Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) M/s. Insecticides India Limited
(b)Name of the Company / Organisation INSECTICIDES INDIA LIMITED
(c)Registered Address E-442,443 & 444, RIICO Industrial Area, Chopanki, Tal: Bhiwadi, Dist: Alwar,,Alwar,Rajasthan-301707
(d)Legal Status of the Company Others
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Mukesh Kumar
(b)Designation (Owner/ Partner/ CEO) GeneralManager
(c)Address E-442,443,444, RIICO Industrial Area, Chopanki, Bhiwadi, Alwar, Rajasthan,,Alwar,Alwar,Rajasthan-301707
(d)Pin code 301707
(e)E-mail mukeshiilindia@gmail.com
(f)STD Code. 1493(f)Telephone No. 298189
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity5(b) Pesticides industry and pesticide specific intermediates (excluding formulations)
Minor Activity
(b)Category A
(c)Proposal Number IA/RJ/IND2/116690/2019
(d)Master Proposal Number(Single Window) SW/116684/2019
(e)EAC concerned (for category A Projects only) Industrial Projects - 2
(f)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Plot No. E-442, 443 & 444
(b)Pincode 301707
(c)Bounded Latitudes (North)
From
Degree 28.152
Minutes
Second
From
Degree 28.153
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 76.877
Minutes
Second
From
Degree 76.878
Minutes
Second
(e)Survey of India Topo Sheet No. 53 D/12, 53 D/15 & 53 D/16
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 283
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 30
(j)Seismic Zone 2
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Rajasthan
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number J-11011/63/2009-IA-11(1)
(c)Date of Issue of TOR 18 Feb 2019
(f)Previous TOR Letter Copy of Previous TOR letter
(b)Date of Apply of EC 30 Sep 2019
(c)Date of Issue of EC 17 Aug 2020
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason Located in Notified Industrial area of RIICO, Chop
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Lucknow
(iii)Letter No. IV/ENV/R/Ind-107/740/2005/322
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit May 29 2019 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Capacity180075509350Tons per Annum(TPA)Road
(2.)Area1.195801.1958Hectares(ha)Road
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)Nutsche Filter2245 KL
(2.)Pulverizer101100 Kg/hr
(3.)S. S. Reactor8917Capacity 10 KL
(4.)Glass line reactor358Capacity 5 KL
(5.)M S Reactor112Capacity 5 KL
(6.)Centrifuge SS Basket22448" Dia
(7.)SS tanks423072Capacity 2-5 KL
(8.)Glass lined tanks152035Capacity 2-5 KL
(9.)Ejectors111021NA
(10.)Sparkle filter358NA
(11.)Glass line reactor5914Capacity 6.3 KL
(12.)Agitated nutsche filter drier4610Capacity 5 KL
(13.)RVD369Capacity 1 to 5 KL
(14.)S. S. Reactor131326Capacity 6 KL
(15.)S. S. Reactor6612Capacity 5 KL
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 07 Jan 2016
(iv)Valid Upto 31 May 2018
(v)File No. F(PLG)/Alwar(Alwar)/36(1)/2015-2016/6316-6318
(vi)Application No. 2015-2016/PDF/21
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 45.6708
(b) Funds Allocated for Environment Management (Capital) (in Crores) 9.4337
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.2010
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 9.4337
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 9250
(b)Existing quantity of raw material/fuel 22500
(c)Total quantity of raw material/fuel 31750
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Toluene369.3Tons per AnnumNearby areaRoad8 OthersRaw materialCopy of Linkage
(2.)Methanol738.9Tons per AnnumNearby areaRoad9 OthersRaw materialCopy of Linkage
(3.)Wood3OthersMT/hrNearby areaRoad7 Fuel Supply AgreementCopy of Linkage
(4.)diesel85OthersLit./hrNearby areaRoad8 Fuel Supply AgreementCopy of Linkage
(5.)Briquettes12OthersMT/DayNearby areaRoad8 Fuel Supply AgreementCopy of Linkage
(6.)ethyl alcohol756Tons per AnnumNearby areaRoad8 OthersRaw materialCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Dec 2018 To 28 Feb 2019
(b)Season Winter
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 9
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)SO2Micro Gram per Meter Cube11.091.410.0480
(2.)PM2.5Micro Gram per Meter Cube58.3336.9245.1860
(3.)NOxMicro Gram per Meter Cube15.596.0912.0880
(4.)PM10Micro Gram per Meter Cube99.1862.1272.15100
(5.)OthersO3Micro Gram per Meter Cube21.9512.3418.42100
    14.2.     No. of Ground Water monitoring locations : 9
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)TSSmg/l25250100
(2.)Total Hardnessmg/l428120300600
(3.)Fluoridemg/l1.490.3111.5
(4.)OthersSulfatesmg/l30.395.78200400
(5.)pHNA7.696.936.58.5
(6.)TDSmg/l9464805002000
(7.)Chloridesmg/l234182501000
(8.)Heavy MetalsZincmg/l6.020.11515
    14.3.     No. of Surface Water monitoring locations : 0
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA00A
(2.)BODmg/l00A
(3.)DOmg/l00A
(4.)CODmg/l00A
(5.)OthersChloridesmg/l00A
    14.4.     No. of Ambient Noise monitoring locations : 9
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))74.946.775
(2.)Leq(Night)A-weighted decibels(dB(A))64.831.165
    14.5.     No. of Soil Sample Monitored locations : 9
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pH8.667.32
(2.)N(Nitrogen)Milligram per Kilogram232.3
(3.)K(Potassium)Milligram per Kilogram10.01
(4.)Electric ConductivityMillisiemens per Centimetre5142
(5.)P(Phosphorus)Milligram per Kilogram1.10.02
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 50 To 75
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 60 To 85
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersRIICO Water Supply1888Copy of Permission LetterPipelineOthersPipelineR.M./(WS)/BWD/533814 Oct 2005188
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Industrial & Domestic136136ETP & MEEReuse within the Plant & Recycling,OthersRe-use in plant premises1324
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 136
(b)Total Discharged Water (Kilolitre per Day) 4
(c)Total Reused Water (Kilolitre per Day) 132
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)MEE SaltHazardous Waste (as per Hazardous and Other Waste Management rules 2016)1080Tons8RoadTreatment, Storage and Disposal Facility(TSDF)
(2.)Incineration AshIndustrial Waste16Tons8RoadTreatment, Storage and Disposal Facility(TSDF)
(3.)Drums & Containers, Bags & LinersIndustrial Waste21Tons18RoadAuthorized Recyclers
(4.)Process ResidueHazardous Waste (as per Hazardous and Other Waste Management rules 2016)399.3Tons8RoadOthersIncineration or CHWIF of UCCI, Udaipur
(5.)Used Lubrication OilIndustrial Waste1.45Tons15RoadAuthorized Recyclers
(6.)ETP SludgeHazardous Waste (as per Hazardous and Other Waste Management rules 2016)47.5Tons8RoadTreatment, Storage and Disposal Facility(TSDF)
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)NOxMicrogram per Meter Cube13.760.380.013.7780
(2.)PM10Microgram per Meter Cube69.40.380.7570.2100
(3.)PM2.5Microgram per Meter Cube38.70.380.439.1160
(4.)SO2Microgram per Meter Cube8.350.380.0098.480
(5.)Others(Specify)HBrMicrogram per Meter Cube0.0000.380.0070.008--
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)DG Set (3 Nos.)Diesel60.15SO2262
(2.)DG Set (3 Nos.)Diesel60.15NOx94
(3.)Boiler (2 TPH)Wood301PM10150
(4.)Boiler (2 TPH)Wood301SO2262
(5.)Boiler (2 TPH)Wood301NOx94
(6.)DG Set (3 Nos.)Diesel60.15PM10150
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 860
(b)Source JVVNL
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) DG Set * 3 Nos.
(e)Stack Height (in m) 7
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 1.1958
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 1.1958
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 18810.22
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 89.28
(e)Settlements (ha.) 6996.04
(f)Industrial (ha.) 0
(g)Forest (ha.) 5146.36
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : Scrubland 373.6
    Total (ha.) 31415.5
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Main Plant0.4260
(2.)Green belt0.4
(3.)OthersOpen Area0.24
(4.)Built Up Area0.1298ETP & Utility area
Total (ha.) 1.1958
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)CorridorsNA0NA
(2.)Critically Polluted AreaNA0NA
(3.)ESAsNA0NA
(4.)NPANA0NA
(5.)WLSNA0NA
(6.)ESZsNA0NA
(7.)Wildlife CorridorsNA0NA
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestNA0NA
(2.)Archaeological SitesNA0NA
(3.)OthersNANA0NA
(4.)Defence InstallationsNA0NA
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 1.1958
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired 0
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Yet To Start
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? No
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 160
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 0
(e)No. of working days 330
(f)Total Manpower 160
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt400004000
(2.)Percentage of Total Project Area33.45033.45
(3.)No. of Plants100001000
(4.)Funds Allocated200000002000000
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialProvision of employment to nearby people
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. Stay Order Against QCI NABET
(ii)Name of the EIA Consultant Aqua-Air Environmental Engineers Pvt. Ltd.
(iii)Address 403, Centre Point, Nr. Kadiwala School, Ring Road, Surat- 395002
(iv)Mobile No. 9904433995
(v)Landline No. 0261246124
(vi)Email Id aqua_eia@yahoo.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 12 Feb 2022
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAMay kindly peruse the certified compliance report submitted by regional office. There are certain non-compliance and observations pointed out by the regional office. You are requested to to submit action taken report on the observations of the Regional officer 30 Sep 2019
2.NAThe correction have been made as per the instruction received 30 Sep 2019
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1. ADS Reply LetterReport from SPCB, Rajasthan regarding factual status of the project is obtained and is attached as Additional Document. 28 Jul 2020
2. ADS Reply LetterReport from SPCB, Rajasthan regarding factual status of the project is obtained and is attached as Additional Document. 28 Jul 2020
3.NAThe Proposal of EC was considered by the EAC in its meeting held during November 20-22, 2019 & January 21-23, 2020. The matter was examined in the Ministry and it is noted that the CPCB has visited the unit on January 11th 2020 and verified all the relevant documents along with EMS compliance. The Committee deliberated the CPCB repot and found in order. However the report from SPCB is still awaited. In view of the above, SPCB, Rajasthan is kindly requested to provide the report for further necessary action by the Ministry. 05 Apr 2020
4.NAThe Proposal of EC was considered by the EAC in its meeting held during November 20-22, 2019 & January 21-23, 2020. The matter was examined in the Ministry and it is noted that the CPCB has visited the unit on January 11th 2020 and verified all the relevant documents along with EMS compliance. The Committee deliberated the CPCB repot and found in order. However the report from SPCB is still awaited. In view of the above, SPCB, Rajasthan is kindly requested to provide the report for further necessary action by the Ministry. 05 Apr 2020
5. ADS Reply LetterAdditional Details Sought, Revised Form-2 & EIA Report which conforms to Appendix-III of the EIA Notification, 2006 is attached as additional document. 06 Jan 2020
6.NAThe EAC, during deliberations noted that the project details mentioned in the EIA report were not consistent with that presented during the meeting. The EAC, after detailed deliberations has asked for clarification/inputs, in respect of the following:- (i) EIA report to be revised as per the terms of reference granted for the project, and shall conform to Appendix III of the EIA Notification, 2006. (ii) EAC noted that PP has not submitted adequately TOR compliance and PP needs to be resubmit the TOR compliance adequately. (iii) Action plan in view of the project site being in Critically Polluted Area. (iv) PP needs to prepare the species specific conservation plan for schedule-I species along with budgetary allocation and PP to take approval for the Wildlife conservation and management plan from CWLW State Government. (v) Details of courts/NGT cases, if any, on the project area or against the project proponent. (vi) Details of existing production with supporting documents. (vii) Considering complaint against the project proponent regarding production without prior permission, pollution etc, report from SPCB and CPCB on the factual status. (viii) Revised water balance with details of total water and fresh water requirement, and permission from concerned regulatory authority. (ix) Effluent treatment mechanism with plan for Zero Liquid Discharge. (x) Onsite emergency plan as per MSIHC Rules. The proposal was accordingly deferred for the needful. 10 Dec 2019
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantMukesh Kumar
DesignationGeneralManager
Name of Company (Applicant Name should not be given here)INSECTICIDES INDIA LIMITED
AddressE-442,443 & 444, RIICO Industrial Area, Chopanki, Tal: Bhiwadi, Dist: Alwar