Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Manuguru opencast coal mining project
(b)Name of the Company / Organisation The Singareni Collieries Company Limited
(c)Registered Address M/s. Singareni Collieries Company Limited PO: Kothagudem Collieries - 507 101 Dist: KHAMMAM, T.Sr,,Khammam,Telangana-507101
(d)Legal Status of the Company State Government
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Shri G Venkateswara Reddy
(b)Designation (Owner/ Partner/ CEO) Director (Planning & Projects)
(c)Address Kothagudem P.O -507101 Bhadradri Kothagudem District,,,Bhadradri Kothagudem,Telangana-507101
(d)Pin code 507101
(e)E-mail gm_env@scclmines.com
(f)STD Code. 8744(f)Telephone No. 243059
(g)Fax No. 08744244115
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity1(a) Mining of minerals
Minor Activity
(b)Category A
(c)Proposal Number IA/TG/CMIN/114765/2019
(d)Master Proposal Number(Single Window) SW/114745/2019
(e)EAC concerned (for category A Projects only) Coal Mining
(f)Project Type Expansion under para 7(ii)
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Govt. Land: Manuguru (V) – Sy.No. 12,341,404,423,8
(b)Pincode 504231
(c)Bounded Latitudes (North)
From
Degree 175748
Minutes
Second
From
Degree 175919
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 804858
Minutes
Second
From
Degree 805111
Minutes
Second
(e)Survey of India Topo Sheet No. 65 C/13
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 781.00
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 60
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Telangana
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)TelanganaBhadradri KothagudemManuguruRajupeta
6.
Details of Terms of Reference (ToR)/EC: Not Applicable
4.
Whether the Project Exempted from Public Hearing? Details Not Applicable
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Chennai
(iii)Letter No. EP/12.1/770/A.P
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit Jul 17 2019 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)668.42 ha1.50.62.1OthersMillion TonnesRoad,Conveyor Belt
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)coal mining with Shovel and dumper1.5 MTPA in 668.4 ha with shovel and dumper2.1 MTPA in 668.4 ha with shovel and dumper2.1 MTPA in 668.4 ha with shovel and dumper40 % capacity expansion
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 13 Mar 2017
(iv)Valid Upto 31 Oct 2021
(v)File No. 17052553274
(vi)Application No. 17052553274
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 415.70
(b) Funds Allocated for Environment Management (Capital) (in Crores) 8.20
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 3.1177
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 6.5
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 6499.67
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 6499.67
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Explosives6499.67Tons per AnnumPurchasing from the explosive companiesRoad210 MoUCopy of Linkage
(2.)Power0.803OthersMVA132 KV substation of ManuguruOthersOver head Transmission4 Fuel Supply AgreementCopy of Linkage
(3.)Diesel9191.19Kilo Litre per DayCompany established oil bunks at siteRoad210 MoUCopy of Linkage
(4.)Water1680Kilo Litre per DayMIne dischargeOthersPipe line.1 OthersMine dischargeCopy of Linkage
16.
Baseline Data Not Applicable
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 19.3 To 3
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 1.66 To 17.58
(c)Whether Ground Water Intersection will be there ? NA
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater16800Copy of Permission LetterPipelineOthersGround water during mining14536/Hg.II(1)/0704 Jun 20084390
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Mine discharge29292929Settling ponds / Slow sand filtersOthersNearby streams / agricultural fields16801249
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 2929
(b)Total Discharged Water (Kilolitre per Day) 1249
(c)Total Reused Water (Kilolitre per Day) 1680
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)TOp soilOthersTop soil777857Tons.1OthersDumpers and trucksOthersSpreading on OB dumps
(2.)Hard Over burdenOthersOB46680000Tons.1OthersTrucks & dumpersOthersStored as dumps
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)NOxMicrogram per Meter Cube20.700.36421.1120
(2.)SO2Microgram per Meter Cube14.200.0214.22120
(3.)PM10Microgram per Meter Cube20308.09211.10250
(4.)PM2.5Microgram per Meter Cube60.204.0564.26Not Specified
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)NANA00PM100
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 803
(b)Source 132 KV Manuguru substation
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) Second source electricity available
(e)Stack Height (in m) 0
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 34.95
(b)Private Land (ha.) 331.36
(c)Government Land (ha.) 302.11
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 668.42
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 594.58
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 8.62
(e)Settlements (ha.) 27.94
(f)Industrial (ha.) 0
(g)Forest (ha.) 34.95
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : Roads 2.33
    Total (ha.) 668.4200000000002
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)OB Dump Area244.56
(2.)Safety Zone100.32
(3.)Built Up Area34.05
(4.)Quarry Area208.92
(5.)Green belt34.71
(6.)OthersEmbankment45.86
Total (ha.) 668.42
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)ESAsNA0NA
(2.)WLSNil0NA
(3.)ESZsKinnerasani wild life sanctuary5.67Nil
(4.)Critically Polluted AreaNA0na
(5.)NPANA0NA
(6.)Wildlife CorridorsNA0NA
(7.)CorridorsNA0NA
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Defence InstallationsNA0NA
(2.)ForestReserve forest034.95 ha of Forest land is involved in the project, Forest Clearances obtained 1. Surface rights for 33.58 ha vide F.No.8-73/2005-FC dt.09.05.2016, 2. Surface rights for 1.37 ha (part of 1312 ha).
(3.)Archaeological SitesNA0NA
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? Yes
(a)Forests Clearance Status Application for Forest Clearance yet to be submitted
(b)Legal Status of Forest Land Reserved
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 668.42
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired NA
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 4
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 1124
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 3280
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? Yes
(i)Details of Water Bodies in Core Area 6 Nos. of seasonal tanks are present within the area. The elevation varies from 759.83 m to 781.00 m with an average elevation of 766.65m.
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area This area is drained by perennial Godavari River and its ephemeral tributaries like Gorripeta vagu and Kodipunjula vagu. The streams are sub-parallel flowing towards northeast and east to join the Godavari River which is on the North east side of the block (HFL-765.47m). The overall drainage density is about 1.83 km/Sq.km. In the block the drainage density is very low, because of sandy soil cover
(ii)Direction of Water Bodies in Buffer Area North East
(iii)Distance of Water Bodies in Buffer Area .183
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 220
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 188
(e)No. of working days 365
(f)Total Manpower 408
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt16.81413.02429.83
(2.)Percentage of Total Project Area3.91096.089199.9991
(3.)No. of Plants4202510325501074575
(4.)Funds Allocated234650.9085765349.16000000.007999999
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)EnvironmentalIn the project area of 668.42 ha an amount of 429.83 ha will be reclaimed in stage wise by the end of the project.
(2.)SocialThe social infrastructure in terms of connectivity by road, communication, health, sanitation, community centers, education, financial institution will be improved..
(3.)FinancialNew jobs will be created and there will be a boost up in the local business in the area which will improve the financial status of the nearby habitants.
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For Coal Mining
S. No.Item Details
     1.       No. of Mineral(s) to be Mined : 1
S. No.Mineral(s) to be Mined Major or Minor Mineral
(1.)CoalMajor
2.
Mine Capacity in ROM (Run of Mine) 2.1 MT
3.
Uploaded 500 meters Cluster Certificate from State Mines and Geology in case of minor minerals Copy of 500 meters Cluster Certificate from State Mines and Geology
4.
Mining Plan:
(a)Approval Letter No. PCA-38011/12/2017-PCA
(b)Date of Approval 22 Apr 2019
(c)Approved Letter Copy of Approved Letter
(d)Approved By State Mining and Geology Department Coal
(e)Approved Mining Lease Area 668.42
(f)Approved Capacity 2.1
5.
Technical Details:
(a)Total Geological Reserves (Million Ton) 19.96
(b)Mineable Reserves (Million Ton) 16.66
(c)Extractable Reserves(Million Ton) 13.69
(d)Percent(%) of Extraction 68.58
(e)Grade of Coal /Ore /Mineral G-9 to G-12
(f)Stripping Ratio 1 : 13.92
(g)Category of Gaseousness (Only for Coal Mining, Others may Write NA) Degree -1
(h)Average Gradient(Degree) 1 in 3.3 to 5.5
(i)Mining Method Opencast
(j)Life of Mine (Years) 7 ( from 2018-19)
6.
Details of Beneficiations:
(a)Whether it is proposed to install beneficiation plant/Coal washery within the mining lease area No
(b)Whether it is proposed to install crusher within the mining lease area No
7.
Details of Seams:
(a)Whether details of seam applicable Yes
(b)No. of seams 8
(c)Thickness of seams to be worked on 0.17
(d)Maximum Thickness of Seams (metres) 5.89
8.
Details of Mining Lease:
(a)Mining Lease Area (in Hectare) 668.42
(b)Whether obtained Letter of Intent (LOI) from the state government ? No
(i)Reason thereof Already Lease obtained for entire project area of
(c)Whether Lease Deed Executed ? Yes
(i)Copy of Executed Lease deed valid as on Date Copy of Executed Lease deed
(ii)Provide area in Hectare as per executed lease deed (initial) document 2180
(iii)Validity of the lease deed From : 23 Jul 1974 To : 23 Jul 2005
(iv)Date of Execution of Mining Lese 12 Aug 1974
(v)Reference Number G.O.Ms No.810, Ind & Com(M-III) Dept
(d)Whether Lease Deed Renewed ? Yes
     8.1.    Earlier Renewals:
S. No.Lease Details Date of Renewal Period Copy of Earlier Lease Letter No.Area Remarks
(1.)Initial 01 Jan 1900 From : 06 Feb 2015 To : 15 Apr 2035 Copy of Earlier LeaseG.O.Ms No. 6 373.90 NIl
(2.)Renewal 12 Aug 2008 From : 23 Jul 2005 To : 23 Jul 2035 Copy of Earlier LeaseG.O.Ms No. 217 294.52 Nil
9.
OB (Over Burden) Management:
(a) Details of External Dumps:
(i)No. of OB Dumps
(ii)Total Area (in Hectare)
(iii)Height (in meter)
(iv)Quantity (in Million Cubic meter)
(v)No. of year back fill up
(b) Details of Internal Dumps:
(i)No. of Internal Dumps
(ii)Total Area (in Hectare)
(iii)Height (in meter)
(iv)Quantity (in Million Cubic meter)
10.
Details of Topsoil Management:
(a)Quantity of Topsoil excavated during the entire life of the mine (in Million Cubic metre) 3.63
(b)Quantity of Topsoil proposed for utilization for reclamation during the entire life of the mine (in Million Cubic metre) 2.73
(c)Quantity of Topsoil proposed for utilization for other activities during the entire life of the mine (in Million Cubic metre) 0.9
11.
Details of Final Mine Void:
(a)Area (in Hectare)
(b)Depth (in meter)
(c)Volume (in Million Cubic meter)
12.
Details of Quarry:
(a)Final Void of 158.96 (hectare) at a Depth of 200 meter which is Proposed to be Converted into a Water Body.
(b)Total Quarry Area (ha) 208.92
13.
Details of Transportation:
(a)In Pit/Underground to Surface Dumpers
(b)Surface to Siding/Loading Trucks and conveyor
(c)Transportation / Conveyor Details By Road and conveyor to Kondapur CHP from CHP thro
     14.      Details of Land Usage (Pre-Mining)
S. No.LAND USE Other LAND USEWITHIN ML AREA (Hectare)OUTSIDE ML AREA (Hectare)TOTAL (Hectare)
(1.)FOREST LAND34.95034.95
(2.)SETTLEMENTS27.94027.94
(3.)OTHERS(Specify)Roads2.3302.33
(4.)SURFACE WATER BODIES8.6208.62
(5.)WASTE LAND000
(6.)GRAZING LAND000
(7.)AGRICULTURE LAND594.580594.58
TOTAL668.420668.42
     15.      Details of Land Usage (Post-Mining)
S. No.LAND USE Other LAND USEPlantation (ha)Water Body (ha)Public Use (ha)Undisturbed (ha)Total
(1.)VIRGIN AREA44.0301.8345.86
(2.)INTERNAL OB DUMPS49.960049.96
(3.)EXCAVATION/QUARRY0134.9823.98158.96
(4.)ROADS0000
(5.)EXTERNAL OB DUMPS244.5600244.56
(6.)BUILT UP AREA (COLONY/OFFICE)0034.0534.05
(7.)Othersafety zone49.7223.9626.64100.32
(8.)TOP SOIL STORAGE0000
(9.)GREEN BELT34.710034.71
TOTAL422.98158.9486.50668.42
16.
Details of Reclamation:
Total Afforestation Plan shall be Implemented Covering of Mining.
This will Include:
(a)External OB Dump(in hectare) 244.56
(b)Internal Dump(in hectare) 49.56
(c)Quarry(in hectare) 208.92
(d)Safety Zone(in hectare) 100.32
(e)Final Void of 158.96 (hectare) at a Depth of 200 meter which is Proposed to be Converted into a Water Body.
(f)Density of Tree Plantation per ha (in no.) 2500
(g)Others in ha (such as Excavation Area along ML Boundary, along Roads and Infrastructure, Embankment Area and in Township Located Outside the Lease etc) 135.31
(h)Total afforestation plant (in hectare) 429.83
17.
Status of progressive Mining Closure Plan:
Details Not Applicable
     18.      Details of Actual Coal/ ORE Production vis-a-vis Sanctioned Capacity since the Inception:
S. No.Financial Year Sanctioned Capacity as per EC (MTPA)Sanctioned Capacity as per CTOSanctioned Capacity as per approved mining planActual Production Excess Production Beyond the EC / CTO/ Mining Plan Sanctioned Capacity (MTPA)
(1.)20171.51.51.50.450
(2.)20181.51.51.51.50
(3.)20191.51.51.51.50
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. QCI/NABET/EIA/ACO/19/0981
(ii)Name of the EIA Consultant EPTRI
(iii)Address 91/4 Gachibowli, Hyderabad
(iv)Mobile No. 9885236493
(v)Landline No. 0406756750
(vi)Email Id dgeptri@gmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Coal Mining
(ix)Validity of Accreditation 15 Nov 2019
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NA1. The status of the forestland submitted in the Form-2 and Certificate of compliance submitted by the regional office is contrary to each other. You are requested to provide exact status of forest clearance involved in the project along with copy of clearance 2. Action taken report on the non-compliance reported by the regional officer, Chennai vide letter dated 14th August, 2019 3. The details under final void and OB management shall be filled properly in the Form-II 4. Whether the project falls in the ESZ of the Kinnersani Wildlife Sanctuary?. Plan showing the boundary of Kinnersani Wildlife sanctuary, ESZ and project boundary along with the distances 18 Sep 2019
2.NAThe correction have been made as per the instruction received 29 Sep 2019
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantShri G Venkateswara Reddy
DesignationDirector (Planning & Projects)
Name of Company (Applicant Name should not be given here)The Singareni Collieries Company Limited
AddressKothagudem P.O -507101 Khammam Dt