Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Chintalayapalle Limestone Mine - The Ramco Cements Limited (Formerly Madras Cements Limited)
(b)Name of the Company / Organisation THE RAMCO CEMENTS LIMITED
(c)Registered Address THE RAMCO CEMENTS LIMITED (Formerly known as Madras Cements Ltd) Auras Corporate Centre 98-A Dr. ,THE RAMCO CEMENTS LIMITED (Formerly known as Madras Cements Ltd) Auras Corporate Centre 98-A Dr. ,Chennai,Tamil Nadu-521457
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Reddy Nagaraju Reddy
(b)Designation (Owner/ Partner/ CEO) President (Projects)
(c)Address The Ramco Cements Limited (Formerly Madras Cements Limited) Kalvatala project, Kolimigundla Mandal Nandyal District (Erstwhile Kurnool Dist) Andhra Pradesh Pin code:518 123,The ramco cements limited,,Krishna,Andhra Pradesh-521457
(d)Pin code 521457
(e)E-mail mcljpmqc@gmail.com
(f)STD Code. 865(f)Telephone No. 224400
(g)Fax No. 08654222352
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity1(a) Mining of minerals
Minor Activity
(b)Category A
(c)Proposal Number IA/AP/MIN/62749/2017
(d)Master Proposal Number(Single Window) SW/113799/2019
(e)EAC concerned (for category A Projects only) Non-Coal Mining
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. 2,3,5,6,7,8,9,10,11/1,11/2,12,13,14,15,23,24/1,24/
(b)Pincode 518123
(c)Bounded Latitudes (North)
From
Degree 1662826.52
Minutes
Second
From
Degree 1665213.92
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 187147.41
Minutes
Second
From
Degree 190146.08
Minutes
Second
(e)Survey of India Topo Sheet No. 57 I/4
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 306
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 10
(j)Seismic Zone 2
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Andhra Pradesh
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)Andhra PradeshKurnoolKolimigundla
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number IA-J-11015/15/2017-IA-II(M)
(b)Date of Apply of TOR 23 Feb 2017
(c)Date of Issue of TOR / Standard ToR 01 Jan 1900
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :08 Jan 2019
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :08 Feb 2019
Distance of Public Hearing Venue from the Proposed Project :0
Mining lease Area
State :Andhra Pradesh
District :Kurnool
Tehsil :Kolimigundla
Village :Chintalayapalle
5001. Provide employment opportunities to locals 2. Construct good hospital in the area 3. Drinking water facilities in the surrounding villages 4. Additional compensation to the farmers at the earlieDistrict Collector
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)4.0 MTPA Limestone MiningOpencast Method-
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Limestone4.0OthersMTPARoad
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 10.75
(b) Funds Allocated for Environment Management (Capital) (in Crores) 0.8
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.52
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.32
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 0
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 0
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)EXPLOSIVE476Tons per AnnumlocalRoad100 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Oct 2017 To 31 Dec 2017
(b)Season Post-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube59.343.658.9100
(2.)SO2Micro Gram per Meter Cube13.78.213.080
(3.)NOxMicro Gram per Meter Cube15.19.214.480
(4.)PM2.5Micro Gram per Meter Cube28.217.928.060
    14.2.     No. of Ground Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)TSSmg/l0000
(2.)TDSmg/l14066825002000
(3.)Total Hardnessmg/l585319200600
(4.)Fluoridemg/l0.960.6911.5
(5.)Chloridesmg/l328362501000
(6.)pHNA7.356.856.58.5
(7.)Heavy MetalsZincmg/l0.180.02515
    14.3.     No. of Surface Water monitoring locations : 1
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA7.720C
(2.)DOmg/l5.20C
(3.)CODmg/l100C
(4.)BODmg/l20C
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))54.750.655
(2.)Leq(Day)A-weighted decibels(dB(A))44.741.845
    14.5.     No. of Soil Sample Monitored locations : 8
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)N(Nitrogen)Kilogram per hectare491270
(2.)K(Potassium)Kilogram per hectare1070241
(3.)pH8.026.97
(4.)P(Phosphorus)Kilogram per hectare31013
(5.)Electric ConductivityOthersMicrosiemens per centimeter689143
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 45 To 50
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 40 To 45
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersCement Plant and later Mine pit1503.7Copy of Permission LettermodeOthersMobile water tankersOthersMobile water tankersNone08 Aug 2019150
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic88Septic tank followed by soak pitOthersSeptic tank followed by soak pit08
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 8
(b)Total Discharged Water (Kilolitre per Day) 8
(c)Total Reused Water (Kilolitre per Day) 0
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)No waste generationOthersNo waste generation0Tons0OthersNoneOthersNo waste generation
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)SO2Microgram per Meter Cube12.124.52.3615.1680
(2.)NOxMicrogram per Meter Cube14.214.214.2628.6680
(3.)PM2.5Microgram per Meter Cube28.1101.2229.3560
(4.)PM10Microgram per Meter Cube58.9011.6470.54100
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)NoneNone00OthersNone0
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 800
(b)Source For the mines lighting, portable generator sets wi
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) For the mines lighting, portable generator sets wi
(e)Stack Height (in m) 0
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 449.35
(c)Government Land (ha.) 42.20
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 491.55
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 0
(b)Waste/Barren Land (ha.) 42.20
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 0
(e)Settlements (ha.) 0
(f)Industrial (ha.) 0
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : Agricultural non irrigated land 449.35
    Total (ha.) 491.55
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Green belt51.69Life of Mine
(2.)Quarry Area437.35Life of Mine
(3.)OthersUn mined area2.51
Total (ha.) 491.55
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaNone0-
(2.)ESAsNone0-
(3.)ESZsNone0-
(4.)WLSNone0-
(5.)NPANone0-
(6.)CorridorsNone0-
(7.)Wildlife CorridorsNone0-
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestDhodiyam RF8.4SE
(2.)Archaeological SitesBelum Caves6.6NNE
(3.)Defence InstallationsNone0-
23.3.
(a)Whether Noc / Permission from the competent authority is required? Yes
(i)Uploaded Noc / Permission from the competent authority Copy of Noc / Permission from the competent authority
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 411.271
(b)Land yet to be acquired(Ha) 38.079
(c)Status of Land acquisition if not acquired Under Process
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? Yes
(i)Details of Schedule-I Species Blackbuck, Indian Peafowl
(b)Whether conservation plan for Schedule-I Species has been prepared ? Yes
(i)Uploaded copy of conservation plan Copy of conservation plan
(ii)Fund Provision made 165 Lakhs
(iii)Period of Implementation 10 years
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? Yes
(i)Uploaded copy of approval Copy of approval
(ii)Letter No. RC. No.9968/2018/WL-2
(iii)Date of issue 15 Jul 2019
(iv)Recommendation Conservation measures are recommended
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Mada Vagu - 3.0KM - NE Pedda Vanka – 5.0 km – NW
(ii)Direction of Water Bodies in Buffer Area North East
(iii)Distance of Water Bodies in Buffer Area 3.0
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 120
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 0
(e)No. of working days 300
(f)Total Manpower 120
32.
Green Belt in Ha:
(a)Total Area of Green Belt 51.69
(b)Percentage of Total Project Area 10.52
(c)No. of Plants to be Planted 77535
(d)Funds Allocated for Plantation 2600000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialDirect and indirect employment will be provided
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For Non-Coal Mining
S. No.Item Details
     1.       No. of Mineral(s) to be Mined : 1
S. No.Mineral(s) to be Mined Major or Minor Mineral
(1.)LimestoneMajor
2.
Mine Capacity in ROM (Run of Mine) 4.166
3.
Uploaded 500 meters Cluster Certificate from State Mines and Geology in case of minor minerals Copy of 500 meters Cluster Certificate from State Mines and Geology
4.
Mining Plan:
(a)Approval Letter No. AP/KNL/MP/LST-51/HYD
(b)Date of Approval 15 Jun 2018
(c)Approved Letter Copy of Approved Letter
(d)Approved By State Mining and Geology Department IBM
(e)Approved Mining Lease Area 491.55
(f)Approved Capacity 4.0
5.
Technical Details:
(a)Total Geological Reserves (Million Ton) 144.079
(b)Mineable Reserves (Million Ton) 144.079
(c)Extractable Reserves(Million Ton) 144.079
(d)Percent(%) of Extraction 100
(e)Grade of Coal /Ore /Mineral Cement Grade
(f)Stripping Ratio 1 : 0.067
(g)Category of Gaseousness (Only for Coal Mining, Others may Write NA) NA
(h)Average Gradient(Degree) 5 - 7
(i)Mining Method Opencast
(j)Life of Mine (Years) 36
6.
Details of Beneficiations:
(a)Whether it is proposed to install beneficiation plant/Coal washery within the mining lease area No
(b)Whether it is proposed to install crusher within the mining lease area No
7.
Details of Seams:
(a)Whether details of seam applicable No
8.
Details of Mining Lease:
(a)Mining Lease Area (in Hectare) 491.55
(b)Whether obtained Letter of Intent (LOI) from the state government ? Yes
(i)Copy of Letter of Intent Copy of Letter of Intent
(ii)Date of issue of LOI 15 Feb 2000
(iii)Validity of LOI 50
(iv)Reference No. of LOI GO Ms. No. 4 dated 03.01.2019
(c)Whether Lease Deed Executed ? Yes
(i)Copy of Executed Lease deed valid as on Date Copy of Executed Lease deed
(ii)Provide area in Hectare as per executed lease deed (initial) document 491.55
(iii)Validity of the lease deed From : 15 Feb 2000 To : 08 Aug 2050
(iv)Date of Execution of Mining Lese 26 Mar 2019
(v)Reference Number Proceedings no. 1333/M4/2000
(d)Whether Lease Deed Renewed ? No
(i)Reason thereof valid up to 2050
9.
OB (Over Burden) Management:
(a) Details of External Dumps:
(i)No. of OB Dumps 0
(ii)Total Area (in Hectare) 0
(iii)Height (in meter) 0
(iv)Quantity (in Million Cubic meter) 0
(v)No. of year back fill up 0
(b) Details of Internal Dumps:
(i)No. of Internal Dumps 0
(ii)Total Area (in Hectare) 0
(iii)Height (in meter) 0
(iv)Quantity (in Million Cubic meter) 0
10.
Details of Topsoil Management:
(a)Quantity of Topsoil excavated during the entire life of the mine (in Million Cubic metre) 6.114
(b)Quantity of Topsoil proposed for utilization for reclamation during the entire life of the mine (in Million Cubic metre) 0
(c)Quantity of Topsoil proposed for utilization for other activities during the entire life of the mine (in Million Cubic metre) 6.114
11.
Details of Final Mine Void:
(a)Area (in Hectare) 437.35
(b)Depth (in meter) 29
(c)Volume (in Million Cubic meter) 126.831
12.
Details of Quarry:
(a)Final Void of 437.35 (hectare) at a Depth of 29 meter which is Proposed to be Converted into a Water Body.
(b)Total Quarry Area (ha) 491.55
13.
Details of Transportation:
(a)In Pit/Underground to Surface BY ROAD
(b)Surface to Siding/Loading By road up to crusher
(c)Transportation / Conveyor Details BY ROAD
     14.      Details of Land Usage (Pre-Mining)
S. No.LAND USE Other LAND USEWITHIN ML AREA (Hectare)OUTSIDE ML AREA (Hectare)TOTAL (Hectare)
(1.)WASTE LAND42.20042.2
(2.)AGRICULTURE LAND000
(3.)OTHERS(Specify)Private Non Irrigated Agricultural land449.350449.35
(4.)GRAZING LAND000
(5.)SURFACE WATER BODIES000
(6.)SETTLEMENTS000
(7.)FOREST LAND000
TOTAL491.550491.55
     15.      Details of Land Usage (Post-Mining)
S. No.LAND USE Other LAND USEPlantation (ha)Water Body (ha)Public Use (ha)Undisturbed (ha)Total
(1.)EXCAVATION/QUARRY0437.350437.35
(2.)VIRGIN AREA002.512.51
(3.)TOP SOIL STORAGE0000
(4.)BUILT UP AREA (COLONY/OFFICE)0000
(5.)INTERNAL OB DUMPS0000
(6.)GREEN BELT51.690051.69
(7.)EXTERNAL OB DUMPS0000
(8.)ROADS0000
TOTAL51.69437.352.510491.55
16.
Details of Reclamation:
Total Afforestation Plan shall be Implemented Covering of Mining.
This will Include:
(a)External OB Dump(in hectare) 0
(b)Internal Dump(in hectare) 0
(c)Quarry(in hectare) 491.55
(d)Safety Zone(in hectare) 51.69
(e)Final Void of 437.35 (hectare) at a Depth of 29 meter which is Proposed to be Converted into a Water Body.
(f)Density of Tree Plantation per ha (in no.) 1500
(g)Others in ha (such as Excavation Area along ML Boundary, along Roads and Infrastructure, Embankment Area and in Township Located Outside the Lease etc) 0
(h)Total afforestation plant (in hectare) 51.69
17.
Status of progressive Mining Closure Plan:
Details Not Applicable
     18.      Details of Actual Coal/ ORE Production vis-a-vis Sanctioned Capacity since the Inception:
S. No.Financial Year Sanctioned Capacity as per EC (MTPA)Sanctioned Capacity as per CTOSanctioned Capacity as per approved mining planActual Production Excess Production Beyond the EC / CTO/ Mining Plan Sanctioned Capacity (MTPA)
(1.)000000
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1619/SA 064
(ii)Name of the EIA Consultant B.S. Envi – Tech Pvt. Ltd
(iii)Address B. S. Envi-Tech Pvt Ltd., Amity Ville, 12-13-1270/71/73, 4th Floor, St. Ann's School Road, Tarnaka, Secunderabad
(iv)Mobile No. 9848053012
(v)Landline No. 0404978306
(vi)Email Id info@bsenvitech.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Non-Coal Mining
(ix)Validity of Accreditation 12 Nov 2019
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
      Essential Detail Sought : NIL
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantReddy Nagaraju Reddy
DesignationPresident (Projects)
Name of Company (Applicant Name should not be given here)THE RAMCO CEMENTS LIMITED
AddressTHE RAMCO CEMENTS LIMITED (Formerly known as Madras Cements Ltd) Auras Corporate Centre 98-A Dr.
Print