EC Report
1. Project Details
   Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? : No
1. Project Details
   i. Proposal No. : IA/AS/IND2/27521/2012    ii. MoEFCC File No. : J-11011/563/2011-IA-II    iii.Short narrative of the project: Development (2Nos.)/Exploratory (3Nos.) wells, Group Gathering station and pipe line Kasomarigaon    iv. Project Sector : Industrial Projects-3    v. Company/Proponent : Oil And natural Gas Corporation
  vi.Details of State of the project
Details of State of the project
S.no. State Name District Name Tehsil Name
1.AssamGolaghatSarupathar
 
   vii.Date of TOR Granted 28 May 2012 viii.TOR letter issued by Ministry: Annexure-TOR letter ix.Date of Submission for EC: 06 Aug 2015 x.Project Type: New
2. Uploaded Documents of EIA/EMP,Risk Assessment,Public Hearing etc.
i.EIA/EMP: Annexure-EIA/EMP ii.Risk Assessment: Annexure-Risk Assessment iii.Public Hearing: Annexure-Public Hearing    iv. Date of Public Hearing: 20 Sep 2014   v. Uploaded Additional Report/Study/Document as desired by Ministry/EAC: Annexure-Additional Report/Study/Document   vi. Uploaded Cover Letter: Annexure-Cover Letter   vii.Remarks: Unable to fetch existingTOR(J-111011/30/2012 IA-II(I)dted 28.5.2012 from MoEF site forthis project namely"Dev.&Expl.wells, const of GGS&layingof pipeline at Kasmarigaon",hence uploadedTOR as addl doc.
3. Additional Detail Sought
Additional Detail Sought
Sno. ADS Letter Remarks Date of ADS
1.NAProposal considered in 3rdEAC meeting held in 18-19th January, 2016. Stage 1 forest clearance to be obtained. PP has not submitted the a copy of stage-1 forest clearance till date. 07 Nov 2016
2. ADS LetterNA 09 Dec 2016
3.NAPlease provide the following information for further action into the matter: (i) Whether the user agency had sought permission for exploration by applying on form C or form A need to be ascertained (ii) Copy of approvals granted under FCA 1980 may kindly be provided for confirmation. 13 Jul 2020
4. ADS LetterReply to ADS dated 13.07.2020 14 Jul 2020
5. ADS LetterSub: Drilling of development wells (KSDA and KSDB) and conversion of exploratory wells (KSAB and KSAG) to development wells at Kasomarigaon, Assam Asset at Kasomarigaon, Assam by M/s Oil and Natural Gas Corporation Limited –Minutes of Meeting-reg This has reference to the minutes of meeting held on 16th October, 2020 (Friday) at 03.00 PM through video conferencing (VC) to discuss the above mentioned project submitted by M/s Oil and Natural Gas Corporation Ltd (ONGC) for environmental clearance, under the Chairmanship of Secretary (EF&CC). 2. As per the decision taken in the minutes of the meeting, M/s ONGC has requested for grant of environmental clearance to the well KSAB having forest clearance and proposed to drop drilling at location KSAG. It was also noted that, drilling of wells KSDA & KSDB horizontally from KSAC shall be considered after submission of report constituted by MoPNG to clarify the possibility of adopting new technologies such as Extended Reach Drilling (ERD)/ Horizontal Directional Drilling (HDD) with surface facilities including drilling rigs etc. in which ONGC representative is also a member. 3. In this regard, M/s ONGC is requested to submit the request to the Ministry regarding dropping of drilling at location KSAG. Further, it is also requested to provide details of proposal submitted, if any, with the Regional Office of the Ministry at Shillong for modification in forest clearance of well KSAC/ proof of application for Stage I FC for KSDA & KSDB wells. It is requested that the information may be provided immediately for taking further action into the matter. 13 Nov 2020
6.NAAs per the decision taken , M/s ONGC has requested for grant of environmental clearance to the well KSAB having forest clearance and proposed to drop drilling at location KSAG. It was also noted that, drilling of wells KSDA & KSDB horizontally from KSAC shall be considered after submission of report constituted by MoPNG to clarify the possibility of adopting new technologies such as Extended Reach Drilling (ERD)/ Horizontal Directional Drilling (HDD) with surface facilities including drilling rigs etc. in which ONGC representative is also a member. In this regard, M/s ONGC is requested to submit the request to the Ministry regarding dropping of drilling at location KSAG. Further, it is also requested to provide details of proposal submitted, if any, with the Regional Office of the Ministry at Shillong for modification in forest clearance of well KSAC/ proof of application for Stage I FC for KSDA & KSDB wells. It is requested that the information may be provided immediately for taking further action into the matter. 13 Nov 2020
7. ADS LetterAs per the decision taken , M/s ONGC has requested for grant of environmental clearance to the well KSAB having forest clearance and proposed to drop drilling at location KSAG. It was also noted that, drilling of wells KSDA & KSDB horizontally from KSAC shall be considered after submission of report constituted by MoPNG to clarify the possibility of adopting new technologies such as Extended Reach Drilling (ERD)/ Horizontal Directional Drilling (HDD) with surface facilities including drilling rigs etc. in which ONGC representative is also a member. In this regard, M/s ONGC is requested to submit the request to the Ministry regarding dropping of drilling at location KSAG. Further, it is also requested to provide details of proposal submitted, if any, with the Regional Office of the Ministry at Shillong for modification in forest clearance of well KSAC/ proof of application for Stage I FC for KSDA & KSDB wells. It is requested that the information may be provided immediately for taking further action into the matter. 13 Nov 2020
8. ADS LetterIt is requested that the information may be provided immediately for taking further action into the matter. 13 Nov 2020
9. ADS LetterReply to ADS Kasomarigaon project-18 November 2020 18 Nov 2020
4. Accredited Consultant Details
   i. Accreditation status : Yes    ii. Accreditation No. : NABET/EIA/1013/43 9 Oct 2010    iii. Name of Consultant: Senes Consultants India Ltd   iv. Address : Stesalit Towers, 6th Floot, GP Block, Sector-5 Salt Lake, Kolkotta-700091   v. Mobile No.: 9830094463   vi. Landline No.: 3323578070   vii. Email Id: sharma_js@ongc.co.in
5. Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
   i. Name of Applicant : Ravi    ii. Designation : ChiefGeneralManager    iii. Name of Company(Applicant Name should not be given here) : Oil And natural Gas Corporation    iv. Address : Corporate HSE, 8th Floor Core IV, SCOPE Minar, Delhi 10092 v. Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency: NIL