Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) HINDUPUR STEEL & ALLOYS PVT. LTD.
(b)Name of the Company / Organisation HINDUPUR STEEL AND ALLOYS PRIVATE LTD
(c)Registered Address PLOT NO-29, APIIC INDUSTRIAL PARK (PHASE-3), GOLLAPURAM VILLAGE, HINDUPUR MANDAL, ANANTAPUR DISTRICT, ANDHRA PRADESH,,Anantapur,Andhra Pradesh-515211
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant GANESH AGRAWAL
(b)Designation (Owner/ Partner/ CEO) DIRECTOR
(c)Address Regd. office-2142, Ramachandra Reddy Building, Near Reliance Petrol Pump, B.H. Road, Gauribidanur, Chikkaballapur, Dist. Karnataka -561208,,Chikkaballapura,Chikkaballapura,Karnataka-561208
(d)Pin code 561208
(e)E-mail hindupursteelmoef@gmail.com
(f)STD Code. 8155(f)Telephone No. 41462660
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity3(a) Metallurgical industries (ferrous & non ferrous)
Minor Activity
(b)Category A
(c)Proposal Number IA/AP/IND/3712/2012
(d)Master Proposal Number(Single Window) SW/113273/2019
(e)EAC concerned (for category A Projects only) Industrial Projects - 1
(f)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Plot No.29, APIIC Industrial Park Gollapuaram
(b)Pincode 515211
(c)Bounded Latitudes (North)
From
Degree 13.712331
Minutes
Second
From
Degree 13.713675
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 77.514164
Minutes
Second
From
Degree 77.516789
Minutes
Second
(e)Survey of India Topo Sheet No. 57 G/10
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 678
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 3.2
(j)Seismic Zone 2
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Andhra Pradesh
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)Andhra PradeshAnantapurHindupur
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number J-11011/250/2012-IA.II(I)
(c)Date of Issue of TOR 01 Jan 1900
(f)Previous TOR Letter Copy of Previous TOR letter
(b)Date of Apply of EC 21 Jan 2015
(c)Date of Issue of EC 26 Dec 2019
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :14 Apr 2018
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :17 May 2018
Distance of Public Hearing Venue from the Proposed Project :3.5
near premises of APIIC Office Premises, Thumkunta Check Post
State :Andhra Pradesh
District :Anantapur
Tehsil :Hindupur
Village :Thumkunta
110Employment, Wages, Mineral Water Plant, DispensaryOthersAdditional District Magistrate
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Chennai
(iii)Letter No. EP/12.1/2015-16/11/AP/1917
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit Nov 13 2017 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Rolled Products100000200000300000Tons per Annum(TPA)Road
(2.)Producer gas60001200018000OthersCum/hrOthersCaptive consumption
(3.)Hot metal / MS ingots / MS billets10000045000145000Tons per Annum(TPA)OthersCaptive consumption
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)INDUCTION FURNACE1X8 MT & 2X12 MT1X15 MT1x8 MT, 2x12 MT & 1x15 MT
(2.)Producer Gas60001200018000used as Fuel in Rolling Mill
(3.)Rolling mill100000200000300000Up-gradation of existing unit from 1,00,000 TPA to 1,50,000 TPA & Additional 1,50,000 TPA unit
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 01 Jun 2018
(iv)Valid Upto 30 Apr 2023
(v)File No. APPCB/KNL/KNL/192/CFO/HO/2016
(vi)Application No. APPCB/KNL/KNL/192/CFO/HO/2016
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 40
(b) Funds Allocated for Environment Management (Capital) (in Crores) 5
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.4
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.84
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? Yes
d)Inter-State boundaries and international boundaries Yes
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? Yes
8.(a) If any Industrial Estate/Complex / Export processing Zones /Special Economic Zones/Biotech Parks / Leather Complex with homogeneous type of industries such as Items 4(d), 4(f), 5(e), 5(f), or those Industrial estates with pre –defined set of activities (not necessarily homogeneous, obtains prior environmental clearance, individual industries including proposed industrial housing within such estates /complexes will not be required to take prior environmental clearance, so long as the Terms and Conditions for the industrial estate/complex are complied with (Such estates/complexes must have a clearly identified management with the legal responsibility of ensuring adherence to the Terms and Conditions of prior environmental clearance, who may be held responsible for violation of the same throughout the life of the complex/estate
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 94000
(b)Existing quantity of raw material/fuel 42000
(c)Total quantity of raw material/fuel 136000
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Billets210000Tons per AnnumInhouse & Gollapuram / BellaryRoad220 Open MarketCopy of Linkage
(2.)Sponge Iron42000Tons per AnnumBellary, KarnatakaRoad220 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Oct 2017 To 31 Dec 2017
(b)Season Post-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)SO2Micro Gram per Meter Cube19.47.319.480
(2.)PM2.5Micro Gram per Meter Cube44.617.244.560
(3.)OthersCOMicro Gram per Meter Cube122567812202000
(4.)PM10Micro Gram per Meter Cube78.230.678.0100
(5.)NOxMicro Gram per Meter Cube25.18.025.180
    14.2.     No. of Ground Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)TDSmg/l6332845002000
(2.)Heavy MetalsIronmg/l0.220.0250.31.0
(3.)Total Hardnessmg/l294145300600
(4.)pHmg/l8.27.36.58.5
(5.)TSSmg/l1.20.400
(6.)Chloridesmg/l3041662501000
(7.)Fluoridemg/l0.940.321.01.5
    14.3.     No. of Surface Water monitoring locations : 4
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)BODmg/l2.91.9A
(2.)CODmg/l10.77.8A
(3.)pHOthersNA8.07.1A
(4.)DOmg/l5.44.1A
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))704375
(2.)Leq(Night)A-weighted decibels(dB(A))613470
    14.5.     No. of Soil Sample Monitored locations : 8
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pHOthersNA7.67.1
(2.)K(Potassium)Kilogram per hectare12274
(3.)N(Nitrogen)Kilogram per hectare20541
(4.)P(Phosphorus)Kilogram per hectare8715
(5.)Electric ConductivityMillisiemens per Centimetre15955
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 10 To 5
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 2 To 5
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)Surface152160Copy of Permission LetterPipelineOthersAPIICM(AM)/IP/-GPM/P-29/HSAPL/2011-1205 Aug 2014283
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Sanitary wastewater from Domestic Consumption1.61.6Septic Tank followed by Subsurface dispersionOthersSeptic Tank followed by Subsurface dispersion01.6
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 1.6
(b)Total Discharged Water (Kilolitre per Day) 1.6
(c)Total Reused Water (Kilolitre per Day) 0
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)End cuttings from Rolling MillIndustrial Waste8000Tons0OthersRe used in IFOthersRe used in IF
(2.)Tar from GasifierHazardous Waste (as per Hazardous and Other Waste Management rules 2016)0.25Tons25RoadOthersGiven to TAR recyclers
(3.)Slag from SMSIndustrial Waste4500Tons25RoadOthersAfter recovery of iron,used for road construction.
(4.)Mill Scale from Rolling MillIndustrial Waste2000Tons5RoadOthersgiven to nearby Ferro alloys
(5.)Ash & Dust from APCSOthersfrom APCS17Tons5Roadbrick manufacturingOthersbrick manufacturing
(6.)Waste oilHazardous Waste (as per Hazardous and Other Waste Management rules 2016)0.3Kilolitre100RoadAuthorized Recyclers
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube78.20.81.5879.8100
(2.)SO2Microgram per Meter Cube19.40.84.924.380
(3.)PM2.5Microgram per Meter Cube440.80.94560
(4.)NOxMicrogram per Meter Cube250.87.332.480
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)ROLLING MILLProducer Gas541.7PM101.1
(2.)ROLLING MILLProducer Gas541.7SO217.8
(3.)ROLLING MILLProducer Gas541.7NOx4.6
(4.)Induction FurnaceElectricity301.0PM100.5
(5.)Induction FurnaceElectricity301.0NOx1.9
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 20600
(b)Source State Grid
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 500 KVA
(e)Stack Height (in m) 7
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 0
(c)Government Land (ha.) 4.05
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 4.05
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 0
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 0
(e)Settlements (ha.) 0
(f)Industrial (ha.) 4.05
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : 0 0
    Total (ha.) 4.05
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Main Plant1.21Built-up area
(2.)Green belt1.34
(3.)OthersStorage area & Internal Roads etc1.5
Total (ha.) 4.05
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaNil0None within 10 Kms. radius
(2.)WLSNil0None within 10 Kms. radius
(3.)NPANil0None within 10 Kms. radius
(4.)ESAsNil0None within 10 Kms. radius
(5.)ESZsNil0None within 10 Kms. radius
(6.)CorridorsNil0None within 10 Kms. radius
(7.)Wildlife CorridorsNil0None within 10 Kms. radius
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestNone0None within 10 Kms. radius
(2.)Defence InstallationsNone0None within 10 Kms. radius
(3.)Archaeological SitesNone0None within 10 Kms. radius
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 4.05
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired Land has been taken on lease from APIIC
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Penneru River
(ii)Direction of Water Bodies in Buffer Area West
(iii)Distance of Water Bodies in Buffer Area 3.2
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 50
(c)Temporary Employment- During Construction 150
(d)Temporary Employment- During Operation 0
(e)No. of working days 365
(f)Total Manpower 200
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt1.3401.34
(2.)Percentage of Total Project Area33033
(3.)No. of Plants201702017
(4.)Funds Allocated404
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialThe local areas will be benefited by way of generation of employment opportunities, increased demand for local products and services. There will be an overall improvement in the income level of the local people.
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 1
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/ EIA/ 1619/ RA 026
(ii)Name of the EIA Consultant PIONEER ENVIRO LABORATORIES & CONSULTANTS PVT. LTD
(iii)Address 2nd Floor, A-Z Elite, Plot No. 197, Kavuri Hills, Guttala Begumpet Village, Madhapur, Hyderabad, Telangana - 500081
(iv)Mobile No. 9440677333
(v)Landline No. 0402311427
(vi)Email Id pelcpl@yahoo.co.in
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 1
(ix)Validity of Accreditation 25 Oct 2019
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File NA
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
      Essential Detail Sought : NIL
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantGANESH AGRAWAL
DesignationDIRECTOR
Name of Company (Applicant Name should not be given here)HINDUPUR STEEL AND ALLOYS PRIVATE LTD
AddressPLOT NO-29, APIIC INDUSTRIAL PARK (PHASE-3), GOLLAPURAM VILLAGE, HINDUPUR MANDAL, ANANTAPUR DISTRICT, ANDHRA PRADESH
Print