Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Expansion of Mugoli Nirguda Extension Deep OC
(b)Name of the Company / Organisation Western Coalfields Limited
(c)Registered Address Coal Estate Civil lines, Nagpur-440001,Coal Estate Civil lines, Nagpur-440001,Nagpur,Maharashtra-440001
(d)Legal Status of the Company Central PSU
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Kaushik Chakraborty
(b)Designation (Owner/ Partner/ CEO) G.M (MINING)/ ENVIRONMENT.
(c)Address NIL
(d)Pin code 440001
(e)E-mail gmenvironment.wcl@coalindia.in
(f)STD Code. 712(f)Telephone No. 2510151
(g)Fax No. 2510151
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity1(a) Mining of minerals
Minor Activity2(b) Mineral beneficiation
(b)Category A
(c)Proposal Number IA/MH/CMIN/117098/2010
(d)Master Proposal Number(Single Window) SW/116933/2019
(e)EAC concerned (for category A Projects only) Coal Mining
(f)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. N 19°50'54.36", E 79°07'34.02", Mungoli Village, W
(b)Pincode 445307
(c)Bounded Latitudes (North)
From
Degree 19.8483333
Minutes
Second
From
Degree 19.9158333
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 79.0900000
Minutes
Second
From
Degree 79.1261111
Minutes
Second
(e)Survey of India Topo Sheet No. 56M/1
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 185.165
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 185.165
(j)Seismic Zone 2
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Maharashtra
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number J-11015/299/2010-IA.II(M)
(c)Date of Issue of TOR 16 Nov 2010
(f)Previous TOR Letter Copy of Previous TOR letter
(b)Date of Apply of EC 28 Sep 2019
(c)Date of Issue of EC 26 Feb 2020
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :07 Jan 2019
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :12 Feb 2019
Distance of Public Hearing Venue from the Proposed Project :1.3
Manoranjan Kendra, Kailash Nagar Colony, PO Sakhara, Tehsil Wani, Dist. Yavatmal
State :Maharashtra
District :Yavatmal
Tehsil :Wani
Village :Mungoli
3001. Rehabilitation of Mugoli Village 2. Land Compensation 3. Provision of employement 4. Pollution control measures 5. Plantation activities 6. Medical facilities for nearby villages 7. CSROthersAdditional Magistrate
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Nagpur
(iii)Letter No. F.No:3-19/2011/(ENV)/5637 dated 22/08/2019
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit Jun 26 2019 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)818.05 ha4.00.3754.375OthersMTPARoad,Rail
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)Shovel DumperShovel DumperShovel DumperShovel Dumper
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 05 May 2019
(iv)Valid Upto 31 Dec 2021
(v)File No. 72533
(vi)Application No. 72533
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 461.8319
(b) Funds Allocated for Environment Management (Capital) (in Crores) .9795
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 3.463
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 1.11
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 0
(b)Existing quantity of raw material/fuel 5964
(c)Total quantity of raw material/fuel 5964
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)POL5964OthersKL per AnnumOMCRoad0 Fuel Supply AgreementCopy of Linkage
(2.)Explosives3527321OthersKG per annumCIL vendorsRoad0 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 09 Nov 2015 To 31 Jan 2016
(b)Season Winter
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 6
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube953394.5300
(2.)PM2.5Micro Gram per Meter Cube52185260
(3.)SO2Micro Gram per Meter Cube19.86.319.1120
(4.)NOxMicro Gram per Meter Cube36.210.235.9120
    14.2.     No. of Ground Water monitoring locations : 2
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)Chloridesmg/l206292501000
(2.)Heavy MetalsCoppermg/l000.020.02
(3.)Heavy MetalsNickelmg/l000.020.02
(4.)Heavy MetalsArsenicmg/l000.010.01
(5.)Heavy MetalsAluminiummg/l000.030.2
(6.)pHOthers6.5 - 8.57.57.48.58.5
(7.)Total Hardnessmg/l922432200600
(8.)TSSmg/l18012000
(9.)TDSmg/l13408605002000
(10.)Fluoridemg/l0.50.41.01.5
(11.)Heavy MetalsManganesemg/l0.040.040.10.3
(12.)Heavy MetalsTotal Chromiummg/l0.010.010.050.05
(13.)Heavy MetalsLeadmg/l000.010.01
(14.)Heavy MetalsZincmg/l0.420.30515
(15.)Heavy MetalsCadmiummg/l000.010.01
(16.)Heavy MetalsSeleniummg/l000.010.01
(17.)Heavy MetalsArsenicmg/l000.010.01
    14.3.     No. of Surface Water monitoring locations : 2
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA7.57.3A
(2.)CODmg/l6.84.2A
(3.)DOmg/l6.86.4A
(4.)BODmg/l2.62.2A
    14.4.     No. of Ambient Noise monitoring locations : 6
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))52.947.875
(2.)Leq(Night)A-weighted decibels(dB(A))44.842.570
    14.5.     No. of Soil Sample Monitored locations : 3
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)N(Nitrogen)Kilogram per hectare323.4254.5
(2.)Electric ConductivityMillisiemens per Centimetre0.450.37
(3.)pH6.55.9
(4.)P(Phosphorus)Kilogram per hectare39.427.5
(5.)K(Potassium)Kilogram per hectare151.2126
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 12.55 To 8
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 1.50 To 11.45
(c)Whether Ground Water Intersection will be there ? Yes
(d)Upload Copy of Central Ground Water Authority Letter Copy of Central Ground Water Authority Letter
(e)Letter No. 21-4/343/MH/MIN/2016
(f)Date of Issue 06 Jun 2016
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater150500 Not Appliacble PipelineOthersPumping21-4/343/MH/MIN/201606 Jun 201615050
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Mine Discharge1638016380Sedimentation tanksDischarge into Surface Water Body133015050
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 16380
(b)Total Discharged Water (Kilolitre per Day) 15050
(c)Total Reused Water (Kilolitre per Day) 1330
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)SolidwasteOthersOverburden63200Tons0.1RoadOthersBackfilling into void & dumping on surface
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube660.7022.9288.94100
(2.)SO2Microgram per Meter Cube13.20.703.9617.580
(3.)NOxMicrogram per Meter Cube20.3806.0926.4080
(4.)PM2.5Microgram per Meter Cube360.7010.84760
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)NANA00PM100
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 4699
(b)Source MSETCL
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) NA
(e)Stack Height (in m) 0
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 497.30
(c)Government Land (ha.) 31.88
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 788.37
    Total Land (ha.) 1317.55
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 497.30
(b)Waste/Barren Land (ha.) 31.88
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 0
(e)Settlements (ha.) 0
(f)Industrial (ha.) 788.37
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : NA 0
    Total (ha.) 1317.5500000000002
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Quarry Area513.47
(2.)OB Dump Area445Including embankment & topsoil dump
(3.)Safety Zone226.48Including rationalisation
(4.)OthersInfrastrucutre, Railway, roads,80
(5.)Main Plant33Infrastructure & magazine
(6.)Township19.6Colony & Mugoli village relocation
Total (ha.) 1317.55
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)WLSNA0Not Applicable
(2.)ESAsNA0Not Applicable
(3.)Wildlife CorridorsNA0Not Applicable
(4.)NPANA0Not Applicable
(5.)ESZsNA0Not Applicable
(6.)Critically Polluted AreaNA0Not Applicable
(7.)CorridorsNA0Not Applicable
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestNA0Not Applicable
(2.)Defence InstallationsNA0Not Applicable
(3.)Archaeological SitesNA0Not Applicable
(4.)OthersNANA0Not Applicable
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 788.37
(b)Land yet to be acquired(Ha) 529.18
(c)Status of Land acquisition if not acquired Under process
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 1
(b)No. of Households 649
(c)No. of PDFs (Project Displaced Families) 649
(d)No. of PAFs (Project Affected Families) 649
(e)Funds Allocated for R&R(in INR) (in Lacs) 597.557
(f)Status of R&R In-Progress
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Wardha River and Penganga River
(ii)Direction of Water Bodies in Buffer Area North East
(iii)Distance of Water Bodies in Buffer Area 0
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 839
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 0
(e)No. of working days 330
(f)Total Manpower 839
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt93.5666.8760.3
(2.)Percentage of Total Project Area7.150.6057.7
(3.)No. of Plants23362016671301900750
(4.)Funds Allocated23362000200040000223402000
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)EnvironmentalConservation of coal. Also it will lead to positive environmental impacts like green cover, mine water utilization , etc.
(2.)SocialThe project will lead to development of roads, ancillary industries, Improvement in social & living standards by providing opportunities of direct & indirect employment to local community
(3.)FinancialA substantial percentage of population is dependent on mining industry directly or indirectly. Because of this mining project some of the local population may take direct employment but a substantial impact will be on creation of indirect job opportunities and employment.
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For Coal Mining
S. No.Item Details
     1.       No. of Mineral(s) to be Mined : 1
S. No.Mineral(s) to be Mined Major or Minor Mineral
(1.)CoalMajor
2.
Mine Capacity in ROM (Run of Mine) 4.375 MTPA
3.
Uploaded 500 meters Cluster Certificate from State Mines and Geology in case of minor minerals Copy of 500 meters Cluster Certificate from State Mines and Geology
4.
Mining Plan:
(a)Approval Letter No. WCL/BD/Sectt/BM-271/2015/2408
(b)Date of Approval 24 Nov 2014
(c)Approved Letter Copy of Approved Letter
(d)Approved By State Mining and Geology Department WCL Board
(e)Approved Mining Lease Area 1317.55
(f)Approved Capacity 4.375
5.
Technical Details:
(a)Total Geological Reserves (Million Ton) 59.45
(b)Mineable Reserves (Million Ton) 53.50
(c)Extractable Reserves(Million Ton) 45.85
(d)Percent(%) of Extraction 85.70
(e)Grade of Coal /Ore /Mineral G-9
(f)Stripping Ratio 1 : 6.12
(g)Category of Gaseousness (Only for Coal Mining, Others may Write NA) NA
(h)Average Gradient(Degree) 1 in 10 to 1 in 16.5
(i)Mining Method Opencast
(j)Life of Mine (Years) 15
6.
Details of Beneficiations:
(a)Whether it is proposed to install beneficiation plant/Coal washery within the mining lease area No
(b)Whether it is proposed to install crusher within the mining lease area No
7.
Details of Seams:
(a)Whether details of seam applicable Yes
(b)No. of seams 4
(c)Thickness of seams to be worked on 10.07
(d)Maximum Thickness of Seams (metres) 19.28
8.
Details of Mining Lease:
(a)Mining Lease Area (in Hectare) 1317.55
(b)Whether obtained Letter of Intent (LOI) from the state government ? No
(i)Reason thereof Not Applicable as land acquired under CB(A&D), Act
(c)Whether Lease Deed Executed ? No
(i)Reason thereof Not Applicable as land acquired under CB(A&D), Act
(d)Whether Lease Deed Renewed ? No
(i)Reason thereof Not Applicable as land acquired under CB(A&D), Act
9.
OB (Over Burden) Management:
(a) Details of External Dumps:
(i)No. of OB Dumps 2
(ii)Total Area (in Hectare) 172
(iii)Height (in meter) 90
(iv)Quantity (in Million Cubic meter) 59.58
(v)No. of year back fill up 2
(b) Details of Internal Dumps:
(i)No. of Internal Dumps 2
(ii)Total Area (in Hectare) 217.82
(iii)Height (in meter) 90
(iv)Quantity (in Million Cubic meter) 221.45
10.
Details of Topsoil Management:
(a)Quantity of Topsoil excavated during the entire life of the mine (in Million Cubic metre) 5
(b)Quantity of Topsoil proposed for utilization for reclamation during the entire life of the mine (in Million Cubic metre) 5
(c)Quantity of Topsoil proposed for utilization for other activities during the entire life of the mine (in Million Cubic metre) 0
11.
Details of Final Mine Void:
(a)Area (in Hectare) 295.65
(b)Depth (in meter) 150
(c)Volume (in Million Cubic meter) 345.48
12.
Details of Quarry:
(a)Final Void of 295.65 (hectare) at a Depth of 150 meter which is Proposed to be Converted into a Water Body.
(b)Total Quarry Area (ha) 513.47
13.
Details of Transportation:
(a)In Pit/Underground to Surface Dumper
(b)Surface to Siding/Loading Coal Transportation Trucks
(c)Transportation / Conveyor Details Coal Transportation Trucks
     14.      Details of Land Usage (Pre-Mining)
S. No.LAND USE Other LAND USEWITHIN ML AREA (Hectare)OUTSIDE ML AREA (Hectare)TOTAL (Hectare)
(1.)GRAZING LAND000
(2.)SURFACE WATER BODIES000
(3.)AGRICULTURE LAND435.3062497.3
(4.)FOREST LAND000
(5.)WASTE LAND31.88031.88
(6.)OTHERS(Specify)Land Already Acquired by WCL788.370788.37
(7.)SETTLEMENTS000
TOTAL1255.55621317.55
     15.      Details of Land Usage (Post-Mining)
S. No.LAND USE Other LAND USEPlantation (ha)Water Body (ha)Public Use (ha)Undisturbed (ha)Total
(1.)EXCAVATION/QUARRY0295.650295.65
(2.)TOP SOIL STORAGE0000
(3.)ROADS602430
(4.)GREEN BELT0000
(5.)VIRGIN AREA226.48080306.48
(6.)EXTERNAL OB DUMPS29500295
(7.)BUILT UP AREA (COLONY/OFFICE)8044.652.6
(8.)INTERNAL OB DUMPS217.8200217.82
(9.)OtherEmbankment & Railway siding70113120
TOTAL760.3295.65261.601317.55
16.
Details of Reclamation:
Total Afforestation Plan shall be Implemented Covering of Mining.
This will Include:
(a)External OB Dump(in hectare) 172
(b)Internal Dump(in hectare) 217.82
(c)Quarry(in hectare) 513.47
(d)Safety Zone(in hectare) 123.79
(e)Final Void of 295.65 (hectare) at a Depth of 150 meter which is Proposed to be Converted into a Water Body.
(f)Density of Tree Plantation per ha (in no.) 2500
(g)Others in ha (such as Excavation Area along ML Boundary, along Roads and Infrastructure, Embankment Area and in Township Located Outside the Lease etc) 385.29
(h)Total afforestation plant (in hectare) 760.30
17.
Status of progressive Mining Closure Plan:
Copy of Implementation of Various Activities as per Approved Progressive Mine Closure Plan Copy of Implementation of Various Activities as per Approved Progressive Mine Closure Plan
Any Deviation from the Approved Progressive Mine Closure Plan No
Total Area Excavated (in hectare) 273.25
Total Area Backfilled after Excavation (in hectare) 0
Total Area Reclaimed (in hectare) 25.95
     18.      Details of Actual Coal/ ORE Production vis-a-vis Sanctioned Capacity since the Inception:
S. No.Financial Year Sanctioned Capacity as per EC (MTPA)Sanctioned Capacity as per CTOSanctioned Capacity as per approved mining planActual Production Excess Production Beyond the EC / CTO/ Mining Plan Sanctioned Capacity (MTPA)
(1.)20184443.780
(2.)20174443.540
(3.)20114443.290
(4.)20124443.290
(5.)20134443.600
(6.)201444440
(7.)201544440
(8.)20164443.220
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1720/RA 0092 valid till 01.10.2020
(ii)Name of the EIA Consultant CMPDIL
(iii)Address Jaripatka, Nagpur
(iv)Mobile No. 8275970074
(v)Landline No. 0712264213
(vi)Email Id rdri4.cmpdi@coalindia.in
(vii)Category of Accreditation A
(viii)Sector of Accreditation Coal Mining
(ix)Validity of Accreditation 01 Oct 2020
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File NA
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
      Essential Detail Sought : NIL
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1. ADS Reply LetterSubmitted for kind perusal and needful compliance 16 Dec 2019
2. ADS Raise Letterpls provide the information as per enclosed letter. 04 Dec 2019
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantKaushik Chakraborty
DesignationG.M (MINING)/ ENVIRONMENT.
Name of Company (Applicant Name should not be given here)Western Coalfields Limited
AddressCoal Estate Civil lines, Nagpur-440001