1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | Singrauli Super Thermal Power Project, Stage-III (2x800 MW) | (b)Name of the Company / Organisation | NTPC Limited | (c)Registered Address | NTPC Engineering Office Complex Sector-24, Noida,NTPC Engineering Office Complex Sector-24, Noida,Gautam Buddha Nagar,Uttar Pradesh-201301 | (d)Legal Status of the Company | Central PSU | (e)Joint Venture | No | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | Vijay Prakash | (b)Designation (Owner/ Partner/ CEO) | Head of Deptt Env Engg | (c)Address | NTPC Engineering Office Complex Sector-24, Noida,NTPC Engineering Office Complex Sector-24, Noida,,Gautam Buddha Nagar,Uttar Pradesh-201301 | (d)Pin code | 201301 | (e)E-mail | environment.ntpc@gmail.com | (f)STD Code. | 120(f)Telephone No. | 2410331 | (g)Fax No. | 24105060 | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a.I)Project/Activity | 1(d) Thermal Power Plants
| Minor Activity | | (b)Category | A | (c)Proposal Number | IA/UP/THE/117100/2016 | (d)Master Proposal Number(Single Window) | SW/117086/2019 | (e)EAC concerned (for category A Projects only) | Thermal Projects | (f)Project Type | Expansion |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | 10 | (b)Pincode | 231222 | (c)Bounded Latitudes (North) | | From | | Degree | 2654587.5934 | Minutes | | Second | | From | | Degree | 2654587.5934 | Minutes | | Second | | (d)Bounded Longitudes (East) | | From | | Degree | 601714.5538 | Minutes | | Second | | From | | Degree | 607114.5538 | Minutes | | Second | | (e)Survey of India Topo Sheet No. | 64 L/12,64 L/16 | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 280 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 0.5 | (j)Seismic Zone | 3 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Uttar Pradesh | |
|
|
Details of State of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
NIL | |
|
6. | Details of Terms of Reference (ToR)/EC: | (a)MoEF&CC / SEIAA File Number | J-13012/09/2016-IA I (T) | (c)Date of Issue of TOR | 06 Mar 2017 | (f)Previous TOR Letter | Copy of Previous TOR letter | (b)Date of Apply of EC | 12 Sep 2019 | (c)Date of Issue of EC | 13 Jul 2020 | (d)Previous EC Letter | Copy of Previous EC letter | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | No | (b)Whether details of Public Hearing available? | Yes | (c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above | Yes | |
|
7.1. Details of Public Hearing |
---|
|
S. No. | Details of Advertisement | Details of Public Hearing | Venue | Location Details | No. of People Attended | Issues Raised | Designation of Presiding Officer | Other Designation of Presiding Officer |
---|
(1.) | | Copy of Public Hearing : | Copy of Public Hearing | Date : | 09 Jul 2019 | Distance of Public Hearing Venue from the Proposed Project : | 0.5 |
| Auditorium of NTPC LTD,Shaktinagar | State : | Uttar Pradesh | District : | Sonbhadra | Tehsil : | Dudhi | Village : | Shaktinagar |
| 189 | Drinking water, Road and Sanitation, Electricity. Jobs | Others | Additional Collector | |
8. | Details of Project Configuration/Product: | Details Not Applicable | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | (a)Details of certified report on compliance of earlier environmental clearance condition | (i)Certified Compliance By | SPCB | (ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on | | (iii)Letter No. | 001 | (iv)Status of Compliance | Compiled | (v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) | Copy of Certified Compliance Report | (vi)Date of site visit | Sep 9 2019 12:00AM | (b)Details of Capacity Expansion | |
|
S. No. | Product/Activity (Capacity/Area) | Quantity From | Quantity To | Total | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | Electricity Generation | 2000 | 1600 | 3600 | Mega Watt(MW) | | Others | Transmission line | |
| (c)Details of Configuration | |
|
S. No. | Plant / Equipment / Facility | Existing Configuration | Proposed Configuration | Final configuration after expansion | Remarks |
---|
(1.) | 2x800 | 5x200+2x500 | 2x800 | 3600 | 5x200 will be decommission after commissioning of 2x800 | (2.) | 2x800 | 5x200+2x500 | 2x800 | 3600 | 5x200 will be decommission after commissioning of 2x800 | (3.) | 2x800 | 5x200+2x500 | 2x800 | 3600 | 5x200 will be decommission after commissioning of 2x800 | |
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | 20 Mar 2018 | (iv)Valid Upto | 31 Dec 2019 | (v)File No. | 2236/UPPCB/SONEBHDRA(UPPCBRO)/CTO/AIR/SONEBHADRA/2 | (vi)Application No. | 137004 | (vii)Copy of Consent to operate valid as on date | Copy of Consent to Operate | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in Crores) | 11363 | (b) Funds Allocated for Environment Management (Capital) (in Crores) | 11363 | (c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) | 16 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) | 240 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | Yes | b)Critically polluted areas as notified by the Central Pollution Control Board(CPCB) from time to time | Yes | d)Inter-State boundaries and international boundaries | Yes | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 8400000 | (b)Existing quantity of raw material/fuel | 10000000 | (c)Total quantity of raw material/fuel | 18400000 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | Coal | 8400000 | Tons per Annum | | NCL | Rail | | 0 | Linkage | | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 15 May 2017 To 14 May 2018 | (b)Season | Three-Sesions | |
|
14.1. No. of ambient Air Quality (AAQ) monitoring locations : 12 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | PM10 | | Micro Gram per Meter Cube | 82.7 | 44.5 | 81.7 | 100 | (2.) | PM2.5 | | Micro Gram per Meter Cube | 55.6 | 16.9 | 55.4 | 60 | (3.) | SO2 | | Micro Gram per Meter Cube | 43.8 | 8.5 | 43.6 | 80 | (4.) | NOx | | Micro Gram per Meter Cube | 51.9 | 10.3 | 49.9 | 80 | (5.) | Others | CO | Micro Gram per Meter Cube | 729 | 237 | 728 | 2000 | |
14.2. No. of Ground Water monitoring locations : 15 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | Total Hardness | | | mg/l | | 679.8 | 81 | 200 | 600 | (2.) | TDS | | | mg/l | | 871 | 132 | 500 | 2000 | (3.) | Fluoride | | | mg/l | | 2.1 | 0.2 | 1.0 | 1.5 | (4.) | Heavy Metals | | Cadmium | mg/l | | 0.02 | 0.001 | 0.003 | 0 | (5.) | Heavy Metals | | Zinc | mg/l | | 1.3 | 0.01 | 5 | 15 | (6.) | Others | Total Alkalinity ac CaCO33 | | mg/l | | 426 | 48.3 | 200 | 600 | (7.) | pH | | | Others | not required | 8.31 | 6.2 | 7.5 | 8.5 | (8.) | Heavy Metals | | Lead | mg/l | | 0.08 | 0.009 | 0.01 | 0 | (9.) | Chlorides | | | mg/l | | 246.7 | 14.2 | 250 | 1000 | (10.) | Others | Iron | | mg/l | | 0.282 | 0.01 | 0.3 | 0 | (11.) | TSS | | | mg/l | | 38 | 28 | 0 | 0 | |
14.3. No. of Surface Water monitoring locations : 10 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | DO | | mg/l | | 6.2 | 4.8 | C | (2.) | BOD | | mg/l | | 7 | 3 | C | (3.) | Others | Total Hardness | mg/l | | 298.7 | 40 | C | (4.) | Others | Total Coli-forms | Others | MPN/100 ML | 2190 | 46 | C | (5.) | pH | | NA | | 8.31 | 6.61 | C | (6.) | COD | | mg/l | | 20 | 5 | C | |
14.4. No. of Ambient Noise monitoring locations : 20 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Day) | A-weighted decibels(dB(A)) | 60.25 | 43.83 | 65 | (2.) | Leq(Night) | A-weighted decibels(dB(A)) | 56.65 | 40.23 | 55 | |
14.5. No. of Soil Sample Monitored locations : 15 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | pH | | | 8.1 | 6.1 | (2.) | N(Nitrogen) | Kilogram per hectare | | 430 | 27.2 | (3.) | P(Phosphorus) | Kilogram per hectare | | 307 | 57.7 | (4.) | Electric Conductivity | Millisiemens per Centimetre | | 1003 | 101 | (5.) | K(Potassium) | Kilogram per hectare | | 717.5 | 44.6 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 22 To 4 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 2.10 To 20.50 | (c)Whether Ground Water Intersection will be there ? | No | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity (Kilolitre per Day (Kld)) | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | Surface | | 38880 | 0.4 | Copy of Permission Letter | Pipeline | | Others | Discharge Channel of Singrauli STPS-II | 36/24/2004 | 28 Jan 2004 | 48000 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | DM Filter Backwash | 240 | 240 | Recycled in to DM Clarifier inlet | Reuse within the Plant & Recycling | | 240 | | (2.) | Tube settler Sludge | 120 | 120 | ash water tank | Reuse within the Plant & Recycling | | 120 | | (3.) | Clarifier Sludge | 840 | 840 | tube settler | Reuse within the Plant & Recycling | | 840 | | (4.) | Boiler Blowdown | 2400 | 2400 | Recycled in to ACW make-up | Reuse within the Plant & Recycling | | 2400 | | (5.) | DM Neurtilization Pit water | 480 | 480 | Recycled in to Ash slurry sump | Reuse within the Plant & Recycling | | 480 | | (6.) | Domestic Sewage | 360 | 360 | STP | Green Belt Renewal Plant | | 360 | | |
|
16.1. | (a)Total Waste Water Generation (Kilolitre per Day) | 4440 | (b)Total Discharged Water (Kilolitre per Day) | 0 | (c)Total Reused Water (Kilolitre per Day) | 4440 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | Ash | Bottom Ash | | 570000 | Tons | 7 | Others | Pipeline | Others | ash utilisation | (2.) | Fly ash | Fly Ash | | 2280000 | Tons | 7 | Rail | | Others | ash utilisation | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | SO2 | | Microgram per Meter Cube | 43.8 | 2.2 | 4.9 | 48.7 | 80 | (2.) | PM10 | | Microgram per Meter Cube | 82.7 | 2.2 | 1.5 | 84.21 | 100 | (3.) | NOx | | Microgram per Meter Cube | 51.9 | 2.2 | 4.9 | 56.81 | 80 | (4.) | PM2.5 | | Microgram per Meter Cube | 55.6 | 2.2 | 0.15 | 55.76 | 60 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | Power plant | coal | 275 | 8.8 | SO2 | | 88.4 | (2.) | Power plant | Coal | 275 | 8.8 | PM10 | | 26.5 | (3.) | Power plant | Coal | 275 | 8.8 | NOx | | 88.4 | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 6000 | (b)Source | captive | (c)Uploaded Copy of Agreement | Not Applicable | (d)Standby Arrangement (Details of DG Sets) | 3x2000 KVA | (e)Stack Height (in m) | 30 | |
|
20. | Land Ownership Pattern: | (a)Forest Land (ha.) | 0 | (b)Private Land (ha.) | 0 | (c)Government Land (ha.) | 0 | (d)Revenue Land (ha.) | 0 | (e)Other Land (ha.) | 227.5 | Total Land (ha.) | 227.5 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area (ha.) | 0 | (b)Waste/Barren Land (ha.) | 0 | (c)Grazing/ Community Land (ha.) | 0 | (d)Surface Water Bodies (ha.) | 0 | (e)Settlements (ha.) | 0 | (f)Industrial (ha.) | 227.5 | (g)Forest (ha.) | 0 | (h)Mangroves (ha.) | 0 | (i)Marine Area (ha.) | 0 | (j)Others (ha.) : Not applicable | 0 | Total (ha.) | 227.5 | |
|
22. Land requirement for various activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement (ha.) | Remarks |
---|
(1.) | Main Plant | | 42.9 | including switch yard | (2.) | Others | Air cooled Condenser | 15.3 | | (3.) | Green belt | | 26.30 | | (4.) | Built Up Area | | 143 | DM & PT plant area, CHP, balance facilities | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Critically Polluted Area | Singrauli | 0 | Proposed project is located in Critically Polluted area. | (2.) | NPA | Nil | 10 | There is no National Park within 10 km radius of the project | (3.) | ESAs | Nil | 10 | There is no Eco sensitive area within 10 km radius of the project | (4.) | WLS | Nil | 10 | There is no Wildlife Sanctuary within 10 km radius of the project | (5.) | ESZs | Nil | 10 | There is no eco sensitive zone within 10 km radius of the project | (6.) | Wildlife Corridors | Nil | 10 | Nil | (7.) | Corridors | Nil | 10 | There is no any corridor within 10 km radius of the project | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Forest | | Dudichua Protected Forests | 4.1 | Protected forest | (2.) | Archaeological Sites | | Nil | 0 | Nil | (3.) | Defence Installations | | Nil | 0 | Nil | |
|
23.3. | (a)Whether Noc / Permission from the competent authority is required? | No | (b)Whether NBWL recommendation is required? | No | |
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
25. | Tree Cutting: | (a)No. of Trees Cut for the Project (if Forest Land not Involved) | 12000 | (b)Details of Tree Cutting and Planting of Trees | Not Applicable | |
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 562 | (b)Land yet to be acquired(Ha) | 0 | (c)Status of Land acquisition if not acquired | 0 | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | 0 | (b)No. of Households | 0 | (c)No. of PDFs (Project Displaced Families) | 0 | (d)No. of PAFs (Project Affected Families) | 0 | (e)Funds Allocated for R&R(in INR) (in Lacs) | 0 | (f)Status of R&R | Completed | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | Yes | (i)Details of Schedule-I Species | Python, Marsh crocodiles, Shikra | (b)Whether conservation plan for Schedule-I Species has been prepared ? | No | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | No | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | No | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | Yes | (i)Details of Water Bodies in Buffer Area | Rihand Reservoir, Ralla Kaluva River (1.0 km, NE) Swarnamukhi River (2.2 km, S) | (ii)Direction of Water Bodies in Buffer Area | North East | (iii)Distance of Water Bodies in Buffer Area | 1 | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 250 | (b)Permanent Employment-During Operation | 250 | (c)Temporary Employment- During Construction | 1250 | (d)Temporary Employment- During Operation | 250 | (e)No. of working days | 330 | (f)Total Manpower | 2000 | |
|
|
S. No. | Description | Existing | Proposed | Total |
---|
(1.) | Total Area of Green Belt | 1192 | 65 | 1257 | (2.) | Percentage of Total Project Area | 26.5 | 12 | 38.5 | (3.) | No. of Plants | 1600000 | 116000 | 1716000 | (4.) | Funds Allocated | 0 | 50000000 | 50000000 | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Environmental | Proposed Singrauli STPP Stage-III (2x800 MW) will have state of art Super Critical Technology which has better efficiency and less carbon emissions in comparison to sub-critical technology. Air Cooled Condensers (ACC) technology will reduce the water consumption more than 50% wet cooling tower system. These new technologies will help in conservation of natural resources like coal and water. Installation of High efficiency ESP, FGD and De-Nox System will comply the emission norms of MOEF&CC and r | (2.) | Social | The setting up of the proposed project will lead to direct and indirect benefits to the overall socio-economic development of the region. | (3.) | Financial | Establishment of large developmental projects improve the availability of the physical infrastructure (like approach roads, drainage, communication and transportation facilities etc.) and social infrastructures (like education and health care system). These will also benefit the local population. NTPC has taken up several community welfare and community development activities under Corporate Social Responsibility and this will be strengthened during commissioning of Singrauli STPP Stage-III. | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details For Thermal Projects |
|
1. | Specifications of Plant: | (b) Technology Proposed | Supercritical | (b) Plant Load Factor(%) | 90 | (c) Station Heat Rate (Kcal/Kwh) | 2447 | (d) Steam Rate/Flow Rate | 2660 | (e) Boiler Temperature | 603 | (f) Boiler Pressure | 270 | (g) Type of Stack | Bi-flue | (h) No. of Stacks | 1 | |
|
S. No. | Stack ID | Stack Height (m) | Stack Diameter at exit (m) | Exit Velocity of Stack Gas (m/s) | Exit Temperature of Stack Gas (Degree Celsius) |
---|
(1.) | 8.8 | 275 | 8.8 | 18.3 | 60 | |
|
2. Details of Fuel Linkage |
---|
S. No. | Type of Fuel | Type of Linkage | Other Type of Linkage | Details | Characteristics |
---|
(1.) | Coal | Linkage | | Source of Linkage : | NCL | Quantity of Linkage Granted : | 8400000 | Date of Linkage : | 10 Apr 2018 | Duration of Linkage : | 25 |
| Gross Calorific Value (Kcal/Kg) : | 3500 | Ash Content (%) : | 34 | Sulphur Content (%) : | 0.35 | Moisture (%) : | 13.7 | Mercury (mg/kg) : | 0 | Fixed Carbon (%) : | 29.7 | Volatile Matter (%) : | 23.12 |
| |
|
3. Details of Transportation of Fuel |
---|
S. No. | Fuel | Rail | Road | Pipe Conveyor | Conveyor Belt | Arial Ropeway | Other Mode of Transportation | Total Distance | Total Quantity |
---|
(1.) | Coal | Distance : | 0 | Quantity : | 8400000 |
| | | | | | 0 | 8400000 | |
TOTAL | Distance : 0 Quantity : 8400000 | Distance : 0 Quantity : 0 | Distance : 0 Quantity : 0 | Distance : 0 Quantity : 0 | Distance : 0 Quantity : 0 | Distance : 0 Quantity : 0 | |
|
4. | Details of Cooling System: | (a) Type of Cooling System | Air Cooled | (b) Type of Draft | Forced Draft | (c) Type of Air Circulation | Parallel Flow | (d) Cycle of Cooling (COC) | 5 | (e) Water Req. For Cooling (m3/day) | 195 | (f) Boiler Blow Down Temperature | 60 | |
|
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | Yes | (b)Name of the Court | NGT | (c)Name of the Sub Court | NGT Western Zone | (d)Case No. | 276 of 2013, 162 of 2015, 482 of 2015 | (e)Orders/Directions of the court ,if any and its relevance with the proposed project | Nil | (f)Case Details | 1. Ashwini Kumar Dubey Vs UOI & others 276 of 2013 | (g)Uploaded Court Order | Copy of Court Order | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | Yes | (b)Details of Direction Issued Under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act | Directions under Section 5 of the Environment (Protection) Act, 1986 tegarding compliance of emission limit notified vide notification No.S.0.3305 (E) dated 07.12.2015 | (c)Uploaded Copy of Direction Issued Under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act | Copy of Direction Issued | (d)Compliance status of the directions | Site visit completed | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | QCI/NABET/ENV/ACO/19/0957 Dated: 16th April, 2019 | (ii)Name of the EIA Consultant | Vimta Labs Ltd. | (iii)Address | 142, IDA, Phase-II, Cherlapally, Hyderabad–500051, Telangana State | (iv)Mobile No. | 9000711309 | (v)Landline No. | 0402726414 | (vi)Email Id | env@vimta.com | (vii)Category of Accreditation | A | (viii)Sector of Accreditation | Thermal Projects | (ix)Validity of Accreditation | 19 Nov 2020 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Detail Sought : NIL |
Additional Detail Sought: |
---|
Sno. | ADS Letter | Remarks | Date of ADS |
---|
1. | ADS Reply Letter | Point wise replies to additional information sought by MOEF&CC vide letter dated 22.10.2019 | 12 Feb 2020 | 2. | NA | ok | 10 Oct 2019 | |
| Undertaking |
| I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. |
| Name of Applicant | Vijay Prakash | Designation | Head of Deptt Env Engg | Name of Company (Applicant Name should not be given here) | NTPC Limited | Address | NTPC Engineering Office Complex
Sector-24, Noida |
|