1. Project Details
   Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? : No
1. Project Details
   i. Proposal No. : IA/RJ/MIN/20291/2013    ii. MoEFCC File No. : J-11015/231/2013-IA.II (M)    iii.Short narrative of the project: Bajri Mine (Minor Mineral)    iv. Project Sector : Mining Projects    v. Company/Proponent : M/s Shri Sanjay Kumar Garg
  vi.Details of State of the project
Details of State of the project
S.no. State Name District Name Tehsil Name
1.RajasthanBhilwaraBhilwara
 
   vii.Date of TOR Granted 17 Oct 2013 viii.TOR letter issued by Ministry: Annexure-TOR letter ix.Date of Submission for EC: 09 May 2015 x.Project Type: New
2. Uploaded Documents of EIA/EMP,Risk Assessment,Public Hearing etc.
i.EIA/EMP: Annexure-EIA/EMP ii.Risk Assessment: Annexure-Risk Assessment iii.Public Hearing: Annexure-Public Hearing    iv. Date of Public Hearing: 23 Dec 2014   v. Uploaded Additional Report/Study/Document as desired by Ministry/EAC: Annexure-Additional Report/Study/Document   vi. Uploaded Cover Letter: Annexure-Cover Letter   vii.Remarks: The EIA/ EMP report is being uploaded for final EC consideration.
3. Additional Detail Sought
Additional Detail Sought
Sno. ADS Letter Remarks Date of ADS
1. ADS LetterAdditional Information 27 Jun 2016
2. ADS LetterDear Sir In compliance to additional details sought, enclosed is the replenishment study report carried out by CMPDI. 30 Dec 2017
3. ADS Letterai 05 Feb 2018
4. ADS LetterDear Sir Enclosed is the Scientific Replenishment study Report. Kindly consider the same and accord EC. 13 Mar 2018
5.NAPlease submit complete information in compliance of Special EAC Committee held on 8.01.2018 26 Apr 2018
6. ADS LetterDear Sir Please find complete information in compliance of Special EAC Committee held on 8.01.2018 26 Apr 2018
7. ADS Letterai 04 Jul 2018
8. ADS LetterPlease find attached herewith the replenishment study report for Sand mining Project of Sanjay Kumar Garg located at Village: Suwana, Kodukota Tehsil: Bhilwara. District: Bhilwara State: Rajasthan (Area 1947.12hect.) duly prepared and verified by irrigation Department as well as Department of Mines & Geology Rajasthan complying the points raised by EAC in its 32ND meeting held on May 30-31, 2018. The point wise compliance of 32nd EAC Meeting held on May 30-31, 2018 and the additional information as required during discussion in 16th EAC meeting held on 5-6 May 2020 is also submitted hereby for your ready reference:- 31 Aug 2020
9.NAThe proposal was considered in EAC meeting held during 23-25th sep, 2020. the committee deliberated on the submissions made by the project proponent and presentation made by the consultant in the meeting and deferred the proposal and sought the following information: - (1) The project proponent needs to carry out the fresh baseline data for one-month period (non-monsoon season). The project proponent should submit the photograph of monitoring stations & sampling locations. The photograph should bear the date, time, latitude & longitude of the monitoring station/sampling location. In addition to this project proponent should submit the original test reports and certificates of the labs which will analyze the samples. (2) The project proponent needs to submit the list of flora and fauna, list of schedule-1 species authenticated by the chief wildlife warden. (3) The project proponent needs to submit the action plan as per Enforcement & Monitoring guidelines of sand mining 2020. (4) The project proponent needs to submit the detailed transportation plan as per the Enforcement & Monitoring guidelines of sand mining 2020. Project proponent should clearly show the transport route of the mineral and protection and mitigative measure to be adopted during transportation. (5) The project proponent needs to compare the current baseline data with the previous baseline data. If any changes exist, then detailed mitigation measures needs to be provided. (6) The project proponent shall prepare the conservation plan in consultation with the State Forest Department and approved by the Chief wildlife warden. (7) The project proponent needs to submit the detailed plan in tabular format (year-wise) for afforestation and green belt development in and around the mining lease. The project proponent should submit the number of saplings to be planted, area to be covered under afforestation & green belt, location of plantation, target for survival rate and budget earmarked for the afforestation & green belt development. (8) Project proponent should clearly bring out the details of the manpower to be engaged for this project with their roles /responsibilities/designations. 19 Oct 2020
10. ADS LetterThe proposal was considered in EAC meeting held during 23-25th sep, 2020. the committee deliberated on the submissions made by the project proponent and presentation made by the consultant in the meeting and deferred the proposal and sought the following information: - (1) The project proponent needs to carry out the fresh baseline data for one-month period (non-monsoon season). The project proponent should submit the photograph of monitoring stations & sampling locations. The photograph should bear the date, time, latitude & longitude of the monitoring station/sampling location. In addition to this project proponent should submit the original test reports and certificates of the labs which will analyze the samples. (2) The project proponent needs to submit the list of flora and fauna, list of schedule-1 species authenticated by the chief wildlife warden. (3) The project proponent needs to submit the action plan as per Enforcement & Monitoring guidelines of sand mining 2020. (4) The project proponent needs to submit the detailed transportation plan as per the Enforcement & Monitoring guidelines of sand mining 2020. Project proponent should clearly show the transport route of the mineral and protection and mitigative measure to be adopted during transportation. (5) The project proponent needs to compare the current baseline data with the previous baseline data. If any changes exist, then detailed mitigation measures needs to be provided. (6) The project proponent shall prepare the conservation plan in consultation with the State Forest Department and approved by the Chief wildlife warden. (7) The project proponent needs to submit the detailed plan in tabular format (year-wise) for afforestation and green belt development in and around the mining lease. The project proponent should submit the number of saplings to be planted, area to be covered under afforestation & green belt, location of plantation, target for survival rate and budget earmarked for the afforestation & green belt development. (8) Project proponent should clearly bring out the details of the manpower to be engaged for this project with their roles /responsibilities/designations. 19 Oct 2020
11. ADS LetterThe proposal was considered in EAC meeting held on 23-25th Sep, 2020. the committee deliberated on the submissions made by the project proponent and presentation made by the consultant in the meeting and deferred the proposal and sought the following information: - (1) The project proponent needs to carry out the fresh baseline data for one-month period (non-monsoon season). The project proponent should submit the photograph of monitoring stations & sampling locations. The photograph should bear the date, time, latitude & longitude of the monitoring station/sampling location. In addition to this project proponent should submit the original test reports and certificates of the labs which will analyze the samples. (2) The project proponent needs to submit the list of flora and fauna, list of schedule-1 species authenticated by the chief wildlife warden. (3) The project proponent needs to submit the action plan as per Enforcement & Monitoring guidelines of sand mining 2020. (4) The project proponent needs to submit the detailed transportation plan as per the Enforcement & Monitoring guidelines of sand mining 2020. Project proponent should clearly show the transport route of the mineral and protection and mitigative measure to be adopted during transportation. (5) The project proponent needs to compare the current baseline data with the previous baseline data. If any changes exist, then detailed mitigation measures needs to be provided. (6) The project proponent shall prepare the conservation plan in consultation with the State Forest Department and approved by the Chief wildlife warden. (7) The project proponent needs to submit the detailed plan in tabular format (year-wise) for afforestation and green belt development in and around the mining lease. The project proponent should submit the number of saplings to be planted, area to be covered under afforestation & green belt, location of plantation, target for survival rate and budget earmarked for the afforestation & green belt development. (8) Project proponent should clearly bring out the details of the manpower to be engaged for this project with their roles /responsibilities/designations. 19 Oct 2020
4. Accredited Consultant Details
   i. Accreditation status : Yes    ii. Accreditation No. : 45    iii. Name of Consultant: ENKAY ENVIRO SERVICES PVT. LTD   iv. Address : 24-B, Dadu Marg, Gopal Bari, Jaipur (Raj.) - 302001   v. Mobile No.: 9314363996   vi. Landline No.: 1414013996   vii. Email Id: bhilwarabajri@gmail.com
5. Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
   i. Name of Applicant : Sanjay    ii. Designation : Lessee    iii. Name of Company(Applicant Name should not be given here) : SANJAY KUMAR GARG    iv. Address : MRS Group, A-24, Ambabari, Near Chomu Puliya Jaipur (Rajasthan) v. Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency: NIL
Print