Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) M/s Maihar Cement (A Division of Century Textile & Industries Limited) Increase in clinker production from 3 million TPA to 4 million TPA and cement production from 5 million TPA to 6 million TPA thro
(b)Name of the Company / Organisation MAIHAR CEMENT (CENTURY TEXTILES & INDUSTRIES LTD)
(c)Registered Address Post Sarla Nagar,,Satna,Madhya Pradesh-485772
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Sajay Joshi
(b)Designation (Owner/ Partner/ CEO) President
(c)Address Post Sarla Nagar,,Tehsil- Maihar Dist Satna,Maihar,Satna,Madhya Pradesh-485772
(d)Pin code 485772
(e)E-mail sailesh.pandey@adityabirla.com
(f)STD Code. 0(f)Telephone No. 277067
(g)Fax No. 2772836
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity3(b) Cement plants
Minor Activity
(b)Category A
(c)Proposal Number IA/MP/IND/73253/2018
(d)Master Proposal Number(Single Window) SW/110793/2019
(e)EAC concerned (for category A Projects only) Industrial Projects - 1
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. 2142
(b)Pincode 485772
(c)Bounded Latitudes (North)
From
Degree 24.19143611
Minutes
Second
From
Degree 24.20822222
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 80.78972222
Minutes
Second
From
Degree 80.80805556
Minutes
Second
(e)Survey of India Topo Sheet No. 63D16
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 441
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 0.50
(j)Seismic Zone 2
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Madhya Pradesh
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)Madhya PradeshSatnaMaihar
(2.)Madhya PradeshSatnaMaiharSarlanagar
(3.)MaharashtraSolapurMoholChincholi
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number IA-J-11011/113/2018-IA-II(I)
(b)Date of Apply of TOR 28 Feb 2018
(c)Date of Issue of TOR / Standard ToR 19 Apr 2018
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :06 Feb 2019
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :08 Mar 2019
Distance of Public Hearing Venue from the Proposed Project :0.10
Aganwadi Center, Chopra no. 1
State :Madhya Pradesh
District :Satna
Tehsil :Maihar
Village :Chopra no. 1, Post Sarla Nagar
71S.N. Name & Address (Shri) Issues raised Comments of the applicant 1 Kailash Dwivedi, Village- Sonwari, Tehsil- Maihar Dist Satna (MP) The unemployment problem has been reduced from the inceptioDistrict Collector
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Cement5MTPA to 6MTPA
(2.)Clinker3MTPA to 4MTPA
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Cement6000000Tons per AnnumRoad,Rail
(2.)Clinker4000000Tons per AnnumConveyor Belt
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 05 Nov 2018
(iv)Valid Upto 30 Sep 2019
(v)File No. 87523
(vi)Application No. 13057
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 80
(b) Funds Allocated for Environment Management (Capital) (in Crores) 11.34
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.8
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 6
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 940380000
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 940380000
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Fly ash2040000Tons per Annumcaptive and purchaseRail4 CaptiveCopy of Linkage
(2.)Coal632000Tons per AnnumLinkage/ e-auction/ purchaseRoad,Rail250 LinkageCopy of Linkage
(3.)Pet coke as fuel for lime kiln395000Tons per AnnumLinkage/ e-auction/ purchaseRoad,Rail500 LinkageCopy of Linkage
(4.)Bauxite592000Tons per AnnumpurchaseConveyor Belt100 Open MarketCopy of Linkage
(5.)GYPSUM180000Tons per AnnumpurchaseRail250 Open MarketCopy of Linkage
(6.)LATERITE177600Tons per Annumcaptive and purchaseRoad,Conveyor Belt8 CaptiveCopy of Linkage
(7.)Limestone5920000Tons per Annumcaptive and purchaseRoad,Conveyor Belt8 CaptiveCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Mar 2018 To 31 May 2018
(b)Season Pre-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM2.5Micro Gram per Meter Cube30.0516.6629.9060
(2.)OthersCOMili Gram per Meter Cube1114
(3.)SO2Micro Gram per Meter Cube6.976.06.6980
(4.)NOxMicro Gram per Meter Cube25.488.025.4280
(5.)PM10Micro Gram per Meter Cube77.0942.2471.94100
    14.2.     No. of Ground Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)TDSmg/l681845002000
(2.)Fluoridemg/l1.000.1011.5
(3.)pHNA8.286.376.58.5
(4.)TSSmg/l708100100
(5.)Total Hardnessmg/l45276300600
(6.)Chloridesmg/l127.965.992501000
(7.)Heavy MetalsFemg/l0.050.050.31.00
(8.)OthersNO3mg/l23.875.2745100
    14.3.     No. of Surface Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)CODmg/l704C
(2.)pHNA8.347.06C
(3.)BODmg/l72C
(4.)OthersFemg/l0.050.05C
(5.)DOmg/l5.304.20C
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))54.3432.8445
(2.)Leq(Day)A-weighted decibels(dB(A))76.5453.7155
    14.5.     No. of Soil Sample Monitored locations : 5
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pH7.827.20
(2.)N(Nitrogen)Kilogram per hectare294.7875.26
(3.)P(Phosphorus)Kilogram per hectare61.0719.20
(4.)K(Potassium)Kilogram per hectare356.83144.25
(5.)Electric ConductivityMillisiemens per Centimetre0.1420.042
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 18.0 To 8.70
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 1.50 To 17.4
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersMine pit and water reservoir32256 Not Appliacble PipelineOtherspumping through pipeline254227 Jan 20093225
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)DM Water1010Neutralisation tankReuse within the Plant & Recycling10
(2.)domestic (Plant Colony)385800STPReuse within the Plant & Recycling,Green Belt Renewal Plant,OthersDust suppression30877
(3.)Cooling Tower505neturlisationReuse within the Plant & Recycling5
(4.)domestic (Mine Colony)60150STPGreen Belt Renewal Plant,OthersDust Suppression4812
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 460
(b)Total Discharged Water (Kilolitre per Day) 89
(c)Total Reused Water (Kilolitre per Day) 371
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)metal scrapIndustrial Waste80Tons250RoadAuthorized Recyclers
(2.)Used oilHazardous Waste (as per Hazardous and Other Waste Management rules 2016)27.74Kilolitre500RoadAuthorized Recyclers
(3.)Lead Acid BatteriesHazardous Waste (as per Hazardous and Other Waste Management rules 2016)159Tons500RoadAuthorized Recyclers
(4.)Ruuber Belt ScrapOthersrubber80Tons0Otherscaptive useCo-Processing
(5.)STP sludgeOthersSTP0.66Tons0Otherscaptive useOthersUsed as Manure and used for Plantatio
(6.)Transformer OilHazardous Waste (as per Hazardous and Other Waste Management rules 2016)4Kilolitre500RoadAuthorized Recyclers
(7.)Fly ashFly Ash74250Tons0Conveyor BeltOthersused for manufacturing of PPC
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM2.5Microgram per Meter Cube27.360.500.8528.3260
(2.)SO2Microgram per Meter Cube6.380.502.008.3880
(3.)NOxMicrogram per Meter Cube9.700.503.0012.7180
(4.)PM10Microgram per Meter Cube67.760.500.8568.81100
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)Kiln no. 3coal1024.6PM101.68
(2.)Coal Mill No. 4coal401.8PM100.82
(3.)Clinker Cooler No.1-402.0PM100.43
(4.)Clinker Coller no.2-402PM100.43
(5.)Cement Mill no. 1 & 2-401.5PM100.26
(6.)Cement Mill No. 3-401.8PM100.27
(7.)Cement Mill No. 4 & 5-311.3PM100.26
(8.)Thermal power Plant No. 1Coal702.5PM101.70
(9.)Thermal Power Plant -2coal722.5PM100.59
(10.)Clinker Cooler no. 3-504.8PM102.20
(11.)Kiln No. 1Coal803.9PM102.39
(12.)Coal Mill No; 5coal601.8PM100.31
(13.)Kiln No. 2Coal803.9PM103.41
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 401380
(b)Source Captive Power Plant of 31.4MW and MPSEB
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) captive Power Plant of 31.4MW
(e)Stack Height (in m) 72
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0.0
(b)Private Land (ha.) 0.0
(c)Government Land (ha.) 199.023
(d)Revenue Land (ha.) 0.0
(e)Other Land (ha.) 0.0
    Total Land (ha.) 199.023
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 18850
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 157.79
(d)Surface Water Bodies (ha.) 1212.58
(e)Settlements (ha.) 1981.00
(f)Industrial (ha.) 677
(g)Forest (ha.) 10205.00
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : Road, Railway line, plantation 252.97
    Total (ha.) 33336.340000000004
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Main Plant20.2343
(2.)Township30.3514
(3.)Green belt65.2982exiting 60.2982ha and proposed 5.0ha
(4.)Built Up Area53.0138Cement plant area
(5.)OthersOpen Area30.1251Open Area
Total (ha.) 199.0228
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaNA100none within 10km radius
(2.)CorridorsNA70none within 10km radius
(3.)Wildlife CorridorsNA70none within 10km radius
(4.)ESAsNA100none within 10km radius
(5.)NPANA70none within 10km radius
(6.)ESZsNA70none within 10km radius
(7.)WLSNA100none within 10km radius
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestPF0adjacent
(2.)Archaeological SitesNA15NONE WITHIN 10KM RADIUS
(3.)Defence InstallationsNA200NONE WITHIN 10KM RADIUS
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 199.023
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired running plant
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? Yes
(i)Details of Schedule-I Species Barking Deer, the Peacock, Chital, Sambhar, Jungle Cat, Hyena, Fox and Porcupine alongwith the Vultures and the Indian Python
(b)Whether conservation plan for Schedule-I Species has been prepared ? Yes
(i)Uploaded copy of conservation plan Copy of conservation plan
(ii)Fund Provision made 258.40lakh
(iii)Period of Implementation 10year
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Tamas River
(ii)Direction of Water Bodies in Buffer Area North West
(iii)Distance of Water Bodies in Buffer Area 0.50
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 0
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 25
(e)No. of working days 330
(f)Total Manpower 25
32.
Green Belt in Ha:
(a)Total Area of Green Belt 65.2982
(b)Percentage of Total Project Area 32.81
(c)No. of Plants to be Planted 10000
(d)Funds Allocated for Plantation 15
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)EnvironmentalGreen belt has already been developed within the existing operational premises & mines with 10,78,000 number of trees. Total area (within plan and colony) covered under plantation is about 149 acres (60 hact) with 8,23,000 number of trees. The green belt is consisting of local species would be preferred. Further development of green belt over 5 hectare of area is also proposed around the plant periphery and open space
(2.)SocialIn line with the OM of MoEFCC dated 1st May 2018, following additional provision has been proposed towards the CER which is altogether does not include the cost of implementation of EMP, conservation plan, etc. The existing cost being incurred pertaining to CER aspect shall continue as per requirement. Total Cost of proposed Project : 80 Crores CSR Budget @ 1 % : 0.80 Crores This amount Rs 80 lacs per year will be spent over a period of 2years (@ Rs 40 Lacs per Year) in addition to the
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 1
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1619/RA-0071
(ii)Name of the EIA Consultant Creative Enviro Services
(iii)Address SR-4, Shrirm Kunj, Bharat Nagar, Shahpura, Bhopal
(iv)Mobile No. 9425009319
(v)Landline No. 0755429931
(vi)Email Id creative.bpl@rediffmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 1
(ix)Validity of Accreditation 23 Oct 2019
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
      Essential Detail Sought : NIL
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantSajay Joshi
DesignationPresident
Name of Company (Applicant Name should not be given here)MAIHAR CEMENT (CENTURY TEXTILES & INDUSTRIES LTD)
AddressPost Sarla Nagar