Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Expansion of Bulk drug and Intermediates manufacturing unit by M/s. Dasami Lab Pvt. Ltd.
(b)Name of the Company / Organisation DASAMI LAB PVT LTD
(c)Registered Address Dasami Lab Pvt. Ltd.,Sy. No. 404, 405, 407, 408, 409 and 410, Veliminedu Village, Chityal Mandal, Nalgonda District, Telangana,Nalgonda,Telangana-508114
(d)Legal Status of the Company Central Government
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Vasudeva Reddy M
(b)Designation (Owner/ Partner/ CEO) GMCorporateEHS
(c)Address Dasami Lab Pvt. Ltd.,Sy. No.s 404, 405, 407, 408, 409 and 410, Veliminedu Village, Chityal Mandal, Nalgonda District, Telangana,Chityala,Nalgonda,Telangana-508114
(d)Pin code 508114
(e)E-mail vasudevareddy.m@heterodrugs.com
(f)STD Code. 40(f)Telephone No. 23710405
(g)Fax No. 23700405
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
Minor Activity
(b)Category A
(c)Proposal Number IA/TG/IND2/115224/2016
(d)Master Proposal Number(Single Window) SW/115222/2019
(e)EAC concerned (for category A Projects only) Industrial Projects - 3
(f)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Sy. No. 404, 405, 407, 408, 409 and 410
(b)Pincode 508114
(c)Bounded Latitudes (North)
From
Degree 17.132105
Minutes
Second
From
Degree 17.133794
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 79.025114
Minutes
Second
From
Degree 79.025935
Minutes
Second
(e)Survey of India Topo Sheet No. EaaM15, E44M16, E44N3 and E44N4
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 334
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 220
(j)Seismic Zone 2
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Telangana
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number J-11011/57/2016-IA II (I)
(b)Date of Apply of TOR 27 Jan 2016
(c)Date of Issue of TOR / Standard ToR 08 Jun 2017
(d)Date of Apply of EC 06 Jun 2007
(e)Date of Issue of EC 21 Feb 2008
(f)Previous TOR Letter Copy of Previous TOR letter
(g)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :13 Aug 2018
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :14 Sep 2018
Distance of Public Hearing Venue from the Proposed Project :0.1
Near the existing plant area
State :Telangana
District :Nalgonda
Tehsil :Chityala
Village :Veliminedu
450Employement Generatin Pollution control measures Village developmentOthersJoint Collector & Addl. District Magistrate
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Chennai
(iii)Letter No. EP/12.1/2017-18/1/TE/1131
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit Jun 6 2019 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Clopidogrel Hydrogen Sulfate5510OthersTPMRoad
(2.)Drotaverine HCl2.50.53OthersTPMRoad
(3.)Omeprazole505OthersTPMRoad
(4.)Rampril527OthersTPMRoad
(5.)Sparfloxacin41620OthersTPMRoad
(6.)Tramadol HCl5712OthersTPMRoad
(7.)Amlodipine Besylate02020OthersTPMRoad
(8.)Bocepravir066OthersTPMRoad
(9.)Bupropion HCl02020OthersTPMRoad
(10.)Dexlansoprazole055OthersTPMRoad
(11.)Eslicarbazapine022OthersTPMRoad
(12.)Glimepride033OthersTPMRoad
(13.)Mesalamine077OthersTPMRoad
(14.)Sevelamir HCl02929OthersTPMRoad
(15.)Ticagrelor011OthersTPMRoad
(16.)Valagancyclovir HCl022OthersTPMRoad
(17.)Anastrozole022OthersTPMRoad
(18.)Bendamustine HCl02.52.5OthersTPMRoad
(19.)Bexarotene033OthersTPMRoad
(20.)Bicalutamide055OthersTPMRoad
(21.)Cyclophosphamide022OthersTPMRoad
(22.)Emtricitabine03030OthersTPMRoad
(23.)Erlotinib HCl044OthersTPMRoad
(24.)Lansoprazole088OthersTPMRoad
(25.)Lomitapide022OthersTPMRoad
(26.)Nebumitone01010OthersTPMRoad
(27.)Posaconazole077OthersTPMRoad
(28.)Abiraterone Acetate011OthersTPMRoad
(29.)Capecitabine022OthersTPMRoad
(30.)Irinotrcan HCl01414OthersTPMRoad
(31.)Letrozole02.52.5OthersTPMRoad
(32.)Nilotinib HCl022OthersTPMRoad
(33.)Pazopanib HCl022OthersTPMRoad
(34.)Pemetrexed Disodium00.50.5OthersTPMRoad
(35.)Sorafenib Tosylate066OthersTOMRoad
(36.)Sunitinib Malate066OthersTPMRoad
(37.)Dalfampridine01717OthersTPMRoad
(38.)Telapravir055OthersTPMRoad
(39.)Bortezomib00.50.5OthersTPMRoad
(40.)Dasatinib022OthersTPMRoad
(41.)Gefitinib022OthersTPMRoad
(42.)Carvedilol52530OthersTPMRoad
(43.)Duloxetine HCl31215OthersTPMRoad
(44.)Aprimilast033OthersTPMRoad
(45.)Colisevelam066OthersTPMRoad
(46.)Divalproex Sodium01515OthersTPMRoad
(47.)Fexofenadine HCl01010OthersTPMRoad
(48.)Piperquine Phosphate055OthersTPMRoad
(49.)Ranolazine01010OthersTPMRoad
(50.)Valacyclovir066OthersTPMRoad
(51.)Carboplatin055OthersTPMRoad
(52.)Cisplatin022OthersTPMRoad
(53.)Gemacitabine HCl011OthersTPMRoad
(54.)Imatinib Mesylate01616OthersTPMRoad
(55.)Lapatinib Ditosylate Monohydrate022OthersTPMRoad
(56.)Oxaliplatin044OthersTPMRoad
(57.)Temozolomide011OthersTPMRoad
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)API Bulk Drug and Intermediates15406421Tons Per Month
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 26 Mar 2016
(iv)Valid Upto 30 Apr 2020
(v)File No. TSPCB/RCP/NLG/HO/CFO/2016 02
(vi)Application No. TSPCB/RCP/NLG/HO/CFO/2016 02
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 45
(b) Funds Allocated for Environment Management (Capital) (in Crores) 11.854
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 1.11
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 15.475
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 506
(b)Existing quantity of raw material/fuel 18
(c)Total quantity of raw material/fuel 524
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Synthetic Organic and Inorganic Chemicals6312Tons per AnnumIndigenousRoad200 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Mar 2017 To 01 Jun 2017
(b)Season Summer
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 10
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM2.5Micro Gram per Meter Cube24112360
(2.)SO2Micro Gram per Meter Cube1291280
(3.)NOxMicro Gram per Meter Cube1291180
(4.)PM10Micro Gram per Meter Cube563254100
(5.)OthersVOC in PPMNA1.20.31.1NA
    14.2.     No. of Ground Water monitoring locations : 10
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)Total Hardnessmg/l790130200200
(2.)Fluoridemg/l0.870.411
(3.)Chloridesmg/l36574250250
(4.)pHNA7.8777
(5.)TSSmg/l1310100100
(6.)TDSmg/l1081327500500
    14.3.     No. of Surface Water monitoring locations : 2
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA6.676E
(2.)BODmg/l43.7B
(3.)CODmg/l1311B
(4.)DOmg/l4.44.3B
    14.4.     No. of Ambient Noise monitoring locations : 10
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))534455
(2.)Leq(Night)A-weighted decibels(dB(A))403445
    14.5.     No. of Soil Sample Monitored locations : 10
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)Electric ConductivityOthersds/m0.30.04
(2.)N(Nitrogen)Percent0.290.017
(3.)K(Potassium)Milligram per Kilogram338239
(4.)P(Phosphorus)Percent0.760.32
(5.)pH86.8
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 2.3 To 26
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 0.54 To 16
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersMission Bhagiratha272.73100Copy of Permission LetterPipelineOthersPipelineT1/DEE2/MB Grid/Bulk Water Connections/2017-1807 Feb 2019300
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)High TDS and High COD Stream171.07250Sent to Stripper. Stripper condensate shall be disposed to cement industries for co-processing/TSDF. Stripper bottom is sent to MEE followed by AFTD. Condensate from MEE shall be sent to biological treatment plant followed by RO. RO rejects are sent to MEE and permeate is reused in cooling towers, boiler make-up and scrubbersOthersSent to ZLD System15516.07
(2.)Low TDS and Low COD Stream66250Sent to biological treatment system followed by RO. RO permeate reused for cooling towers, boiler make-up and scrubbers. RO rejects are sent to MEE.OthersSent to ZLD System606
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 237.07
(b)Total Discharged Water (Kilolitre per Day) 22.07
(c)Total Reused Water (Kilolitre per Day) 215
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Solvent ResidueHazardous Waste (as per Hazardous and Other Waste Management rules 2016)2332.8Tons36RoadOthersSent to Cement plants for co-processing or TSDF
(2.)Stripper DistillateHazardous Waste (as per Hazardous and Other Waste Management rules 2016)972Tons36RoadOthersSent to Cement plants for co-processing or TSDF
(3.)Spent CarbonHazardous Waste (as per Hazardous and Other Waste Management rules 2016)356.4Tons36RoadOthersSent to Cement plants for co-processing or TSDF
(4.)Evaporation SaltsHazardous Waste (as per Hazardous and Other Waste Management rules 2016)2592Tons42RoadTreatment, Storage and Disposal Facility(TSDF)
(5.)Inorganic residueHazardous Waste (as per Hazardous and Other Waste Management rules 2016)1245.6Tons42RoadTreatment, Storage and Disposal Facility(TSDF)
(6.)Catalyst and HyflowHazardous Waste (as per Hazardous and Other Waste Management rules 2016)67.5Tons42RoadTreatment, Storage and Disposal Facility(TSDF)
(7.)Mixed Spent SolventsHazardous Waste (as per Hazardous and Other Waste Management rules 2016)5400Tons42RoadOthersSent to authorized recovery units
(8.)ETP SludgeHazardous Waste (as per Hazardous and Other Waste Management rules 2016)126Tons42RoadTreatment, Storage and Disposal Facility(TSDF)
(9.)Organic residueHazardous Waste (as per Hazardous and Other Waste Management rules 2016)2235.6Tons36RoadOthersSent to Cement plants for co-processing or TSDF
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM2.5Microgram per Meter Cube231.60.523.5260
(2.)SO2Microgram per Meter Cube121.63.315.3680
(3.)NOxMicrogram per Meter Cube121.64.216.2880
(4.)PM10Microgram per Meter Cube541.61.155.16100
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)1 x 5 TPHCoal301.3NOx1.2 g/s
(2.)2 x10TPH BoilerCoal351.5PM100.85 g/s
(3.)2 x 10 TPH BoilerCoal351.5SO21.8 g/s
(4.)2 x 10 TPH BoilerCoal351.5NOx2.1 g/s
(5.)1 x 5 TPH BoilerCoal301.3SO20.87 g/s
(6.)1 x 5 TPH BoilerCoal301.3PM100.5 g/s
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 4000
(b)Source TSSPDCL
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 3 x 1000 kVA and 1 x 380 kVA
(e)Stack Height (in m) 10
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 20.64
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 20.64
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 0
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 0
(e)Settlements (ha.) 0
(f)Industrial (ha.) 20.64
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : 0 0
    Total (ha.) 20.64
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Green belt7.2835.3% of Total site area
Total (ha.) 7.28
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)CorridorsNA0No Corridors within 10 km Study Area
(2.)WLSNA0No WLS within 10 km of Study Area
(3.)ESAsNA0No ESAs within 10 km Study Area
(4.)ESZsNA0No ESZs within 10 km Study Area
(5.)Critically Polluted AreaPatancheru and Bollaram79Critically Polluted Area
(6.)NPANA0No NPA within 10 km of Study Area
(7.)Wildlife CorridorsNA0No Wildlife Corridors within 10 km Study Area
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Archaeological SitesNA0No Archaeological Sites within 10 km Study Area
(2.)Defence InstallationsNA0No Defence Installations within 10 km Study Area
(3.)ForestChityal RF6in East
(4.)OthersReserve ForestShivanenigudem RF9in Northeast
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 20.64
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired Completed
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Seasonal nala Chinna Vagu
(ii)Direction of Water Bodies in Buffer Area South West
(iii)Distance of Water Bodies in Buffer Area 6.5
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 50
(b)Permanent Employment-During Operation 350
(c)Temporary Employment- During Construction 30
(d)Temporary Employment- During Operation 20
(e)No. of working days 360
(f)Total Manpower 450
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt0.976.317.279999999999999
(2.)Percentage of Total Project Area332.335.3
(3.)No. of Plants85035504400
(4.)Funds Allocated61218
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialEmployement Potential
(2.)FinancialReduce imports of intermediates
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For Industrial Projects - 3
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1619/RA/0077
(ii)Name of the EIA Consultant Team Labs and Consultants
(iii)Address TEAM Labs and Consultants B-115-117 & 509, Annapurna Block, Aditya Enclave, Ameerpet, Hyderabad-500 038
(iv)Mobile No. 0402374855
(v)Landline No. 0402374855
(vi)Email Id teamlabs@gmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 3
(ix)Validity of Accreditation 01 Dec 2019
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
      Essential Detail Sought : NIL
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1.NA