Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) M/s. BHARAT RASAYAN LIMITED (UNIT-II)
(b)Name of the Company / Organisation BHARAT RASAYAN LIMITED BRL
(c)Registered Address 1501, Vikram Tower, Rajendra Place, New Delhi,,New Delhi,Delhi-110008
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Ajay Kumar Gupta
(b)Designation (Owner/ Partner/ CEO) Director
(c)Address Unit - II, Plot No. 42/4, Dahej GIDC Industrial Estate, Dahej,,Vagra,Bharuch,Gujarat-392130
(d)Pin code 392130
(e)E-mail brldahej@bharatgroup.co.in
(f)STD Code. 11(f)Telephone No. 224805
(g)Fax No. 43661100
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity5(b) Pesticides industry and pesticide specific intermediates (excluding formulations)
Minor Activity5(b) Pesticides industry and pesticide specific intermediates (excluding formulations)
(b)Category A
(c)Proposal Number IA/GJ/IND2/114039/2008
(d)Master Proposal Number(Single Window) SW/114036/2019
(e)EAC concerned (for category A Projects only) Industrial Projects - 2
(f)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Plot No. 42/4
(b)Pincode 392130
(c)Bounded Latitudes (North)
From
Degree 21.721475
Minutes
Second
From
Degree 21.726558
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 72.591178
Minutes
Second
From
Degree 72.593814
Minutes
Second
(e)Survey of India Topo Sheet No. F43M09, F43M10
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 6
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 7
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Gujarat
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number J-11011/961/2008-IA-II (I)
(c)Date of Issue of TOR 25 Feb 2009
(f)Previous TOR Letter Copy of Previous TOR letter
(b)Date of Apply of EC 07 Sep 2019
(c)Date of Issue of EC 19 Oct 2020
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason Projrect Site is located within Dahej-I GIDC Indus
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Bhopal
(iii)Letter No. File No. 5-8/2011(ENV)/410
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit May 16 2019 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Agrochemicals & their intermediates123001690029200Tons per Annum(TPA)Road,Rail
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)Multi Purpose PlantMPP - A, B, CMPP - D, E, F6 Nos. MPPPlease refer Annexure - 16 for more details
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 22 Jan 2018
(iv)Valid Upto 11 Oct 2020
(v)File No. AWH-90645
(vi)Application No. 126940
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 200
(b) Funds Allocated for Environment Management (Capital) (in Crores) 16
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 1.5
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 27.201
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 70000
(b)Existing quantity of raw material/fuel 10000
(c)Total quantity of raw material/fuel 80000
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Natural Gas80000OthersSM3/dayGujarat Gas Company LtdPipe Conveyor30 LinkageCopy of Linkage
(2.)Furnace Oil90OthersMT/DayIOCLRoad30 LinkageCopy of Linkage
(3.)HSD Fuel17OthersKL/DayIOCL / Local suppliersRoad30 Open MarketCopy of Linkage
(4.)Coal200OthersMT/DayAdani Coal SupplyRoad30 Open MarketCopy of Linkage
(5.)Raw material7658OthersMTMIndigenous & Import from other countryRoad,Rail,OthersSea, Air300 LinkageCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Jan 2019 To 31 Mar 2019
(b)Season Pre-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 10
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube1195195NAAQS
(2.)PM2.5Micro Gram per Meter Cube491645NAAQS
(3.)SO2Micro Gram per Meter Cube33631NAAQS
(4.)NOxMicro Gram per Meter Cube351433NAAQS
    14.2.     No. of Ground Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA8.88.178.5
(2.)TDSmg/l38924981010
(3.)Total Hardnessmg/l5861211010
(4.)Fluoridemg/l1.10.50.50.5
(5.)TSSmg/l330101010
(6.)Heavy MetalsZincmg/l0.20.20.20.2
(7.)Chloridesmg/l7734311
    14.3.     No. of Surface Water monitoring locations : 13
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)BODmg/l1010A
(2.)CODmg/l164A
(3.)DOmg/l7.55A
(4.)pHNA8.38.2A
    14.4.     No. of Ambient Noise monitoring locations : 10
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))6934Noise Rules, 2000
(2.)Leq(Day)A-weighted decibels(dB(A))7341Noise Rules, 2000
    14.5.     No. of Soil Sample Monitored locations : 10
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)P(Phosphorus)Milligram per Kilogram21.32.4
(2.)K(Potassium)Milligram per Kilogram840245
(3.)Electric ConductivityOthersµsm/ cm4619275
(4.)N(Nitrogen)Percent0.810.32
(5.)pH9.168.2
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 3 To 9
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 2 To 8
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)Surface30774Copy of Permission LetterPipelineWeir--18 Feb 20191419
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic100120To be treated in STPOthersGardening/Mixed with Industrial effluent0100
(2.)Industrial17501700To be treated in ETP/MEE/ROOthersDischarge into deep sea via u/g GIDC pipeline1301620
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 1850
(b)Total Discharged Water (Kilolitre per Day) 1720
(c)Total Reused Water (Kilolitre per Day) 130
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Used OilHazardous Waste (as per Hazardous and Other Waste Management rules 2016)30Tons15RoadAuthorized Recyclers
(2.)hydrobromic acidHazardous Waste (as per Hazardous and Other Waste Management rules 2016)907Tons50RoadOthersActual end users
(3.)Spent Acid (Dilute H2SO4)Hazardous Waste (as per Hazardous and Other Waste Management rules 2016)2144Tons50RoadOthersActual end users
(4.)Ammonium Sulphate SolnHazardous Waste (as per Hazardous and Other Waste Management rules 2016)496Tons50RoadOthersActual end users
(5.)Date expired and off-specification on residuesHazardous Waste (as per Hazardous and Other Waste Management rules 2016)60Tons50RoadOthersIncineration at ICHWMF Site
(6.)Sodium Sulfite SolidsHazardous Waste (as per Hazardous and Other Waste Management rules 2016)4360Tons50RoadOthersActual end users
(7.)Sodium Sulfite SolnHazardous Waste (as per Hazardous and Other Waste Management rules 2016)7548Tons50RoadOthersActual end users
(8.)Discarded Containers, barrels, linersHazardous Waste (as per Hazardous and Other Waste Management rules 2016)1825Tons15RoadAuthorized Recyclers
(9.)Potassium Chloride SolutionHazardous Waste (as per Hazardous and Other Waste Management rules 2016)6575Tons50RoadOthersActual end users
(10.)Cupric ChlorideHazardous Waste (as per Hazardous and Other Waste Management rules 2016)24Tons50RoadOthersActual end users
(11.)Mixed SolventsHazardous Waste (as per Hazardous and Other Waste Management rules 2016)363Tons50RoadOthersActual end users
(12.)Process Waste/Waste residue containing pesticidesHazardous Waste (as per Hazardous and Other Waste Management rules 2016)2584Tons50RoadOthersco-processing / Incineration at ICHWMF Site
(13.)ETP & MEE SludgeHazardous Waste (as per Hazardous and Other Waste Management rules 2016)15000Tons15RoadTreatment, Storage and Disposal Facility(TSDF)
(14.)Coal AshOthersNon-Hazardous Waste5840Tons50RoadOtherssell to brick manufactures and/or cement industry
(15.)Distillation ResidueHazardous Waste (as per Hazardous and Other Waste Management rules 2016)245Tons50RoadOthersco-processing / Incineration at ICHWMF Site
(16.)Ammonia SolutionHazardous Waste (as per Hazardous and Other Waste Management rules 2016)288Tons50RoadOthersActual end users
(17.)Potassium chloride SolidsHazardous Waste (as per Hazardous and Other Waste Management rules 2016)37Tons50RoadOthersActual end users
(18.)Aq AlumHazardous Waste (as per Hazardous and Other Waste Management rules 2016)13920Tons70RoadOthersActual end users
(19.)Sodium Bromide SolnHazardous Waste (as per Hazardous and Other Waste Management rules 2016)2806Tons50RoadOthersActual end users
(20.)Potassium Bromide SolnHazardous Waste (as per Hazardous and Other Waste Management rules 2016)1264Tons50RoadOthersActual end users
(21.)Potassium Bromide (solid)Hazardous Waste (as per Hazardous and Other Waste Management rules 2016)225Tons50RoadOthersActual end users
(22.)Ammonium ChlorideHazardous Waste (as per Hazardous and Other Waste Management rules 2016)1375Tons50RoadOthersActual end users
(23.)Hydrochloric Acid SolnHazardous Waste (as per Hazardous and Other Waste Management rules 2016)8286Tons50RoadOthersActual end users
(24.)Phosphoric AcidHazardous Waste (as per Hazardous and Other Waste Management rules 2016)126Tons50RoadOthersActual end users
(25.)Methane Sulfinic AcidHazardous Waste (as per Hazardous and Other Waste Management rules 2016)15Tons50RoadOthersActual end users
(26.)Used catalyst (spent catalyst)Hazardous Waste (as per Hazardous and Other Waste Management rules 2016)4.3Tons50RoadOthersActual end users
(27.)Sodium bi sulfide SolnHazardous Waste (as per Hazardous and Other Waste Management rules 2016)1112Tons50RoadOthersActual end users
(28.)DMA Solution-40%Hazardous Waste (as per Hazardous and Other Waste Management rules 2016)116Tons50RoadOthersActual end users
(29.)Acetic AcidHazardous Waste (as per Hazardous and Other Waste Management rules 2016)28Tons50RoadOthersActual end users
(30.)Sulfur (Solid)Hazardous Waste (as per Hazardous and Other Waste Management rules 2016)27Tons50RoadOthersActual end users
(31.)Potassium methane sulfinate saltHazardous Waste (as per Hazardous and Other Waste Management rules 2016)222Tons50RoadOthersActual end users
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM2.5Microgram per Meter Cube451.050.2045.201NAAQS
(2.)PM10Microgram per Meter Cube941.050.4594.455NAAQS
(3.)NOxMicrogram per Meter Cube331.051.5934.592NAAQS
(4.)SO2Microgram per Meter Cube311.053.8834.885NAAQS
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)Common Stack attached to Boiler-1&2, TFH-1&2NG OR FO, Coal301.1OthersPM, SO2, NOX150 mg/Nm3, 100 ppm, 50 ppm
(2.)DG Set-1HSD110.15OthersPM, SO2, NOX150 mg/Nm3, 100 ppm, 50 ppm
(3.)Common Stack attached to Boiler-3, THF-3&4NG OR FO, Coal401.3OthersPM, SO2, NOX150 mg/Nm3, 100 ppm, 50 ppm
(4.)DG Set - 2HSD150.15OthersPM, SO2, NOX150 mg/Nm3, 100 ppm, 50 ppm
(5.)Process Vent - 2NA (Process Stack)150.15OthersHCl, Cl2, VOC20, 5 mg/Nm3
(6.)Process Vent - 6NA (Process Stack)150.15OthersHCl, SO220, 40 mg/Nm3
(7.)Process Vent - 7NA (Process Stack)150.15OthersPM150 mg/Nm3
(8.)General Stack - 1NA (Process Stack)150.15OthersVOC--
(9.)General Stack - 2NA (Process Stack)150.15OthersVOC--
(10.)General Stack - 3NA (Process Stack)150.15OthersVOC--
(11.)General Stack - 5NA (Process Stack)150.15OthersVOC--
(12.)General Stack - 6NA (Process Stack)150.15OthersHCl, Cl220, 5 mg/Nm3
(13.)General Stack - 7NA (Process Stack)150.15OthersDMA--
(14.)General Stack - 8NA (Process Stack)150.15OthersNaCN--
(15.)Process Vent - 10NA (Process Stack)150.15OthersHCl, SO220, 40 mg/Nm3
(16.)General Stack - 9NA (Process Stack)150.15OthersVOC--
(17.)Process Vent - 3NA (Process Stack)150.15OthersH2S5 mg/Nm3
(18.)Process Vent - 4NA (Process Stack)150.15OthersHCl, SO220, 40 mg/Nm3
(19.)DG Set - 3HSD150.15OthersPM, SO2, NOX150 mg/Nm3, 100 ppm, 50 ppm
(20.)General Stack - 4NA (Process Stack)150.15OthersVOC--
(21.)General Stack - 10NA (Process Stack)150.15OthersHCl20 mg/Nm3
(22.)Process Vent - 5NA (Process Stack)150.15OthersHCl, SO220, 40 mg/Nm3
(23.)Process Vent - 8NA (Process Stack)150.15OthersPM150 mg/Nm3
(24.)Process Vent - 9NA (Process Stack)150.15OthersHCl, SO220, 40 mg/Nm3
(25.)Process Vent - 11NA (Process Vent)150.15OthersNH3175 mg/Nm3
(26.)Process Vent - 12NA (Process Stack)150.15NOx25 mg/Nm3
(27.)General stack - 11NA (Process Stack)150.15OthersVOC--
(28.)General Stack - 12NA (Process Stack)150.15OthersPM150 mg/Nm3
(29.)Process Vent - 1NA (Process Stack)150.15OthersHCl, Cl2, SO2, HBr, Br220, 5, 40, 5, 2 mg/Nm3
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 7000
(b)Source Dakshin Gujarat Vij Company Ltd.
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 2 Nos. of 1500 KVA of Each, 1 No. of 750 KVA
(e)Stack Height (in m) 15
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 0
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 10.510675
    Total Land (ha.) 10.51067
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 3787
(b)Waste/Barren Land (ha.) 10963
(c)Grazing/ Community Land (ha.) 0.0
(d)Surface Water Bodies (ha.) 189
(e)Settlements (ha.) 275
(f)Industrial (ha.) 10240
(g)Forest (ha.) 277
(h)Mangroves (ha.) 764
(i)Marine Area (ha.) 4921
(j)Others (ha.) : NA 0.0
    Total (ha.) 31416
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Built Up Area4.740843
(2.)Green belt3.479200
(3.)OthersApproach road(s)/ drains & Open area2.290632
Total (ha.) 10.510675
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaNA0--
(2.)NPANA0--
(3.)ESZsNA0--
(4.)ESAsNA0--
(5.)CorridorsNA0--
(6.)Wildlife CorridorsNA0--
(7.)WLSNA0--
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Archaeological SitesNA0--
(2.)Defence InstallationsNA0--
(3.)OthersNANA0--
(4.)ForestDahej Reserve Forest5.74--
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) Not Applicable
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 10.510675
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired NA
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? Yes
(i)Details of Schedule-I Species Indian Peafowl, Bengal Monitor Lizard
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? Yes
(i)Details of Water Bodies in Core Area Pond
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Reservoir, Pond, Estuary
(ii)Direction of Water Bodies in Buffer Area South East
(iii)Distance of Water Bodies in Buffer Area 5
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 350
(b)Permanent Employment-During Operation 500
(c)Temporary Employment- During Construction 250
(d)Temporary Employment- During Operation 400
(e)No. of working days 330
(f)Total Manpower 1500
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt3.479203.4792
(2.)Percentage of Total Project Area33.10033.1
(3.)No. of Plants640006400
(4.)Funds Allocated305080
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)FinancialRevenue generation by Exports. Emp generation
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1821/RA0104
(ii)Name of the EIA Consultant M/s. SIDDHI GREEN EXCELLENCE PVT. LTD.
(iii)Address Kamal Arcade – The Vertical Sunclock”, Comm. Plot No. C-3/3, Nr. SBI Industrial Branch, Station Road, G.I.D.C, Ankleshwar – 393 002, Gujarat State, India
(iv)Mobile No. 9824345895
(v)Landline No. 0264622480
(vi)Email Id siddhi.ank@gmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 27 Apr 2021
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAPlease clarify/inform/provide the following:- - Copy of the existing EC dated 3/7/2009 showing present pesticides production@12300 TPA. - Complete CCR dated 2/7/2019 to be uploaded against column 9 of Form-2 (presently only forwarding letter) - Industrial operations/units at plot No.42/4 & 44/4, GIDC Dahej-I. 06 Sep 2019
2.NAThe correction have been made as per the instruction received 07 Sep 2019
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1. ADS Reply LetterWe have uploaded additional documents as per minutes of the 19th EAC meeting. We request your goodself to consider our proposal and grant EC. 07 Jul 2020
2.NAPP vide email dated 06.07.2020 requested to upload the information as sough by the EAC in its earlier meeting, accordingly ADS generated: The request of PP is as: Respected Sir, Our unit, M/s. Bharat Rasayan Limited (Unit-II) at Plot No. 42/4, Amod Road, Dahej-I GIDC Industrial Estate, Dahej, District Bharuch, Gujarat, India has attended 19th Expert Appraisal Committee (Industry-2) Meeting held on 13th May, 2020 for consideration of EC of our Expansion project. We are not able to upload additional documents for M/s. Bharat Rasayan Limited ,Dahej on portal as per minutes of the 19th EAC meeting because ADS has not been raised by authority on parivesh portal. As per our understanding if ADS has been generated after that We can upload additional documents for EC -reconsideration. Proposal ID: IA/GJ/IND2/114039/2008 We request you to kindly advise to resolve above issue. 07 Jul 2020
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantAjay Kumar Gupta
DesignationDirector
Name of Company (Applicant Name should not be given here)BHARAT RASAYAN LIMITED BRL
Address1501, Vikram Tower, Rajendra Place, New Delhi
Print