Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) MEWASA BAUXITE MINE
(b)Name of the Company / Organisation SAURASHTRA CALCINE BAUXITE AND ALLIED INDUSTRIES
(c)Registered Address NIL
(d)Legal Status of the Company NIL
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant D K Raichura ji
(b)Designation (Owner/ Partner/ CEO) Partner
(c)Address NIL
(d)Pin code 361315
(e)E-mail scabal@scabalindia.com
(f)STD Code. 2891(f)Telephone No. 233199
(g)Fax No. 233155
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity1(a) Mining of minerals
Minor Activity
(b)Category A
(c)Proposal Number IA/GJ/MIN/18422/2013
(d)Master Proposal Number(Single Window) SW/110964/2019
(e)EAC concerned (for category A Projects only) Non-Coal Mining
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. 138
(b)Pincode 361320
(c)Bounded Latitudes (North)
From
Degree 221352.488
Minutes
Second
From
Degree 221405.793
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 691851.398
Minutes
Second
From
Degree 691902.575
Minutes
Second
(e)Survey of India Topo Sheet No. 41F/3
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 42
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 0
(j)Seismic Zone 4
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Gujarat
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number J-11015/115/2013.IA.II(M)
(b)Date of Apply of TOR 17 Apr 2013
(c)Date of Issue of TOR / Standard ToR 31 Aug 2015
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :27 May 2018
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :30 Jun 2018
Distance of Public Hearing Venue from the Proposed Project :0
At Mine Site, Survey No.:- 138, Village – Mewasa, Taluka – Kalyanpur, District – Devbhoomi Dwaraka (Gujarat)
State :Gujarat
District :Devbhumi Dwarka
Tehsil :Kalyanpur
Village :Mewasa
41Employment is the major issue raised in public hearing.OthersAdditional District Magistrate
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Jack hammer (RH 658/ 42)32mm2 Nos.
(2.)Water tanker4000 L1 nos
(3.)Dewatering Pump10 HP1 Nos
(4.)Compressor450 CFM, 100 PSV1 nos
(5.)Tippers35 HP2 Nos.
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)36000 TPA of ROM/ 9.66 Ha.36000Tons per AnnumRoad
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? Obtained
(ii)Copies of all Consent to operate obtained since inception Copy of Consent to Operate
(iii)Date of Issue 21 Jun 2011
(iv)Valid Upto 27 Jan 2015
(v)File No. PC/CCA-JMN-311(2)/ID_17099/84555
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 0.75
(b) Funds Allocated for Environment Management (Capital) (in Crores) 0.1907
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.05
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.003
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? Yes
a)Protected areas notified under the wildlife (Protection) Act, 1972 Yes
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 0
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 0
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Diesel10.59Tons per AnnumNearby PumpRoad1 OthersNACopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Oct 2015 To 31 Dec 2015
(b)Season Post-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 6
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube118.5069.30113.93100
(2.)NOxMicro Gram per Meter Cube32.3013.2031.9880
(3.)SO2Micro Gram per Meter Cube21.5011.021.0480
(4.)OthersCOMicro Gram per Meter Cube143029014002000
(5.)PM2.5Micro Gram per Meter Cube62.3032.3061.7560
    14.2.     No. of Ground Water monitoring locations : 2
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)TDSmg/l371231885002000
(2.)Chloridesmg/l143313202501000
(3.)pHNA7.907.706.58.5
(4.)TSSmg/l0000
(5.)Total Hardnessmg/l12511193200600
(6.)Fluoridemg/l21.8011.5
(7.)Heavy MetalsCadmiummg/l0.01010.00170.0030
    14.3.     No. of Surface Water monitoring locations : 6
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)DOmg/l6.75.4C
(2.)CODmg/l9820C
(3.)BODmg/l304C
(4.)pHNA8.407.65C
    14.4.     No. of Ambient Noise monitoring locations : 6
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))45.84045
(2.)Leq(Day)A-weighted decibels(dB(A))64.149.855
    14.5.     No. of Soil Sample Monitored locations : 4
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)K(Potassium)Milligram per Kilogram14362
(2.)pH8.361.62
(3.)P(Phosphorus)Milligram per Kilogram2.120.23
(4.)Electric ConductivityMillisiemens per Centimetre52307.81
(5.)N(Nitrogen)Milligram per Kilogram147.536.0
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 22 To 22
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 28 To 28
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersWater Tanker6.51.0Copy of Permission LettermodeOthersRoadOthersWater TankerNA10 Jul 20196.5
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic1.52Septic tank followed by soak pitOthersSeptic tank followed by soak pit0.51.0
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 1.5
(b)Total Discharged Water (Kilolitre per Day) 1
(c)Total Reused Water (Kilolitre per Day) 0.5
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Municipal Solid WasteMunicipal Solid Waste2.7Tons75RoadAuthorized Recyclers
(2.)Mine WasteOthersMine Waste1800Tons0RoadOthersBackfilling
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube114.609.8124.6100
(2.)NOxMicrogram per Meter Cube26.700.00426.7180
(3.)PM2.5Microgram per Meter Cube62.304.566.960
(4.)SO2Microgram per Meter Cube00010
(5.)Others(Specify)COMicrogram per Meter Cube143000.0021430.0032000
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)NA000PM100
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 0
(b)Source NA
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 0
(e)Stack Height (in m) 0
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 9.66
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 9.66
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 9.66
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 0
(e)Settlements (ha.) 0
(f)Industrial (ha.) 0
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : Private Agriculture Land 0
    Total (ha.) 9.66
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Water Reservoir8.3655Water Reservoir
(2.)Green belt0.200Plantation
(3.)Built Up Area0.0100Used for plantation
(4.)OthersUndisturbed area1.0845Plantation
Total (ha.) 9.66
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)WLSNA0NA
(2.)NPAMarine National Park3.34Towards NE
(3.)Wildlife CorridorsNA0NA
(4.)ESAsNA0NA
(5.)Critically Polluted AreaNA0NA
(6.)ESZsNA0NA
(7.)CorridorsNA0NA
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Defence InstallationsNA0NA
(2.)ForestR.F.5.10Towards NE
(3.)Archaeological SitesNA0NA
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? Selec
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) Not Applicable
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 9.66
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired NA
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? Yes
(i)Details of Schedule-I Species Pea-fowl
(b)Whether conservation plan for Schedule-I Species has been prepared ? Yes
(i)Uploaded copy of conservation plan Copy of conservation plan
(ii)Fund Provision made 5.0 Lacs
(iii)Period of Implementation Life of Mine
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Rani Nadi
(ii)Direction of Water Bodies in Buffer Area South West
(iii)Distance of Water Bodies in Buffer Area 3.73
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 40
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 20
(e)No. of working days 300
(f)Total Manpower 60
32.
Green Belt in Ha:
(a)Total Area of Green Belt 1.2945
(b)Percentage of Total Project Area 13.40
(c)No. of Plants to be Planted 1294
(d)Funds Allocated for Plantation 6.47
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)EnvironmentalA total of 1294 plants will be planted till the life of mine.
(2.)SocialEmployment to 60 people will be provided.
(3.)FinancialState Govt. will get revenue in form of royalty and taxes.
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For Non-Coal Mining
S. No.Item Details
     1.       No. of Mineral(s) to be Mined : 1
S. No.Mineral(s) to be Mined Major or Minor Mineral
(1.)BauxiteMajor
2.
Mine Capacity in ROM (Run of Mine) 36000
3.
Uploaded 500 meters Cluster Certificate from State Mines and Geology in case of minor minerals Copy of 500 meters Cluster Certificate from State Mines and Geology
4.
Mining Plan:
(a)Approval Letter No. 682 (23) (MS – 630)/2007
(b)Date of Approval 22 Jan 2016
(c)Approved Letter Copy of Approved Letter
(d)Approved By State Mining and Geology Department IBM
(e)Approved Mining Lease Area 9.66
(f)Approved Capacity 36000
5.
Technical Details:
(a)Total Geological Reserves (Million Ton) 0.095582
(b)Mineable Reserves (Million Ton) 0.412759
(c)Extractable Reserves(Million Ton) 0.412759
(d)Percent(%) of Extraction 100
(e)Grade of Coal /Ore /Mineral Al2O3-45% High Grade; A12O3-35% Low Grade
(f)Stripping Ratio 0.020 : 1
(g)Category of Gaseousness (Only for Coal Mining, Others may Write NA) NA
(h)Average Gradient(Degree) 0
(i)Mining Method Opencast
(j)Life of Mine (Years) 12
6.
Details of Beneficiations:
(a)Whether it is proposed to install beneficiation plant/Coal washery within the mining lease area No
(b)Whether it is proposed to install crusher within the mining lease area No
7.
Details of Seams:
(a)Whether details of seam applicable No
8.
Details of Mining Lease:
(a)Mining Lease Area (in Hectare) 9.66
(b)Whether obtained Letter of Intent (LOI) from the state government ? No
(i)Reason thereof It is a existing mine
(c)Whether Lease Deed Executed ? Yes
(i)Copy of Executed Lease deed valid as on Date Copy of Executed Lease deed
(ii)Provide area in Hectare as per executed lease deed (initial) document 9.66
(iii)Validity of the lease deed From : 03 Sep 1986 To : 02 Sep 2036
(iv)Date of Execution of Mining Lese 03 Sep 1986
(v)Reference Number MCR-1585 CHH-80550
(d)Whether Lease Deed Renewed ? No
(i)Reason thereof As per Amendment Act Dated 12.01.2015 Validity of
9.
OB (Over Burden) Management:
(a) Details of External Dumps:
(i)No. of OB Dumps 0
(ii)Total Area (in Hectare) 0
(iii)Height (in meter) 0
(iv)Quantity (in Million Cubic meter) 0
(v)No. of year back fill up 0
(b) Details of Internal Dumps:
(i)No. of Internal Dumps 1
(ii)Total Area (in Hectare) 8.3655
(iii)Height (in meter) 12
(iv)Quantity (in Million Cubic meter) 1.00386
10.
Details of Topsoil Management:
(a)Quantity of Topsoil excavated during the entire life of the mine (in Million Cubic metre) 0
(b)Quantity of Topsoil proposed for utilization for reclamation during the entire life of the mine (in Million Cubic metre) 0
(c)Quantity of Topsoil proposed for utilization for other activities during the entire life of the mine (in Million Cubic metre) 0
11.
Details of Final Mine Void:
(a)Area (in Hectare) 8.3655
(b)Depth (in meter) 12
(c)Volume (in Million Cubic meter) 1.00386
12.
Details of Quarry:
(a)Final Void of 8.3655 (hectare) at a Depth of 12 meter which is Proposed to be Converted into a Water Body.
(b)Total Quarry Area (ha) 9.66
13.
Details of Transportation:
(a)In Pit/Underground to Surface By Tippers
(b)Surface to Siding/Loading By Tippers
(c)Transportation / Conveyor Details By Road
     14.      Details of Land Usage (Pre-Mining)
S. No.LAND USE Other LAND USEWITHIN ML AREA (Hectare)OUTSIDE ML AREA (Hectare)TOTAL (Hectare)
(1.)AGRICULTURE LAND9.6609.66
(2.)FOREST LAND000
(3.)GRAZING LAND000
(4.)SETTLEMENTS000
(5.)SURFACE WATER BODIES000
(6.)WASTE LAND000
TOTAL9.6609.66
     15.      Details of Land Usage (Post-Mining)
S. No.LAND USE Other LAND USEPlantation (ha)Water Body (ha)Public Use (ha)Undisturbed (ha)Total
(1.)TOP SOIL STORAGE0000
(2.)INTERNAL OB DUMPS0000
(3.)VIRGIN AREA1.0845001.0845
(4.)EXCAVATION/QUARRY08.36508.365
(5.)EXTERNAL OB DUMPS0000
(6.)ROADS0000
(7.)BUILT UP AREA (COLONY/OFFICE)0.0100000.01
(8.)GREEN BELT0.200000.2
TOTAL1.29458.365009.6595
16.
Details of Reclamation:
Total Afforestation Plan shall be Implemented Covering of Mining.
This will Include:
(a)External OB Dump(in hectare) 0
(b)Internal Dump(in hectare) 0
(c)Quarry(in hectare) 9.66
(d)Safety Zone(in hectare) 0
(e)Final Void of 8.3655 (hectare) at a Depth of 12 meter which is Proposed to be Converted into a Water Body.
(f)Density of Tree Plantation per ha (in no.) 1000
(g)Others in ha (such as Excavation Area along ML Boundary, along Roads and Infrastructure, Embankment Area and in Township Located Outside the Lease etc) 0
(h)Total afforestation plant (in hectare) 1294
17.
Status of progressive Mining Closure Plan:
Details Not Applicable
     18.      Details of Actual Coal/ ORE Production vis-a-vis Sanctioned Capacity since the Inception:
S. No.Financial Year Sanctioned Capacity as per EC (MTPA)Sanctioned Capacity as per CTOSanctioned Capacity as per approved mining planActual Production Excess Production Beyond the EC / CTO/ Mining Plan Sanctioned Capacity (MTPA)
(1.)199000062670
(2.)1993000115260
(3.)1994000255720
(4.)1996000373420
(5.)1998000668200
(6.)1999000250740
(7.)2001000232820
(8.)2002036000094550
(9.)2003036000057180
(10.)20040360000102080
(11.)200703600032130359210
(12.)200803600032775358890
(13.)200903600033900104600
(14.)20100360003180032310
(15.)2011036000294984650
(16.)201203600030537123000
(17.)20140360003002400
(18.)20170360003234800
(19.)20180360003206300
(20.)198800060070
(21.)1992000232900
(22.)1995000228380
(23.)2000000270140
(24.)20050360000157280
(25.)20160360003214800
(26.)201303600030375196700
(27.)1991000269910
(28.)1997000617940
(29.)200603600035955334090
(30.)20150360003045600
(31.)1989000168520
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. 47
(ii)Name of the EIA Consultant Enkay Enviro Services Pvt. Ltd.
(iii)Address 92, Heera Nagar-A, Near Shalimar Bagh, Ajmer Road, Jaipur
(iv)Mobile No. 9314363996
(v)Landline No. 0141492077
(vi)Email Id info@enkayenviro.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Non-Coal Mining
(ix)Validity of Accreditation 14 Aug 2019
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAPP is requested to submit the following: Copy of action taken for violation made by the project proponent 2. Details of demand for the violation if any raised by Department of Mining and Geology. 3. Details of payment for the violation, if any made to Department of Mines & Geology 4. Status of mine whether working or not 5. Copy of approval letter of Conservation plan for Schedule I species 6. Status of the NBWL clearance 06 Sep 2019
2.NAThe correction have been made as per the instruction received 20 Sep 2019
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1.NA

Deferred

28 Mar 2023
2. ADS Reply LetterADS REPLY ENCLOSED WITH ANNEXURE 23 Feb 2023
3.NA

deferred the proposal

20 Nov 2019
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantD K Raichura ji
DesignationPartner
Name of Company (Applicant Name should not be given here)SAURASHTRA CALCINE BAUXITE AND ALLIED INDUSTRIES
AddressHarshad Road, P.O. - Bhatia Taluka - Kalyanpur