Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Proposed Biomass based Renewal Fuel Plant
(b)Name of the Company / Organisation M/S. SUN LIGHT FUELS PVT. LTD.
(c)Registered Address village, Bhikhpur, Tehsil-Hargaon, Disrict-Sitapur, Uttar Pradesh, India,,Sitapur,Uttar Pradesh-261121
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Nishant singhal
(b)Designation (Owner/ Partner/ CEO) Director
(c)Address M-58, M Block Market Greater Kailsh-2, New Delhi,,Kalkaji,South,Delhi-111092
(d)Pin code 111092
(e)E-mail nishant@sunlightfuels.in
(f)STD Code. 11(f)Telephone No. 24211477
(g)Fax No. 29216352
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
Minor Activity
(b)Category A
(c)Proposal Number IA/UP/IND2/71266/2017
(d)Master Proposal Number(Single Window) SW/111795/2019
(e)EAC concerned (for category A Projects only) Industrial Projects - 2
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Bhikpur Village, Tehsil Sitapur
(b)Pincode 261121
(c)Bounded Latitudes (North)
From
Degree 27.779578
Minutes
Second
From
Degree 27.786550
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 80.751681
Minutes
Second
From
Degree 80.755742
Minutes
Second
(e)Survey of India Topo Sheet No. 63 A/9, 63 A/10, 63 A/13, 63 A/14
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 147
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 8.0
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Uttar Pradesh
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)Uttar PradeshSitapurSitapur
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number IA-J-11011/555/2017-IA-II(I)
(b)Date of Apply of TOR 10 Jan 2018
(c)Date of Issue of TOR / Standard ToR 22 Mar 2018
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :07 Mar 2019
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :12 Apr 2019
Distance of Public Hearing Venue from the Proposed Project :0
Project Site
State :Uttar Pradesh
District :Sitapur
Tehsil :Sitapur
Village :Bhikpur
43During the public hearing proceedings the issues raised by the local peoples were regarding control the waste water pollution , justified compensation to the people for there acquired land , health fOthersADM
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Bagasse Storage6.07
(2.)Product Storage0.2
(3.)Raw Water Storage0.53
(4.)Open Area for Construction/ Future Expansion0.81
(5.)Green Belt12.02
(6.)Total Plot Area36.42
(7.)LPG Mounted Storage0.12
(8.)Process Area16.67
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Gasoline / Diesel175OthersKLDRoad
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 15 Jan 2019
(iv)Valid Upto 15 Feb 2022
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 1234
(b) Funds Allocated for Environment Management (Capital) (in Crores) 11.88
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 6.70
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.895
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 165500
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 165500
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Bagasse165500OthersMTPAFrom nearby Sugar MillRoad50 MoUPOCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Mar 2018 To 31 May 2018
(b)Season Pre-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)NOxMicro Gram per Meter Cube17.710.217.780
(2.)PM2.5Micro Gram per Meter Cube45204560
(3.)PM10Micro Gram per Meter Cube964895100
(4.)SO2Micro Gram per Meter Cube9.14.88.880
(5.)OthersNH3Micro Gram per Meter Cube16916400
    14.2.     No. of Ground Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)TSSmg/l21.900
(2.)Heavy MetalsIronmg/l0.280.200.30
(3.)pHNA7.997.766.58.5
(4.)TDSmg/l4763445002000
(5.)Chloridesmg/l72202501000
(6.)Total Hardnessmg/l310208200600
(7.)Fluoridemg/l0.660.2611.5
(8.)OthersTotal Alkalinitymg/l436220200600
    14.3.     No. of Surface Water monitoring locations : 1
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA7.757.75C
(2.)DOmg/l7.07.0C
(3.)BODmg/l2.62.6C
(4.)CODmg/l1818C
(5.)OthersTemperatureOthersDegree Centigrade25.925.9C
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))63.051.055
(2.)Leq(Night)A-weighted decibels(dB(A))56.142.165
    14.5.     No. of Soil Sample Monitored locations : 4
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)K(Potassium)Kilogram per hectare168.5116.6
(2.)pH7.847.65
(3.)P(Phosphorus)Kilogram per hectare22.414.2
(4.)Electric ConductivityMillisiemens per Centimetre449.5368.4
(5.)N(Nitrogen)Kilogram per hectare285.5265.8
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 4 To 6
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 2 To 4
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater1708.80.5 Not Appliacble PipelineTube WellNA15 Jan 20191708.8
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Boiler/DM Water Plant5.20Ultra filtration/RO/MEBGreen Belt Renewal Plant5.2
(2.)Cooling Tower100Ultrafiltration/RO/MEBReuse within the Plant & Recycling10
(3.)Potable/ Service water0.80.8STPReuse within the Plant & Recycling0.8
(4.)Process18.20Not requiredReuse within the Plant & Recycling18.2
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 34.2
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 34.2
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Guard Bed FillIndustrial Waste4Tons0RoadAuthorized Recyclers
(2.)Vapour Phase HSD CatalystIndustrial Waste2.125Tons50RoadAuthorized Recyclers
(3.)Zinc OxideIndustrial Waste30Tons50RoadAuthorized Recyclers
(4.)LT Shift CatalystIndustrial Waste5.4Tons50RoadAuthorized Recyclers
(5.)Liquid Phase HSD CatalystIndustrial Waste0.75Tons50RoadAuthorized Recyclers
(6.)Steam Methane Reforming CatalystIndustrial Waste2.3Tons50RoadAuthorized Recyclers
(7.)H2 Plant LT Shift CatalystIndustrial Waste2.34Tons50RoadAuthorized Recyclers
(8.)H2 Plant HT Shift CatalystIndustrial Waste2.2Tons50RoadAuthorized Recyclers
(9.)Aromatics Saturation CatalystIndustrial Waste1.175Tons50RoadAuthorized Recyclers
(10.)Hydro Conversion CatalystIndustrial Waste17.375Tons50RoadAuthorized Recyclers
(11.)Boiler AshFly Ash7300Tons10RoadOthersAs the ash has NPK value hence given to farmers
(12.)CharOthersProcess Waste16060Tons00Conveyor BeltOthersByproduct & used in Boiler as fuel
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube900.32.4292.43100
(2.)PM2.5Microgram per Meter Cube410.31.6142.6260
(3.)SO2Microgram per Meter Cube7.60.30.1547.75580
(4.)NOxMicrogram per Meter Cube16.50.31.6618.1780
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)Char Boiler StackChar601.4OthersPM, SO2, NOxNA
(2.)HT Plant ReformerFurnace Oil601.4OthersPM, SO2, NOx, CO, VOCNA
(3.)Flare StackFurnace Oil600.35OthersPM, SO2, NOx, VOCNA
(4.)Hot Oil HeaterFurnace Oil501.0OthersPM,SO2, NOx,VOCNA
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 9000
(b)Source State Grid/Captive Generation
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 2000kVA
(e)Stack Height (in m) 4
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 36.42
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 36.42
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 32323
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 222
(e)Settlements (ha.) 779
(f)Industrial (ha.) 0
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : Others (open scrub land, Vegetation) 545
    Total (ha.) 33869
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Main Plant24.4
(2.)Green belt12.02
Total (ha.) 36.42
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)WLSNone0-
(2.)NPAProtected Forest9.8SW
(3.)Critically Polluted AreaNone0-
(4.)ESAsNone0-
(5.)CorridorsNone0-
(6.)Wildlife CorridorsNone0-
(7.)ESZsNone0-
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestProtected Forest9.8-
(2.)Archaeological SitesNone0-
(3.)Defence InstallationsNone0-
(4.)OthersSeismic Zone30-
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 36.42
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired Land is already acquired
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area 222 ha/Sarayan River, Jamuari River & Irrigation Canal
(ii)Direction of Water Bodies in Buffer Area North West
(iii)Distance of Water Bodies in Buffer Area 8
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 100
(c)Temporary Employment- During Construction 350
(d)Temporary Employment- During Operation 0
(e)No. of working days 330
(f)Total Manpower 450
32.
Green Belt in Ha:
(a)Total Area of Green Belt 12.02
(b)Percentage of Total Project Area 33.00
(c)No. of Plants to be Planted 14400
(d)Funds Allocated for Plantation 207.27
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)Financial? The greenbelt development area and tree plantation will help in enhancing the aesthetics of the plant. The greenbelt development area and tree plantation will help to minimize the noise levels and suitable measures will be adopted during both construction and operation phase. Short term positive impacts will result in better quality of life. ? The proposed project will generate direct and indirect employment opportunities. ? The project will be beneficial to local people as the company progr
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1619/SA070; July 17, 2018 , Extension No
(ii)Name of the EIA Consultant EQMS India Pvt. Ltd.
(iii)Address 304-305, 3rd Floor, Plot No. 16, Rishabh Corporate Tower, Community Centre, Karkardooma, Delhi – 110092
(iv)Mobile No. 9650002530
(v)Landline No. 0113000320
(vi)Email Id eqms@eqmsindia.org
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 23 Nov 2019
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File NA
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAPlease inform/clarify the following:- - Categorization of the project/activity in terms of the items listed in the schedule to the EIA Notification, 2006 to ascertain its applicability. - Accreditation of the EIA Consultant is no more valid. What is the present status of assessment. - Permission from the concerned regulatory authority for ground water withdrawal of 1708 cum/day. 11 Aug 2019
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantNishant singhal
DesignationDirector
Name of Company (Applicant Name should not be given here)M/S. SUN LIGHT FUELS PVT. LTD.
Addressvillage, Bhikhpur, Tehsil-Hargaon, Disrict-Sitapur, Uttar Pradesh, India