Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) PROPOSED DYES MANUFACTURING UNIT
(b)Name of the Company / Organisation SHREE SAI INDUSTRIES
(c)Registered Address Survey No. 358, Vaduchi Mandir Road, Lunej Khambhat, Anand, Gujarat,,Anand,Gujarat-388620
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Sureshbhai Motiram Patel
(b)Designation (Owner/ Partner/ CEO) Proprietor
(c)Address 132,Karma Estate, Trikampura Patia,Phase-III, GIDC, Vatva,,Daskroi,Ahmedabad,Gujarat-382445
(d)Pin code 382445
(e)E-mail smppatel1968@gmail.com
(f)STD Code. 79(f)Telephone No. 22147550
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
Minor Activity
(b)Category A
(c)Proposal Number IA/GJ/IND2/91773/2019
(d)Master Proposal Number(Single Window) SW/116534/2019
(e)EAC concerned (for category A Projects only) Industrial Projects - 2
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Survey No. 358, Vaduchi Mandir Road, Village: Lune
(b)Pincode 388620
(c)Bounded Latitudes (North)
From
Degree 22.344313
Minutes
Second
From
Degree 22.344916
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 72.57962
Minutes
Second
From
Degree 72.580106
Minutes
Second
(e)Survey of India Topo Sheet No. Environmental Information Center
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 9
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 6.2
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Gujarat
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)GujaratAnandKhambhat
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number IA-J-11011/19/2019-IA-II(I)
(b)Date of Apply of TOR 21 Jan 2019
(c)Date of Issue of TOR / Standard ToR 26 Feb 2019
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :12 Jun 2019
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :15 Jul 2019
Distance of Public Hearing Venue from the Proposed Project :5
22 Gaam Levuva Patidar Samaj Ni Wadi, Press Road
State :Gujarat
District :Anand
Tehsil :Khambhat
Village :Khambhat
119Local Employment, Tree Plantation, Infrastructure facility, etc...District Collector
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Manufacturing PlantDyes65 MT/Month
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Dyes780Tons per AnnumRoad
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 31 May 2019
(iv)Valid Upto 30 May 2026
(v)File No. GPCB/AND-CTE-290/PCB ID-70091
(vi)Application No. GPCB/AND-CTE-290/PCB ID-70091
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 2
(b) Funds Allocated for Environment Management (Capital) (in Crores) 0.5
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.04
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.6
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 1200
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 1200
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Coal720Tons per AnnumLocal MarketRoad15 Open MarketCopy of Linkage
(2.)Sulfuric Acid (98%)100Tons per AnnumLocal MarketRoad15 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Oct 2017 To 31 Dec 2017
(b)Season Post-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 10
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)NOxMicro Gram per Meter Cube17.0911.941780
(2.)SO2Micro Gram per Meter Cube12.928.571280
(3.)OthersAmmoniaMicro Gram per Meter Cube000400
(4.)PM2.5Micro Gram per Meter Cube47.2840.354760
(5.)PM10Micro Gram per Meter Cube78.8369.3578100
    14.2.     No. of Ground Water monitoring locations : 10
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)TSSmg/l52250100
(2.)Heavy MetalsZincmg/l0.150515
(3.)pHNA9.078.16.58.5
(4.)Fluoridemg/l0011.5
(5.)TDSmg/l19204225002100
(6.)Total Hardnessmg/l47658.06300600
(7.)Chloridesmg/l617.641102501000
    14.3.     No. of Surface Water monitoring locations : 4
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA8.517.89A
(2.)DOmg/l6.330.41A
(3.)BODmg/l13.8911.24A
(4.)CODmg/l13.8911.24A
    14.4.     No. of Ambient Noise monitoring locations : 10
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))554755
(2.)Leq(Night)A-weighted decibels(dB(A))453845
    14.5.     No. of Soil Sample Monitored locations : 10
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pH9.257.69
(2.)N(Nitrogen)Milligram per Kilogram26.80.2
(3.)P(Phosphorus)Milligram per Kilogram4.451.26
(4.)K(Potassium)Milligram per Kilogram27.59.01
(5.)Electric ConductivityMillisiemens per Centimetre53.532.1
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 100 To 50
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 80 To 90
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater12.60Copy of Permission LetterPipelineTube Well21-4/5342/GJ/IND/201930 Aug 201912.6
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic1.62Soak PitOthersSoak Pit01.6
(2.)Industrial2.55ETP, Spray DryerOthersEvaporated02.5
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 4.1
(b)Total Discharged Water (Kilolitre per Day) 4.1
(c)Total Reused Water (Kilolitre per Day) 0
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Spray Dryer SaltIndustrial Waste216Tons50RoadTreatment, Storage and Disposal Facility(TSDF)
(2.)Sodium sulphate solutionIndustrial Waste360Kilolitre10RoadOthersrule 9
(3.)ETP SludgeHazardous Waste (as per Hazardous and Other Waste Management rules 2016)180Tons50RoadTreatment, Storage and Disposal Facility(TSDF)
(4.)used oilIndustrial Waste1.2Kilolitre10RoadOthersregistered reprocessor
(5.)Discarded DrumsIndustrial Waste120Tons10RoadAuthorized Recyclers
(6.)Dilute Sulfuric AcidIndustrial Waste1120Kilolitre10RoadOthersrule 9
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM2.5Microgram per Meter Cube41.61.270.141.860
(2.)PM10Microgram per Meter Cube72.81.270.172.9100
(3.)SO2Microgram per Meter Cube8.571.270.098.6780
(4.)NOxMicrogram per Meter Cube12.451.270.0312.580
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)DG SetDiesel110.1PM10100
(2.)BoilerCoal120.3PM10100
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 150
(b)Source MGVCL
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 50 KVA
(e)Stack Height (in m) 11
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 0.24
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 0.24
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 0.9368
(b)Waste/Barren Land (ha.) 0.0775
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 0.0158
(e)Settlements (ha.) 0.01
(f)Industrial (ha.) 0.0075
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0.0
(i)Marine Area (ha.) 0.014
(j)Others (ha.) : Scrubs, River, Open Vegetation, etc 2.0791
    Total (ha.) 3.1407
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Green belt720--
(2.)Main Plant1370--
(3.)OthersOpen Area & Road310--
Total (ha.) 2400
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)WLS--0--
(2.)NPA--0--
(3.)ESAs--0--
(4.)ESZs--0--
(5.)Corridors--0--
(6.)Wildlife Corridors--0--
(7.)Critically Polluted Area--0--
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Defence Installations--0--
(2.)Forest--00--
(3.)Archaeological Sites--0--
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 0.24
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired Land is already acquired
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? No
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 5
(b)Permanent Employment-During Operation 5
(c)Temporary Employment- During Construction 5
(d)Temporary Employment- During Operation 5
(e)No. of working days 345
(f)Total Manpower 20
32.
Green Belt in Ha:
(a)Total Area of Green Belt 0.072
(b)Percentage of Total Project Area 30.00
(c)No. of Plants to be Planted 150
(d)Funds Allocated for Plantation 225000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)FinancialCSR & CER
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. Stay oder against NABET/QCI
(ii)Name of the EIA Consultant Aqua Air Environmental Engineers Pvt. Ltd.
(iii)Address 403, Center Point, Nr. Kadiwala School, Ring Road, Surat– 395002, Gujarat, India.
(iv)Mobile No. 8155016995
(v)Landline No. 0261277380
(vi)Email Id aqua_eia@yahoo.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 07 Apr 2016
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File NA
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
      Essential Detail Sought : NIL
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantSureshbhai Motiram Patel
DesignationProprietor
Name of Company (Applicant Name should not be given here)SHREE SAI INDUSTRIES
AddressSurvey No. 358, Vaduchi Mandir Road, Lunej Khambhat, Anand, Gujarat
Print