1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | Expansion of Sukinda Mines (Chromite) | (b)Name of the Company / Organisation | Indian Metals & Ferro Alloys Ltd | (c)Registered Address | Bomikhal, Rasulgarh,Bomikhal, Rasulgarh,Khordha,Sikkim-751010 | (d)Legal Status of the Company | Private | (e)Joint Venture | No | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | Sandeep B Narade | (b)Designation (Owner/ Partner/ CEO) | Vice President | (c)Address | Bomikhal, Rasulgarh,Bomikhal, Rasulgarh,,Khordha,Orissa-751010 | (d)Pin code | 751010 | (e)E-mail | minesplanningcell@imfa.in | (f)STD Code. | 674(f)Telephone No. | 2580100 | (g)Fax No. | 2580020 | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a.I)Project/Activity | 1(a) Mining of minerals
| Minor Activity | 1(a) Mining of minerals
| (b)Category | A | (c)Proposal Number | IA/OR/MIN/114264/2007 | (d)Master Proposal Number(Single Window) | SW/114259/2019 | (e)EAC concerned (for category A Projects only) | Non-Coal Mining | (f)Project Type | Expansion |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | khasra no. 488 (p), 502, 627 (p), 628 (p), 629, 63 | (b)Pincode | 751010 | (c)Bounded Latitudes (North) | | From | | Degree | 21.029308 | Minutes | | Second | | From | | Degree | 21.042725 | Minutes | | Second | | (d)Bounded Longitudes (East) | | From | | Degree | 85.759975 | Minutes | | Second | | From | | Degree | 85.7783 | Minutes | | Second | | (e)Survey of India Topo Sheet No. | 73-G/16 | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 185 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 8.91 | (j)Seismic Zone | 2 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Orissa | |
|
|
Details of State of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
NIL | |
|
6. | Details of Terms of Reference (ToR)/EC: | (a)MoEF&CC / SEIAA File Number | J-11015/204/2015-IA.II(M) | (c)Date of Issue of TOR | 31 Jul 2007 | (f)Previous TOR Letter | Copy of Previous TOR letter | (b)Date of Apply of EC | 12 Sep 2019 | (c)Date of Issue of EC | 28 Dec 2020 | (d)Previous EC Letter | Copy of Previous EC letter | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | No | (b)Whether details of Public Hearing available? | Yes | (c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above | Yes | |
|
7.1. Details of Public Hearing |
---|
|
S. No. | Details of Advertisement | Details of Public Hearing | Venue | Location Details | No. of People Attended | Issues Raised | Designation of Presiding Officer | Other Designation of Presiding Officer |
---|
(1.) | | Copy of Public Hearing : | Copy of Public Hearing | Date : | 23 Jun 2017 | Distance of Public Hearing Venue from the Proposed Project : | 0.5 |
| At Mahagiri Enclave, Khata no. 53/15, Plot no. 664 | State : | Orissa | District : | Jajpur | Tehsil : | Sukinda | Village : | Kaliapani |
| 650 | Local employment opportunity, health care facility, drinking water supply, road maintenance | Others | Additional District Magistrate (ADM) | |
8. | Details of Project Configuration/Product: | Details Not Applicable | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | (a)Details of certified report on compliance of earlier environmental clearance condition | (i)Certified Compliance By | Regional | (ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on | Bhubaneswar | (iii)Letter No. | 101-409/EPE/83 | (iv)Status of Compliance | Compiled | (v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) | Copy of Certified Compliance Report | (vi)Date of site visit | Sep 22 2016 12:00AM | (b)Details of Capacity Expansion | |
|
S. No. | Product/Activity (Capacity/Area) | Quantity From | Quantity To | Total | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | Chromite Ore | 351000 | 249000 | 600000 | Tons per Annum(TPA) | | Road,Rail | | |
| (c)Details of Configuration | |
|
S. No. | Plant / Equipment / Facility | Existing Configuration | Proposed Configuration | Final configuration after expansion | Remarks |
---|
(1.) | Wagon Drill (115 mm) | 1 | 0 | 1 | For opencast mining | (2.) | Dumper (32 Tonne) | 21 | 5 | 26 | For opencast mining | (3.) | Dozer (170 HP to 200 HP) | 3 | 0 | 3 | For opencast mining | (4.) | Front End Loader (0.3 to 1.7 cum) | 1 | 1 | 2 | For opencast mining | (5.) | Water tanker (9 to 14 KL) | 3 | 0 | 3 | For opencast mining | (6.) | Explosive Van (2.39 Tonnes) | 1 | 0 | 1 | For opencast mining | (7.) | Grader (135 HP) | 1 | 0 | 1 | For opencast mining | (8.) | Excavator (0.9 to 3.5 cum) | 4 | 1 | 5 | For opencast mining | (9.) | Diesel Dispensing Unit (6 KL) | 1 | 0 | 1 | For opencast mining | (10.) | Roller | 0 | 1 | 1 | For opencast mining | (11.) | Ambulance | 1 | 0 | 1 | For opencast mining | |
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | Copy of Consent to Operate | (iii)Date of Issue | 06 Feb 2016 | (iv)Valid Upto | 31 Mar 2021 | (v)File No. | 2483/IND-I-CON-2274 | (vi)Application No. | 409649 dated 04.12.2015 | (vii)Copy of Consent to operate valid as on date | Copy of Consent to Operate | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in Crores) | 394.45 | (b) Funds Allocated for Environment Management (Capital) (in Crores) | 2.0 | (c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) | 2.98 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) | 1.43 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | No | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 0 | (b)Existing quantity of raw material/fuel | 5 | (c)Total quantity of raw material/fuel | 5 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | HSD | 31250 | Kilo Litre per Day | | IOCL | Road | | 1.5 | Fuel Supply Agreement | | Copy of Linkage | (2.) | EXPLOSIVE | 28 | Tons per Annum | | Magazine SMC | Road | | 0.17 | Others | License | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 01 Oct 2018 To 31 Oct 2018 | (b)Season | Post-Monsoon | |
|
14.1. No. of ambient Air Quality (AAQ) monitoring locations : 13 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | SO2 | | Micro Gram per Meter Cube | 8.1 | 4.3 | 7.2 | 80 | (2.) | NOx | | Micro Gram per Meter Cube | 19.1 | 10.3 | 18.6 | 80 | (3.) | PM10 | | Micro Gram per Meter Cube | 40.4 | 23.1 | 36.7 | 100 | (4.) | PM2.5 | | Micro Gram per Meter Cube | 19.9 | 12.2 | 19.1 | 60 | |
14.2. No. of Ground Water monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | Chlorides | | | mg/l | | 45 | 10 | 250 | 250 | (2.) | TSS | | | mg/l | | 0 | 0 | 0 | 0 | (3.) | pH | | | NA | | 7.5 | 6.5 | 6.5 | 8.5 | (4.) | TDS | | | mg/l | | 224.3 | 33.1 | 500 | 500 | (5.) | Total Hardness | | | mg/l | | 142 | 24 | 200 | 200 | (6.) | Fluoride | | | mg/l | | 1.28 | 0.1 | 1 | 1 | (7.) | Heavy Metals | | Total Chromium | mg/l | | 0.52 | 0.33 | 0.05 | 0.05 | |
14.3. No. of Surface Water monitoring locations : 9 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | DO | | mg/l | | 5.4 | 4.5 | C | (2.) | BOD | | mg/l | | 8.4 | 1.5 | C | (3.) | COD | | mg/l | | 40 | 16 | C | (4.) | pH | | mg/l | | 8.2 | 7.0 | C | |
14.4. No. of Ambient Noise monitoring locations : 13 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Night) | A-weighted decibels(dB(A)) | 62.5 | 48.5 | 45-70 | (2.) | Leq(Day) | A-weighted decibels(dB(A)) | 67.9 | 57.5 | 55-75 | |
14.5. No. of Soil Sample Monitored locations : 9 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | Electric Conductivity | Others | microsiemens per centimeter | 136.3 | 22.3 | (2.) | N(Nitrogen) | Milligram per Kilogram | | 92.9 | 71.1 | (3.) | K(Potassium) | Milligram per Kilogram | | 45 | 16.2 | (4.) | pH | | | 8.1 | 6.2 | (5.) | P(Phosphorus) | Milligram per Kilogram | | 12.3 | 2.9 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 10 To 5 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 2 To 5 | (c)Whether Ground Water Intersection will be there ? | Yes | (d)Upload Copy of Central Ground Water Authority Letter | Copy of Central Ground Water Authority Letter | (e)Letter No. | CGWA/NOC/MIN/REN/1/2018/5556 | (f)Date of Issue | 14 Dec 2018 | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity (Kilolitre per Day (Kld)) | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | GroundWater | | 3500 | 0 | Copy of Permission Letter | Pipeline | | Tube Well | | CGWA/NOC/MIN/REN/1/2018/5556 | 14 Dec 2018 | 3500 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | Drinking & Domestic | 192 | 0 | soak pit | Others | discharge to septic tank via soak pit | 0 | 192 | (2.) | Mine water | 3260 | 0 | ETP | Discharge into Surface Water Body,Reuse within the Plant & Recycling | | 20 | 3240 | |
|
16.1. | (a)Total Waste Water Generation (Kilolitre per Day) | 3452 | (b)Total Discharged Water (Kilolitre per Day) | 3432 | (c)Total Reused Water (Kilolitre per Day) | 20 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | Tailings from COB plant | Industrial Waste | | 25000 | Tons | 0 | Road | | Others | Designated place near sub grade dump | (2.) | Overburden/Interburden | Others | Overburden | 407407 | Tons | 0 | Road | | Others | Internal OB dump & backfilling of excavated area | (3.) | Municipal Solid waste | Municipal Solid Waste | | 51.1 | Tons | 0 | Road | | Sanitary Landfills | | (4.) | Used oil | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 18.25 | Kilolitre | 0 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | (5.) | ETP Sludge | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 150 | Tons | 0 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | PM10 | | Microgram per Meter Cube | 27.8 | 0.9 | 3.5 | 31.5 | 100 | (2.) | PM2.5 | | Microgram per Meter Cube | 14.6 | 0.9 | 2.37 | 16.99 | 60 | (3.) | NOx | | Microgram per Meter Cube | 14.4 | 0.9 | 11.45 | 25.95 | 80 | (4.) | SO2 | | Microgram per Meter Cube | 5.6 | 0.9 | 0.6 | 6.4 | 80 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | DG sets | HSD | 4.5 | 0.5 | PM10 | | 0.25 | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 4750 | (b)Source | CESU | (c)Uploaded Copy of Agreement | Copy of Agreement | (d)Standby Arrangement (Details of DG Sets) | 62.5 KVA, 200 KVA, 82.5 KVA, 250 KVA | (e)Stack Height (in m) | 4.5 | |
|
20. | Land Ownership Pattern: | (a)Forest Land (ha.) | 115.05 | (b)Private Land (ha.) | 0 | (c)Government Land (ha.) | 1.71 | (d)Revenue Land (ha.) | 0 | (e)Other Land (ha.) | 0 | Total Land (ha.) | 116.76 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area (ha.) | 0 | (b)Waste/Barren Land (ha.) | 1.71 | (c)Grazing/ Community Land (ha.) | 0 | (d)Surface Water Bodies (ha.) | 0 | (e)Settlements (ha.) | 0 | (f)Industrial (ha.) | 0 | (g)Forest (ha.) | 115.05 | (h)Mangroves (ha.) | 0 | (i)Marine Area (ha.) | 0 | (j)Others (ha.) : Not Applicable | 0 | Total (ha.) | 116.75999999999999 | |
|
22. Land requirement for various activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement (ha.) | Remarks |
---|
(1.) | Quarry Area | | 42.437 | At the end of conceptual period | (2.) | OB Dump Area | | 51.683 | At the end of conceptual period | (3.) | Township | | 1.050 | At the end of conceptual period | (4.) | Safety Zone | | 4.138 | At the end of conceptual period | (5.) | Others | Mineral Storage | 17.452 | | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | WLS | Not Applicable | 0 | Not Applicable | (2.) | Corridors | Not Applicable | 0 | Not Applicable | (3.) | Wildlife Corridors | Not Applicable | 0 | Not Applicable | (4.) | Critically Polluted Area | Not Applicable | 0 | Not Applicable | (5.) | ESAs | Not Applicable | 0 | Not Applicable | (6.) | ESZs | Not Applicable | 0 | Not Applicable | (7.) | NPA | Not Applicable | 0 | Not Applicable | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Forest | | Mahagiri PF | 0 | Project area falls within PF | (2.) | Defence Installations | | Not Applicable | 0 | Not Applicable | (3.) | Others | Not Applicable | Not Applicable | 0 | 0 | (4.) | Archaeological Sites | | Not Applicable | 0 | Not Applicable | |
|
|
24. | Forest Land: | Whether any Forest Land involved? | Yes | (a)Forests Clearance Status | Application for Forest Clearance yet to be submitted | (b)Legal Status of Forest Land | Protected | |
|
25. | Tree Cutting: | (a)No. of Trees Cut for the Project (if Forest Land not Involved) | 0 | (b)Details of Tree Cutting and Planting of Trees | Not Applicable | |
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 116.76 | (b)Land yet to be acquired(Ha) | 0 | (c)Status of Land acquisition if not acquired | Total land acquired | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | 0 | (b)No. of Households | 0 | (c)No. of PDFs (Project Displaced Families) | 0 | (d)No. of PAFs (Project Affected Families) | 0 | (e)Funds Allocated for R&R(in INR) (in Lacs) | 0 | (f)Status of R&R | Completed | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | Yes | (i)Details of Schedule-I Species | Four horned antelope, Indian elephant, Mouse deer, Sloth bear, Pea fowl, Spotted owlet, python, yellow monitor lizard, Great Indian hornbill, Bengal monitor, Ratel or Honey Badger | (b)Whether conservation plan for Schedule-I Species has been prepared ? | Yes | (i)Uploaded copy of conservation plan | Copy of conservation plan | (ii)Fund Provision made | Rs 63.77 lakhs & Rs 257 lakhs towards conservatio | (iii)Period of Implementation | It is already implemented | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | Yes | (i)Uploaded copy of approval | Copy of approval | (ii)Letter No. | 10061/1WL-SSP-181/2015 | (iii)Date of issue | 18 Nov 2015 | (iv)Recommendation | NA | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | No | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | Yes | (i)Details of Water Bodies in Buffer Area | Damsal Nala | (ii)Direction of Water Bodies in Buffer Area | North West | (iii)Distance of Water Bodies in Buffer Area | 0.74 | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 0 | (b)Permanent Employment-During Operation | 195 | (c)Temporary Employment- During Construction | 0 | (d)Temporary Employment- During Operation | 726 | (e)No. of working days | 300 | (f)Total Manpower | 921 | |
|
|
S. No. | Description | Existing | Proposed | Total |
---|
(1.) | Total Area of Green Belt | 23.660 | 4.7 | 28.36 | (2.) | Percentage of Total Project Area | 20.26 | 4.02 | 24.28 | (3.) | No. of Plants | 74476 | 11750 | 86226 | (4.) | Funds Allocated | 12 | 8 | 20 | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Environmental | Afforestation within the lease area will increase the aesthetic beauty of the area | (2.) | Social | Project will create direct and indirect employment | (3.) | Financial | Royalty paid will contribute to revenue of the State Government. | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details For Non-Coal Mining |
|
1. No. of Mineral(s) to be Mined : 1 |
---|
S. No. | Mineral(s) to be Mined | Major or Minor Mineral |
---|
(1.) | Chromite Ore | Major | |
|
2. | Mine Capacity in ROM (Run of Mine) | 6.0 Lakh TPA | |
|
|
4. | Mining Plan: | (a)Approval Letter No. | MS/FM/27-ORI/BHU/2018-19 | (b)Date of Approval | 31 Oct 2018 | (c)Approved Letter | Copy of Approved Letter | (d)Approved By State Mining and Geology Department | IBM | (e)Approved Mining Lease Area | 116.76 | (f)Approved Capacity | 6.0 | |
|
5. | Technical Details: | (a)Total Geological Reserves (Million Ton) | 34.533 (as on 01.07.2018) | (b)Mineable Reserves (Million Ton) | 11.961 (as on 01.07.2018) | (c)Extractable Reserves(Million Ton) | 11.961 | (d)Percent(%) of Extraction | 100 | (e)Grade of Coal /Ore /Mineral | 10-54% of Cr2O3 | (f)Stripping Ratio | 1 : 4.2 | (g)Category of Gaseousness (Only for Coal Mining, Others may Write NA) | NA | (h)Average Gradient(Degree) | 30 | (i)Mining Method | Mixed | (j)Life of Mine (Years) | 48 years as per present exploration | |
|
6. | Details of Beneficiations: | (a)Whether it is proposed to install beneficiation plant/Coal washery within the mining lease area | Yes | (b)Beneficiation / Washing Technology | wet gravity separation by Tabling & Falcon Concent | (c)Capacity | 40 | (d)Whether it is proposed to install crusher within the mining lease area | No | |
|
7. | Details of Seams: | (a)Whether details of seam applicable | No | |
|
8. | Details of Mining Lease: | (a)Mining Lease Area (in Hectare) | 116.76 | (b)Whether obtained Letter of Intent (LOI) from the state government ? | No | (i)Reason thereof | Lease has already been executed | (c)Whether Lease Deed Executed ? | Yes | (i)Copy of Executed Lease deed valid as on Date | Copy of Executed Lease deed | (ii)Provide area in Hectare as per executed lease deed (initial) document | 116.76 | (iii)Validity of the lease deed | From : 04 Sep 1999 To : 03 Sep 2049 | (iv)Date of Execution of Mining Lese | 04 Sep 1999 | (v)Reference Number | 2085 | (d)Whether Lease Deed Renewed ? | No | (i)Reason thereof | Lease is valid till 03.09.20149 as per MMDR Amendm | |
|
9. | OB (Over Burden) Management: | Details Not Applicable | |
|
10. | Details of Topsoil Management: | (a)Quantity of Topsoil excavated during the entire life of the mine (in Million Cubic metre) | 0 | (b)Quantity of Topsoil proposed for utilization for reclamation during the entire life of the mine (in Million Cubic metre) | 0 | (c)Quantity of Topsoil proposed for utilization for other activities during the entire life of the mine (in Million Cubic metre) | 0 | |
|
11. | Details of Final Mine Void: | (a)Area (in Hectare) | 42.437 | (b)Depth (in meter) | 138 | (c)Volume (in Million Cubic meter) | 20.90 | |
|
12. | Details of Quarry: | (a)Final Void of 42.437 (hectare) at a Depth of 0 meter which is Proposed to be Converted into a Water Body. | (b)Total Quarry Area (ha) | 42.437 | |
|
13. | Details of Transportation: | (a)In Pit/Underground to Surface | Truck/Dumper | (b)Surface to Siding/Loading | Truck/Dumper | (c)Transportation / Conveyor Details | Road,Rail | |
|
|
14. Details of Land Usage (Pre-Mining) |
---|
S. No. | LAND USE | Other LAND USE | WITHIN ML AREA (Hectare) | OUTSIDE ML AREA (Hectare) | TOTAL (Hectare) |
---|
(1.) | AGRICULTURE LAND | | 0 | 0 | 0 | (2.) | SETTLEMENTS | | 0 | 0 | 0 | (3.) | OTHERS(Specify) | Not Applicable | 0 | 0 | 0 | (4.) | FOREST LAND | | 115.05 | 0 | 115.05 | (5.) | WASTE LAND | | 1.710 | 0 | 1.71 | (6.) | SURFACE WATER BODIES | | 0 | 0 | 0 | (7.) | GRAZING LAND | | 0 | 0 | 0 | |
TOTAL | 116.76 | 0 | 116.76 | |
|
15. Details of Land Usage (Post-Mining) |
---|
S. No. | LAND USE | Other LAND USE | Plantation (ha) | Water Body (ha) | Public Use (ha) | Undisturbed (ha) | Total |
---|
(1.) | TOP SOIL STORAGE | | 0 | 0 | 0 | | 0 | (2.) | ROADS | | 0 | 0 | 2.920 | | 2.92 | (3.) | Other | Mineral Storage, ETP | 0 | 0 | 5.582 | | 5.582 | (4.) | VIRGIN AREA | | 0 | 0 | 0 | | 0 | (5.) | EXCAVATION/QUARRY | | 42.437 | 0 | 0 | | 42.437 | (6.) | EXTERNAL OB DUMPS | | 0 | 0 | 0 | | 0 | (7.) | INTERNAL OB DUMPS | | 51.683 | 0 | 0 | | 51.683 | (8.) | BUILT UP AREA (COLONY/OFFICE) | | 0 | 0 | 10 | | 10 | (9.) | GREEN BELT | | 4.138 | 0 | 0 | | 4.138 | |
TOTAL | 98.258 | 0 | 18.502 | 0 | 116.76 | |
16. | Details of Reclamation: | Total Afforestation Plan shall be Implemented Covering of Mining.This will Include: | (a)External OB Dump(in hectare) | | (b)Internal Dump(in hectare) | | (c)Quarry(in hectare) | | (d)Safety Zone(in hectare) | | (e)Final Void of (hectare) at a Depth of meter which is Proposed to be Converted into a Water Body. | (f)Density of Tree Plantation per ha (in no.) | | (g)Others in ha (such as Excavation Area along ML Boundary, along Roads and Infrastructure, Embankment Area and in Township Located Outside the Lease etc) | | (h)Total afforestation plant (in hectare) | | |
|
|
18. Details of Actual Coal/ ORE Production vis-a-vis Sanctioned Capacity since the Inception: |
---|
S. No. | Financial Year | Sanctioned Capacity as per EC (MTPA) | Sanctioned Capacity as per CTO | Sanctioned Capacity as per approved mining plan | Actual Production | Excess Production Beyond the EC / CTO/ Mining Plan Sanctioned Capacity (MTPA) |
---|
(1.) | 20012002 | 0 | 0 | 198190 | 214315.685 | 167650.265 | (2.) | 20052006 | 255000 | 255000 | 206008 | 259925.112 | 4925.112 | (3.) | 20102011 | 351000 | 351000 | 252000 | 251995.00 | 0.000 | (4.) | 20152016 | 351000 | 351000 | 273786 | 273548.830 | 0.000 | (5.) | 20162017 | 351000 | 351000 | 351000 | 350512.00 | 0.000 | (6.) | 20172018 | 351000 | 351000 | 351000 | 350571.560 | 0.000 | (7.) | 20042005 | 255000 | 255000 | 170761 | 243584.963 | 0.000 | (8.) | 20072008 | 255000 | 255000 | 349938 | 295817.660 | 40817.660 | (9.) | 20082009 | 351000 | 255000 | 419310 | 284753.459 | 0.000 | (10.) | 20092010 | 351000 | 255000 | 200276 | 218618.0 | 0.000 | (11.) | 20112012 | 351000 | 351000 | 377530 | 350168.00 | 0.000 | (12.) | 20002001 | 0 | 0 | 229780 | 144802.450 | 98137.030 | (13.) | 20092010 | 351000 | 255000 | 200276 | 218618.00 | 0.000 | (14.) | 20022003 | 255000 | 255000 | 224102 | 188376.994 | 114001.994 | (15.) | 20032004 | 255000 | 255000 | 256500 | 309615.046 | 54615.046 | (16.) | 20062007 | 255000 | 255000 | 285829 | 235466.681 | 0.000 | (17.) | 20132014 | 351000 | 351000 | 350994 | 348568.510 | 0.00 | (18.) | 19992000 | 0 | 0 | 125570 | 46665.420 | 0 | (19.) | 20182019 | 351000 | 351000 | 351000 | 341003.00 | 0.000 | (20.) | 20122013 | 351000 | 351000 | 351000 | 296635.940 | 0.00 | (21.) | 20142015 | 351000 | 351000 | 282467 | 258580.350 | 0.000 | |
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | Yes | (b)Name of the Court | Tribunals | (c)Name of the Sub Court | Central Administrative Tribunal | (d)Case No. | RA No. 22/46/2018/RC-I | (e)Orders/Directions of the court ,if any and its relevance with the proposed project | Having considered revision petition of project. Ma | (f)Case Details | Revision application was filed challenging the dem | (g)Uploaded Court Order | Copy of Court Order | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | No | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | S.No. 112, Rev.77, July 10, 2019 | (ii)Name of the EIA Consultant | Perfact Enviro Solutions Pvt. Ltd. | (iii)Address | 5th Floor, NN Mall, Sec-3, Rohini, New Delhi-110085 | (iv)Mobile No. | 9818346370 | (v)Landline No. | 0114928136 | (vi)Email Id | info@perfactgroup.in | (vii)Category of Accreditation | A | (viii)Sector of Accreditation | Non-Coal Mining | (ix)Validity of Accreditation | 21 Nov 2019 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Detail Sought: |
---|
Sno. | EDS Letter | Remarks | Date of EDS |
---|
1. | NA | PP is requested to submit the following:
1. Certified compliance report for existing EC
2. EIA report is not as per the format. Content of EIA report comprises 10 chapter only. Please check and upload the correct document.
3. Updated status of the court cases.
4. Copy of EC document for the capacity of 2.55 lakh tonnes per annum.
5. Authenticated Certificate for hydro-geologist and the laboratory who carried out the hydrogeological study | 06 Sep 2019 | 2. | NA | The correction have been made as per the instruction received | 12 Sep 2019 | |
Additional Detail Sought: |
---|
Sno. | ADS Letter | Remarks | Date of ADS |
---|
1. | ADS Reply Letter | Reply of ADS generated vide 18th EAC meeting dated 22.06.2020 | 16 Jul 2020 | 2. | NA | deferred | 01 Jul 2020 | 3. | ADS Reply Letter | Reply of ADS generated vide letter no. J-11015/204/2015-IA.II (M) dated 13.12.2019. | 31 Jan 2020 | 4. | NA | Based
on the presentation made by PP and the discussion held, the Committee deferred the proposal and asked the PP
to submit requisite information for further consideration. i.