Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Proposed Expansion of Writing & Printing Paper Plant (200 to 400 TPD) and Co-generation Power Plant (12 MW to 30 MW) At Village Rampura, Tehsil Sadar (Shahjahanpur), District Shahjahanpur (Uttar Prade
(b)Name of the Company / Organisation KR PULP & PAPERS LIMITED
(c)Registered Address 304, Roots Tower, District Centre, Laxmi Nagar, New Delhi,,New Delhi,Delhi-110092
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Jitendra Prakash Gupta
(b)Designation (Owner/ Partner/ CEO) SrVP
(c)Address KR Pulp and Papers Limited, Jalalabad Road, Shahjahanpur, UP,,Shahjahanpur,Shahjahanpur,Uttar Pradesh-242001
(d)Pin code 242001
(e)E-mail jp.gupta@krpapers.com
(f)STD Code. 11(f)Telephone No. 240135
(g)Fax No. 42448977
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity5(i) Pulp & paper industry excluding manufacturing of paper from waste
Minor Activity
(b)Category A
(c)Proposal Number IA/UP/IND/2366/2008
(d)Master Proposal Number(Single Window) SW/110339/2019
(e)EAC concerned (for category A Projects only) Industrial Projects - 1
(f)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. 156,168,169,163,174,167,166,164,165,173,170,155,14
(b)Pincode 242001
(c)Bounded Latitudes (North)
From
Degree 27.83861111
Minutes
Second
From
Degree 27.84472222
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 79.84861111
Minutes
Second
From
Degree 79.85694444
Minutes
Second
(e)Survey of India Topo Sheet No. 54M13 and 54M9
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 150
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 3.7
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Uttar Pradesh
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number J-11011/1132/2007.-IA.II(I)
(c)Date of Issue of TOR
(f)Previous TOR Letter NA
(b)Date of Apply of EC 24 Dec 2008
(c)Date of Issue of EC 12 Feb 2009
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :13 Apr 2019
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :15 May 2019
Distance of Public Hearing Venue from the Proposed Project :0
At plant site i.e. Village Rampura, Tehsil Sadar, District Shahjahanpur (Uttar Pradesh)
State :Uttar Pradesh
District :Shahjahanpur
Tehsil :Shahjahanpur
Village :Rampura
60CSR activities, air and water pollution, mitigation measures and monitoring, powerOthersAdditional District Magistrate
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Lucknow
(iii)Letter No. IV/ENV/UP/Ind-120/305/2009/668 dated 05.03.19
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit Feb 13 2019 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Writing and printing paper200200400OthersTons per day (TPD)Road
(2.)Power121830Mega Watt(MW)OthersCables
(3.)Conventional CRP with lime kiln0700700OthersTons per dayOtherspipelines
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)Co-generation power plant121830MW
(2.)Writing and printing paper plant200200400TPD
(3.)Conventional CRP with lime kiln0700700TPD
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 11 Apr 2019
(iv)Valid Upto 31 Dec 2020
(v)File No. CTO Air-38652/UPPCB/Bareilly(UPPCBRO)/CTO/air/SHAH
(vi)Application No. CTO Air-38652/UPPCB/Bareilly(UPPCBRO)/CTO/air/SHAH
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 460.25
(b) Funds Allocated for Environment Management (Capital) (in Crores) 21.03
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 3.7
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 4.35
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 256740
(b)Existing quantity of raw material/fuel 258720
(c)Total quantity of raw material/fuel 515460
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Bagasse, wheat straw, mixed hard wood515460Tons per AnnumNearby Sugar Mill/Farmers and plywood industriesRoad130 OthersMoU and Purchase orderCopy of Linkage
(2.)Sodium Chlorate2174.7Tons per AnnumOpen marketsRoad1000 Open MarketCopy of Linkage
(3.)Hydrogen Peroxide1481.7Tons per AnnumOpen marketsRoad1000 Open MarketCopy of Linkage
(4.)Starch792Tons per AnnumOpen marketsRoad800 Open MarketCopy of Linkage
(5.)Pet coke as fuel for lime kiln14850Tons per AnnumNearby refineriesRoad300 OthersNearby refineriesCopy of Linkage
(6.)caustic53130Tons per Annum95% from CRP through pipeline and 5% from MarketRoad,OthersPipeline400 Open MarketCopy of Linkage
(7.)Rice Husk and Bagasse Pith141900Tons per AnnumOpen marketsRoad100 OthersPurchase orderCopy of Linkage
(8.)Alkyletene dimer1584Tons per AnnumOpen marketsRoad300 Open MarketCopy of Linkage
(9.)PCC/GCC24750Tons per AnnumIn house/marketRoad500 Open MarketCopy of Linkage
(10.)Coal217800Tons per AnnumOpen marketsRoad1000 OthersPurchase orderCopy of Linkage
(11.)Oxygen1980Tons per AnnumIn houseOthersPipeline0 OthersIn house by pipelineCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Oct 2018 To 31 Dec 2018
(b)Season Post-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube94.662.493.91100
(2.)SO2Micro Gram per Meter Cube20.66.319.9780
(3.)NOxMicro Gram per Meter Cube41.415.839.2180
(4.)PM2.5Micro Gram per Meter Cube54.538.953.9360
    14.2.     No. of Ground Water monitoring locations : 9
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)TSSmg/l0000
(2.)TDSmg/l5892285002000
(3.)pHNA7.927.196.58.5
(4.)Total Hardnessmg/l361.35133.65200600
(5.)Chloridesmg/l61.6410.852501000
(6.)Fluoridemg/l0.850.261.01.5
    14.3.     No. of Surface Water monitoring locations : 3
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA7.897.73E
(2.)DOmg/l6.43.6E
(3.)CODmg/l126.97.9E
(4.)BODmg/l26.42.3E
    14.4.     No. of Ambient Noise monitoring locations : 9
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))73.952.8Industrial- 75 Residential -55
(2.)Leq(Night)A-weighted decibels(dB(A))67.442.8Industrial - 70 Residential -45
    14.5.     No. of Soil Sample Monitored locations : 6
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pH8.067.16
(2.)N(Nitrogen)Kilogram per hectare258.92137.85
(3.)Electric ConductivityMillisiemens per Centimetre0.670.21
(4.)P(Phosphorus)Kilogram per hectare117.5850.38
(5.)K(Potassium)Kilogram per hectare155.0342.21
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 2.6 To 9.17
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 0.82 To 8.95
(c)Whether Ground Water Intersection will be there ? NA
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater165600Copy of Permission LetterPipelineTube WellCGWA/NOC/IND/REN/2/2019/556218 Jun 201916560
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Industrial Process1300013000Effluent Treatment PlantOthersIrrigation013000
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 13000
(b)Total Discharged Water (Kilolitre per Day) 13000
(c)Total Reused Water (Kilolitre per Day) 0
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)AshFly Ash65340Tons0OthersGiven to farmers as manure and brick manufacturingOthersGiven to farmers as manure and brick manufacturing
(2.)ETP sludgeIndustrial Waste5280Tons0OthersBurnt in boiler as fuelOthersDried and burnt in boiler as fuel
(3.)Lime sludgeIndustrial Waste76560Tons0OthersBurnt in lime kilnOthersBurnt in lime kiln
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)SO2Microgram per Meter Cube16.61018.6980
(2.)PM10Microgram per Meter Cube84.41085.85100
(3.)NOxMicrogram per Meter Cube30.31033.6580
(4.)PM2.5Microgram per Meter Cube52.61053.0660
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)Proposed 60 TPH BoilerCoal722.0PM1030
(2.)90 TPH recovery boilerBlack liquor702.8PM10100
(3.)Existing 80 TPH boilerRice husk/coal with pith and sludge652.8PM10100
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 26250
(b)Source Existing 12 MW CPP and proposed 18 MW CPP (Co-gen
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 0
(e)Stack Height (in m) 0
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 0
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 24
    Total Land (ha.) 24
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 24585.07
(b)Waste/Barren Land (ha.) 2313.86
(c)Grazing/ Community Land (ha.) 1221.54
(d)Surface Water Bodies (ha.) 895.73
(e)Settlements (ha.) 2859.53
(f)Industrial (ha.) 893.38
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : No other land 0
    Total (ha.) 32769.11
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Main Plant5.81Machinery, utilities and storage area
(2.)Green belt7.9
(3.)OthersAdmin/excise office,road/ paved area and open area10.29Admin/excise office,road/ paved area and open area
Total (ha.) 24
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaNot applicable0No CPA within 10 km radius
(2.)ESAsNot applicable0No ESAs within 10 km radius
(3.)ESZsNot applicable0No ESZs within 10 km radius
(4.)Wildlife CorridorsNot applicable0No Wildlife Corridors within 10 km radius
(5.)NPANot applicable0No NPA within 10 km radius
(6.)WLSNot applicable0No WLS within 10 km radius
(7.)CorridorsNot applicable0No Corridors within 10 km radius
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestNot applicable0No Forest within 10 km radius
(2.)Archaeological SitesNot applicable0No archaeological sites in 10 km radius
(3.)Defence InstallationsNot applicable0No defence installations in 10 km radius
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 24
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired Already acquired
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Deoha or Garra River
(ii)Direction of Water Bodies in Buffer Area South East
(iii)Distance of Water Bodies in Buffer Area 3.7
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 10
(b)Permanent Employment-During Operation 361
(c)Temporary Employment- During Construction 600
(d)Temporary Employment- During Operation 180
(e)No. of working days 330
(f)Total Manpower 1151
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt7.907.9
(2.)Percentage of Total Project Area33033
(3.)No. of Plants10048180011848
(4.)Funds Allocated10000000500000015000000
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)EnvironmentalUtilization of agricultural waste as raw material and fuel
(2.)SocialEmployment generation and CER activities
(3.)FinancialImproved livelihood with increased business opportunities
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 1
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1619/RA 0069
(ii)Name of the EIA Consultant J.M. EnviroNet Pvt. Ltd.
(iii)Address JM EnviroNet Pvt. Ltd., 202A, ABW Tower, Near Iffco Chowk, Sector 25, Gurugram (Haryana)
(iv)Mobile No. 9015209362
(v)Landline No. 9015209362
(vi)Email Id jmenviron@hotmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 1
(ix)Validity of Accreditation 07 Feb 2020
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File NA
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
      Essential Detail Sought : NIL
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1. ADS Reply LetterWe request your good self to kindly consider our proposal for EC proceedings. 03 Oct 2019
2.NAProposal deferred for want of additional information 16 Aug 2019
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantJitendra Prakash Gupta
DesignationSrVP
Name of Company (Applicant Name should not be given here)KR PULP & PAPERS LIMITED
Address304, Roots Tower, District Centre, Laxmi Nagar, New Delhi