into Surface Water Body | | | 63300 | |
|
16.1. | (a)Total Waste Water Generation (Kilolitre per Day) | 64300 | (b)Total Discharged Water (Kilolitre per Day) | 63300 | (c)Total Reused Water (Kilolitre per Day) | 1000 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | Lime mud | Industrial Waste | | 149600 | Tons | 0 | Road | | Others | Recycled using lime kiln with make-up lime | (2.) | Saw Dust | Industrial Waste | | 27200 | Tons | 0 | Others | NA | Others | Fired in boiler | (3.) | ETP sludge | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 27200 | Tons | 100 | Road | | Others | Sent to card board /egg tray manufacturer | (4.) | Plastic waste | Plastic Waste | | 1700 | Tons | 100 | Road | | Authorized Recyclers | | (5.) | De-Inking Plant sludge | Industrial Waste | | 10200 | Tons | 100 | Road | | Others | sent to authorized dealers/fired in boilers | (6.) | Fly ash | Fly Ash | | 200600 | Tons | 100 | Road | | Co-Processing | | (7.) | Used oil | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 20.4 | Kilolitre | 400 | Road | | Authorized Recyclers | | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | PM2.5 | | Microgram per Meter Cube | 28.55 | 2 | 0.37 | 28.93 | 60 | (2.) | SO2 | | Microgram per Meter Cube | 9.54 | 2 | 9.6 | 19.15 | 80 | (3.) | NOx | | Microgram per Meter Cube | 18.25 | 2 | 4.5 | 22.76 | 80 | (4.) | PM10 | | Microgram per Meter Cube | 59.66 | 2 | 0.94 | 60.60 | 100 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | Proposed FBC boiler | Mix of imported and Indian coals | 85 | 3 | NOx | | 5.83 | (2.) | Proposed FBC Boiler | Mix of imported and Indian coals | 85 | 3 | PM10 | | 1.38 | (3.) | Proposed FBC Boiler | Mix of imported and Indian coals | 85 | 3 | SO2 | | 40.2 | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 63100 | (b)Source | Captive Power Plant | (c)Uploaded Copy of Agreement | Not Applicable | (d)Standby Arrangement (Details of DG Sets) | NA | (e)Stack Height (in m) | 0 | |
|
20. | Land Ownership Pattern: | (a)Forest Land (ha.) | 0 | (b)Private Land (ha.) | 152.05 | (c)Government Land (ha.) | 0 | (d)Revenue Land (ha.) | 0 | (e)Other Land (ha.) | 0 | Total Land (ha.) | 152.05 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area (ha.) | 0 | (b)Waste/Barren Land (ha.) | 0 | (c)Grazing/ Community Land (ha.) | 0 | (d)Surface Water Bodies (ha.) | 0 | (e)Settlements (ha.) | 0 | (f)Industrial (ha.) | 152.05 | (g)Forest (ha.) | 0 | (h)Mangroves (ha.) | 0 | (i)Marine Area (ha.) | 0 | (j)Others (ha.) : NA | 0 | Total (ha.) | 152.05 | |
|
22. Land requirement for various activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement (ha.) | Remarks |
---|
(1.) | Main Plant | | 2.22 | Plant and Building | (2.) | Others | Material storage | 1.61 | | (3.) | Area for Solid Waste Management | | 0.20 | | (4.) | Green belt | | 0.80 | | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Critically Polluted Area | NA | 0 | NA | (2.) | Corridors | NA | 0 | NA | (3.) | Wildlife Corridors | NA | 0 | NA | (4.) | ESZs | Dandeli-Anshi Tiger Reserve/Kali Tiger Reserve | 2 | ESZ draft notification is published | (5.) | WLS | Dandeli Wildlife Sanctuary | 9 | East | (6.) | NPA | NA | 0 | NA | (7.) | ESAs | NA | 0 | NA | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Forest | | Dandeli Reserve Forest | 0.5 | NA | (2.) | Archaeological Sites | | NA | 0 | NA | (3.) | Defence Installations | | NA | 0 | NA | |
|
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
25. | Tree Cutting: | (a)No. of Trees Cut for the Project (if Forest Land not Involved) | 0 | (b)Details of Tree Cutting and Planting of Trees | Not Applicable | |
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 152.05 | (b)Land yet to be acquired(Ha) | 0 | (c)Status of Land acquisition if not acquired | Entire land is already acquired | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | 0 | (b)No. of Households | 0 | (c)No. of PDFs (Project Displaced Families) | 0 | (d)No. of PAFs (Project Affected Families) | 0 | (e)Funds Allocated for R&R(in INR) (in Lacs) | 0 | (f)Status of R&R | Completed | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | No | (b)Whether conservation plan for Schedule-I Species has been prepared ? | No | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | No | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | Yes | (i)Details of Water Bodies in Core Area | Kali River | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | No | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 0 | (b)Permanent Employment-During Operation | 175 | (c)Temporary Employment- During Construction | 375 | (d)Temporary Employment- During Operation | 125 | (e)No. of working days | 340 | (f)Total Manpower | 675 | |
|
|
S. No. | Description | Existing | Proposed | Total |
---|
(1.) | Total Area of Green Belt | 41.6 | 0.809 | 42.409 | (2.) | Percentage of Total Project Area | 27 | 1 | 28 | (3.) | No. of Plants | 113000 | 3000 | 116000 | (4.) | Funds Allocated | 50 | 100 | 150 | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Environmental | • Up gradation of Environmental Management Systems.
• Maximizing the internal recycling
• Reduction in specific freshwater consumption.
• Reduction in specific wastewater generation | (2.) | Social | Rs. 375 Lakhs has been embarked for the local community development within the vicinity of the project area for 5 years under CER
The proposed project will create direct employment to about 175 persons and indirect employment to about 125 persons | (3.) | Financial | The project is likely to generate income to the state by way of Goods and Service Tax (GST) to the tune of Rs 50 crores per annum. | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details : NOT APPLICABLE |
35. Sector Specific Details For Industrial Projects - 1 |
|
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | No | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | No | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | NABET/EIA/1619/SA 076 | (ii)Name of the EIA Consultant | Cholamandalam MS Risk Services Limited | (iii)Address | Parry House, 3rd Floor, No.2, NSC Bose Road, Chennai- 600001 | (iv)Mobile No. | 9677003778 | (v)Landline No. | 0443044562 | (vi)Email Id | bhaskarvs@cholams.murugappa.com | (vii)Category of Accreditation | A | (viii)Sector of Accreditation | Industrial Projects - 1 | (ix)Validity of Accreditation | 15 Nov 2019 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Detail Sought: |
---|
Sno. | EDS Letter | Remarks | Date of EDS |
---|
1. | NA | Proposal is returned due to the following shortcomings:
• RO certified report is of January, 2017 which is more than two years old. Recent report of RO shall be furnished.
• Plant lay out is not legible, not scaled and no legends are mentioned. Revised layout shall be furnished.
• Water consumption per ton of paper production is reported as 56 m3 which appears to be on higher side. Water consumption may be reworked out.
• Total wastewater generation is 64,300 KLD. Only 1000 KLD is reused and remaining 63,300 is discharged in to surface water body. Reuse of wastewater may be reworked out.
• Project site is located at about 2 km from the Eco sensitive zone boundary of DandeliAnshi Tiger Reserve & Hornbill Conservation Reserve boundary as per draft ESZ MoEF&CC Notification. Dandeli Wildlife Sanctuary is located at 9 km (E). Permission obtained from Standing Committee of National Board for Wildlife (SCNBWL) for the existing unit shall be furnished. | 13 Sep 2019 | 2. | NA | The correction have been made as per the instruction received | 29 Apr 2020 | |
Additional Detail Sought : NIL |
| Undertaking |
| I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. |
| Name of Applicant | Rajendra Jain | Designation | ED | Name of Company (Applicant Name should not be given here) | THE WEST COAST PAPER MILLS LIMITED | Address | BANGURNAGAR DANDELI |
|