S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Altra Pure Chem
(b)Name of the Company / Organisation ALTRA PURE CHEM
(c)Registered Address S. No. 234, H. No. 04, Plot No. 45, Additional MIDC Zone, Jindal Compound, Bhopar Village, Manpada, Dombivali (E),,Thane,Maharashtra-421204
(d)Legal Status of the Company Others
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Mithun Patil
(b)Designation (Owner/ Partner/ CEO) Owner
(c)Address S. No. 234, H. No. 04, Plot No. 45, Additional MIDC Zone, Jindal Compound, Bhopar, Village Manpada, Dombivli - East,,Kalyan,Thane,Maharashtra-421204
(d)Pin code 421204
(e)E-mail altrapurechem45@gmail.com
(f)STD Code. 251(f)Telephone No. 2870379
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity5(b) Pesticides industry and pesticide specific intermediates (excluding formulations)
Minor Activity5(b) Pesticides industry and pesticide specific intermediates (excluding formulations)
(b)Category A
(c)Proposal Number IA/MH/IND2/109064/2019
(d)Master Proposal Number(Single Window) SW/114366/2019
(e)EAC concerned (for category A Projects only) Industrial Projects - 2
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. N-67
(b)Pincode 421506
(c)Bounded Latitudes (North)
From
Degree 92
Minutes
Second
From
Degree 92
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 73
Minutes
Second
From
Degree 73
Minutes
Second
(e)Survey of India Topo Sheet No. E43B4
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 74
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 5.48
(j)Seismic Zone 1
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Maharashtra
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)MaharashtraThaneAmbarnath
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number IA-J-11011/214/2019-IA-II(I)
(b)Date of Apply of TOR 27 Jun 2019
(c)Date of Issue of TOR / Standard ToR 02 Aug 2019
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason Altra Pure Chem will execute the proposed activity
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)GLR5 KL21 No.
(2.)Water ring pump--5 No.
(3.)Water jet pump--1 No.
(4.)PumpsRPP 1204 No.
(5.)HDPE Storage Tank5.0 KL4 No.
(6.)GLR – Day Tank0.5 KL14 No.
(7.)SS 316 – Day Tank0.5 KL8 No.
(8.)GLR3 KL32 No.
(9.)Condenser20 Sq m3 No.
(10.)Condenser30 Sq m1 No.
(11.)Diaphragm Pump (Air)S40-32-105 No.
(12.)Vertical PumpWLW-1002 No.
(13.)Receivers10000 L1 No.
(14.)Extraction Vessel--1 No.
(15.)Chip Condenser15 Sq m3 No.
(16.)Graphite Condenser15 Sq m1 No.
(17.)Metering Tank200/300/600/100017 No.
(18.)Distillation column700 mm dia./20 m
(19.)Storage Tank50 /20 cu. m2 No.
(20.)Water spray absorber--2 No.
(21.)Oil Separation Tank--2 No.
(22.)Air Compressor--1 No.
(23.)Falling Film Absorber--2 No.
(24.)Cooling tower600 TR1 No.
(25.)Chilling plant25 TR1 No.
(26.)HDPE Storage Tank2.0 KL6 No.
(27.)GLR – Day Tank2.0 KL4 No.
(28.)GLR – Day Tank1.0 KL12 No.
(29.)GLR2 KL15 No.
(30.)Rotary Vane Condenser30 Sq m5 No.
(31.)Auto vertical SS Centrifuge--3 No.
(32.)Receivers1000/500 L3 No.
(33.)Snake Type Glass Condenser1.5 Sq m4 No.
(34.)Water Tank5000 L1 No.
(35.)Glass Condenser3 sq m
(36.)Double Cone Dryer--
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Dimethyl amine (By-product)2.6OthersMT/MOthersRoad, Air/ Sea route
(2.)Magnesium chloride (By-product)124.6OthersMT/MOthersRoad, Air/Sea route
(3.)Potassium dihydrogen borate (By-product)1.8OthersMT/MOthersRoad, Air/Sea route
(4.)2 Methyl 3-Biphenyl Methanol100OthersMT/MOthersRoad, Sea/Air route
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 13 Sep 2006
(iv)Valid Upto 13 Aug 2019
(v)File No. Not Applicable
(vi)Application No. Not Applicable
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 25.0
(b) Funds Allocated for Environment Management (Capital) (in Crores) 6.7716
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.5
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 27.08
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 14924
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 14924
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Bromobenzene1440Tons per AnnumLocalRoad250 Open MarketCopy of Linkage
(2.)Toluene4344Tons per AnnumLocalRoad20 Open MarketCopy of Linkage
(3.)Potassium Borohydride96Tons per AnnumLocalRoad30 Open MarketCopy of Linkage
(4.)2,6 Dichloro Tolune1500Tons per AnnumLocalRoad30 Open MarketCopy of Linkage
(5.)Processed Natural Gas350OthersNm3LocalPipe Conveyor0 Open MarketCopy of Linkage
(6.)Tetrahydrofuran4272Tons per AnnumLocalRoad30 Open MarketCopy of Linkage
(7.)Di Methyl Formamide564Tons per AnnumLocalRoad30 Open MarketCopy of Linkage
(8.)Magnesium tablets408Tons per AnnumLocalRoad250 Open MarketCopy of Linkage
(9.)Hydrochloric Acid1992Tons per AnnumLocalRoad20 Open MarketCopy of Linkage
(10.)FUEL- FURNACE OIL308Otherskg/hr.LocalRoad50 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Mar 2018 To 31 May 2018
(b)Season Summer
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube876386.5100
(2.)NOxMicro Gram per Meter Cube42.114.041.780
(3.)SO2Micro Gram per Meter Cube34.612.033.680
(4.)PM2.5Micro Gram per Meter Cube46.228.845.060
    14.2.     No. of Ground Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)TSSmg/l6112000000000000
(2.)Total Hardnessmg/l8535200600
(3.)Fluoridemg/l0.60.0211.5
(4.)Heavy MetalsCadmiummg/l0.00250.00250.0030
(5.)Heavy MetalsLeadmg/l0.010.010.010
(6.)Heavy MetalsChromiummg/l0.010.010.050
(7.)Heavy MetalsMercurymg/l0.0010.0010.0010
(8.)pHNA7.376.956.58.5
(9.)TDSmg/l128615002000
(10.)Heavy MetalsZincmg/l0.080.01515
(11.)Heavy MetalsNickelmg/l0.010.010.020
(12.)ChloridesNA28.19.52501000
(13.)Heavy MetalsArsenicmg/l0.010.010.010.05
    14.3.     No. of Surface Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA7.667.01C
(2.)CODmg/l248B
(3.)BODmg/l73B
(4.)DOmg/l6.74.3C
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))68.244.575
(2.)Leq(Night)A-weighted decibels(dB(A))50.239.970
    14.5.     No. of Soil Sample Monitored locations : 8
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pH8.36.8
(2.)K(Potassium)Milligram per Kilogram341.2105.6
(3.)P(Phosphorus)Milligram per Kilogram16.810.3
(4.)N(Nitrogen)Milligram per Kilogram43.526.9
(5.)Electric ConductivityMillisiemens per Centimetre159.549.5
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 2.46 To 2.47
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 0.52 To 0.53
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersAdditional Ambernath MIDC204.930Copy of Permission LetterPipelineOthersSupply by MIDC Pipeline014 Aug 2019204.93
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic activity2.0105Subjected to aeration tank of ETPReuse within the Plant & Recycling2
(2.)Boiler blow down4.2105Full fledged ETP comprising of primary, secondary & tertiary treatment schemeReuse within the Plant & Recycling4.2
(3.)Process HCOD-HTDS36.4255Stripper MEEReuse within the Plant & Recycling36.42
(4.)Process LCOD-LTDS24.28105Full fledged ETP comprising primary, secondary & tertiary treatment schemeReuse within the Plant & Recycling24.28
(5.)Cooling Tower blow down20.70105Full fledged ETP comprising of primary, secondary & tertiary treatment schemeReuse within the Plant & Recycling20.70
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 87.6
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 87.6
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Empty drums, Carboys & ContainersHazardous Waste (as per Hazardous and Other Waste Management rules 2016)100Tons30RoadOthersSale to MPCB authorized vendors
(2.)MEE ResidueHazardous Waste (as per Hazardous and Other Waste Management rules 2016)860.4Tons30RoadOthersCHWTSDF or sale to MPCB Authorized Vendors
(3.)ETP SludgeHazardous Waste (as per Hazardous and Other Waste Management rules 2016)120Tons30RoadTreatment, Storage and Disposal Facility(TSDF)
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube8720.0487.05100
(2.)PM2.5Microgram per Meter Cube46.220.00546.20660
(3.)SO2Microgram per Meter Cube34.600.134.880
(4.)NOxMicrogram per Meter Cube42.100.0842.1980
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)Stack No.1NA40.2OthersToluene & THF0
(2.)Stack No.2NA40.2OthersBromine0
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 500
(b)Source MSEDCL
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 500 kVA x 1
(e)Stack Height (in m) 4.5
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 0
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0.65
    Total Land (ha.) 0.65
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 6160
(b)Waste/Barren Land (ha.) 11121
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 70
(e)Settlements (ha.) 7087
(f)Industrial (ha.) 0
(g)Forest (ha.) 5514
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : 0 0
    Total (ha.) 29952
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)OthersFull fledged manufacturing plant will be set up.0.65
Total (ha.) 0.65
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaNot present within 5 km radial area000000Any of the notified CPAs are not present within 5 km radial area form project site
(2.)WLSNot present within 5 km radial area000000No WLS is located within 5 km radial area from project plot
(3.)ESAsNot present within 5 km radial area000000No ESAs present within 5 km raidal area from project plot
(4.)CorridorsNot present within 5 km radial area000000No Corridors are present within 5 km radial area from project plot
(5.)Wildlife CorridorsNot present within 5 km radial area000000No Wildlife Corridors are present within 5 km radial area from project plot
(6.)NPANot present within 5 km radial area000000No NPA is located within 5 km radial area from project plot
(7.)ESZsNot present within 5 km radial area000000No ESZs are present within 5 km radial area from project plot
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Defence InstallationsAmbernath Ordnance Factory5.55The distance given here is areal distance from project site
(2.)Archaeological SitesShiv Mandir3.74The distance given here is areal distance from project site
(3.)ForestNear Bohonoli2.34The distance given here is areal distance from project site
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 0.65
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired Project plot is in possession of Project Proponent
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? Yes
(i)Details of Water Bodies in Core Area 1) GIP Railway Dam - 0.8 km, 2) Chiklili Dam - 1.1 km, 3) Lotus Pond - 2.9 km , 4) Ulhas River - 4.7 km
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Kondeshwar Lake
(ii)Direction of Water Bodies in Buffer Area South
(iii)Distance of Water Bodies in Buffer Area 6.46
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 50
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 0
(e)No. of working days 26
(f)Total Manpower 50.0
32.
Green Belt in Ha:
(a)Total Area of Green Belt 0.2161
(b)Percentage of Total Project Area 33.25
(c)No. of Plants to be Planted 320
(d)Funds Allocated for Plantation 600000.00
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)Environmental1. The project will be ZLD activity, treated effluent will be completely reused. 2. Project is having membership of Mumbai Waste Management Ltd. - CHWTSDF. 3. Solvent recovery will be acheived 4. Green belt will be developed in 2161.00 sq.m. 5. Project plot specific Rain Water Harvesting will be implemented.
(2.)Social1. Project activity will generate employment for 50 nos. 2. Indirect employment opportunities will be generated in vicinity due to project activity. 3. Locals will be priotorized for employment. 4. Need based CER activities will be implemented in surrounding area, budgetary allocation for implementation of CER activities is 50.0 lakhs.
(3.)Financial1. The product to be manufactured is export oriented also, it will lead to earning of Foreign Exchange for Country & State.
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1821/RA 0121
(ii)Name of the EIA Consultant Sadekar Enviro Engineers Pvt. Ltd.
(iii)Address Plot No. A - 95, Road no. 16, Near MSEB, Kisan Nagar Road, Opp. Petrol Pump, Wagle Estate, MIDC Area, Thane West, Maharashtra - 400604.
(iv)Mobile No. 9820144125
(v)Landline No. 25833321
(vi)Email Id prs@sadekarenviro.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 16 Oct 2021
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
      Essential Detail Sought : NIL
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantMithun Patil
DesignationOwner
Name of Company (Applicant Name should not be given here)ALTRA PURE CHEM