1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | Proposed Expansion of Writing & Printing Paper Plant (200 to 400 TPD) and Co-generation Power Plant (12 MW to 30 MW) At Village Rampura, Tehsil Sadar (Shahjahanpur), District Shahjahanpur (Uttar Prade | (b)Name of the Company / Organisation | KR PULP & PAPERS LIMITED | (c)Registered Address | 304, Roots Tower, District Centre, Laxmi Nagar, New Delhi,,New Delhi,Delhi-110092 | (d)Legal Status of the Company | Private | (e)Joint Venture | No | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | Jitendra Prakash Gupta | (b)Designation (Owner/ Partner/ CEO) | SrVP | (c)Address | KR Pulp and Papers Limited, Jalalabad Road, Shahjahanpur, UP,,Shahjahanpur,Shahjahanpur,Uttar Pradesh-242001 | (d)Pin code | 242001 | (e)E-mail | jp.gupta@krpapers.com | (f)STD Code. | 11(f)Telephone No. | 240135 | (g)Fax No. | 42448977 | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a.I)Project/Activity | 5(i) Pulp & paper industry excluding manufacturing of paper from waste
| Minor Activity | | (b)Category | A | (c)Proposal Number | IA/UP/IND/2366/2008 | (d)Master Proposal Number(Single Window) | SW/110339/2019 | (e)EAC concerned (for category A Projects only) | Industrial Projects - 1 | (f)Project Type | Expansion |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | 156,168,169,163,174,167,166,164,165,173,170,155,14 | (b)Pincode | 242001 | (c)Bounded Latitudes (North) | | From | | Degree | 27.83861111 | Minutes | | Second | | From | | Degree | 27.84472222 | Minutes | | Second | | (d)Bounded Longitudes (East) | | From | | Degree | 79.84861111 | Minutes | | Second | | From | | Degree | 79.85694444 | Minutes | | Second | | (e)Survey of India Topo Sheet No. | 54M13 and 54M9 | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 150 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 3.7 | (j)Seismic Zone | 3 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Uttar Pradesh | |
|
|
Details of State of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
NIL | |
|
6. | Details of Terms of Reference (ToR)/EC: | (a)MoEF&CC / SEIAA File Number | J-11011/1132/2007.-IA.II(I) | (c)Date of Issue of TOR | | (f)Previous TOR Letter | NA | (b)Date of Apply of EC | 24 Dec 2008 | (c)Date of Issue of EC | 12 Feb 2009 | (d)Previous EC Letter | Copy of Previous EC letter | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | No | (b)Whether details of Public Hearing available? | Yes | (c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above | Yes | |
|
7.1. Details of Public Hearing |
---|
|
S. No. | Details of Advertisement | Details of Public Hearing | Venue | Location Details | No. of People Attended | Issues Raised | Designation of Presiding Officer | Other Designation of Presiding Officer |
---|
(1.) | | Copy of Public Hearing : | Copy of Public Hearing | Date : | 15 May 2019 | Distance of Public Hearing Venue from the Proposed Project : | 0 |
| At plant site i.e. Village Rampura, Tehsil Sadar, District Shahjahanpur (Uttar Pradesh) | State : | Uttar Pradesh | District : | Shahjahanpur | Tehsil : | Shahjahanpur | Village : | Rampura |
| 60 | CSR activities, air and water pollution, mitigation measures and monitoring, power | Others | Additional District Magistrate | |
8. | Details of Project Configuration/Product: | Details Not Applicable | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | (a)Details of certified report on compliance of earlier environmental clearance condition | (i)Certified Compliance By | Regional | (ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on | Lucknow | (iii)Letter No. | IV/ENV/UP/Ind-120/305/2009/668 dated 05.03.19 | (iv)Status of Compliance | Compiled | (v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) | Copy of Certified Compliance Report | (vi)Date of site visit | Feb 13 2019 12:00AM | (b)Details of Capacity Expansion | |
|
S. No. | Product/Activity (Capacity/Area) | Quantity From | Quantity To | Total | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | Writing and printing paper | 200 | 200 | 400 | Others | Tons per day (TPD) | Road | | (2.) | Power | 12 | 18 | 30 | Mega Watt(MW) | | Others | Cables | (3.) | Conventional CRP with lime kiln | 0 | 700 | 700 | Others | Tons per day | Others | pipelines | |
| (c)Details of Configuration | |
|
S. No. | Plant / Equipment / Facility | Existing Configuration | Proposed Configuration | Final configuration after expansion | Remarks |
---|
(1.) | Co-generation power plant | 12 | 18 | 30 | MW | (2.) | Writing and printing paper plant | 200 | 200 | 400 | TPD | (3.) | Conventional CRP with lime kiln | 0 | 700 | 700 | TPD | |
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | 11 Apr 2019 | (iv)Valid Upto | 31 Dec 2020 | (v)File No. | CTO Air-38652/UPPCB/Bareilly(UPPCBRO)/CTO/air/SHAH | (vi)Application No. | CTO Air-38652/UPPCB/Bareilly(UPPCBRO)/CTO/air/SHAH | (vii)Copy of Consent to operate valid as on date | Copy of Consent to Operate | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in Crores) | 460.25 | (b) Funds Allocated for Environment Management (Capital) (in Crores) | 21.03 | (c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) | 3.7 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) | 4.35 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | No | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 256740 | (b)Existing quantity of raw material/fuel | 258720 | (c)Total quantity of raw material/fuel | 515460 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | Bagasse, wheat straw, mixed hard wood | 515460 | Tons per Annum | | Nearby Sugar Mill/Farmers and plywood industries | Road | | 130 | Others | MoU and Purchase order | Copy of Linkage | (2.) | Sodium Chlorate | 2174.7 | Tons per Annum | | Open markets | Road | | 1000 | Open Market | | Copy of Linkage | (3.) | Hydrogen Peroxide | 1481.7 | Tons per Annum | | Open markets | Road | | 1000 | Open Market | | Copy of Linkage | (4.) | Starch | 792 | Tons per Annum | | Open markets | Road | | 800 | Open Market | | Copy of Linkage | (5.) | Pet coke as fuel for lime kiln | 14850 | Tons per Annum | | Nearby refineries | Road | | 300 | Others | Nearby refineries | Copy of Linkage | (6.) | caustic | 53130 | Tons per Annum | | 95% from CRP through pipeline and 5% from Market | Road,Others | Pipeline | 400 | Open Market | | Copy of Linkage | (7.) | Rice Husk and Bagasse Pith | 141900 | Tons per Annum | | Open markets | Road | | 100 | Others | Purchase order | Copy of Linkage | (8.) | Alkyletene dimer | 1584 | Tons per Annum | | Open markets | Road | | 300 | Open Market | | Copy of Linkage | (9.) | PCC/GCC | 24750 | Tons per Annum | | In house/market | Road | | 500 | Open Market | | Copy of Linkage | (10.) | Coal | 217800 | Tons per Annum | | Open markets | Road | | 1000 | Others | Purchase order | Copy of Linkage | (11.) | Oxygen | 1980 | Tons per Annum | | In house | Others | Pipeline | 0 | Others | In house by pipeline | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 01 Oct 2018 To 31 Dec 2018 | (b)Season | Post-Monsoon | |
|
14.1. No. of ambient Air Quality (AAQ) monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | PM10 | | Micro Gram per Meter Cube | 94.6 | 62.4 | 93.91 | 100 | (2.) | SO2 | | Micro Gram per Meter Cube | 20.6 | 6.3 | 19.97 | 80 | (3.) | NOx | | Micro Gram per Meter Cube | 41.4 | 15.8 | 39.21 | 80 | (4.) | PM2.5 | | Micro Gram per Meter Cube | 54.5 | 38.9 | 53.93 | 60 | |
14.2. No. of Ground Water monitoring locations : 9 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | TSS | | | mg/l | | 0 | 0 | 0 | 0 | (2.) | TDS | | | mg/l | | 589 | 228 | 500 | 2000 | (3.) | pH | | | NA | | 7.92 | 7.19 | 6.5 | 8.5 | (4.) | Total Hardness | | | mg/l | | 361.35 | 133.65 | 200 | 600 | (5.) | Chlorides | | | mg/l | | 61.64 | 10.85 | 250 | 1000 | (6.) | Fluoride | | | mg/l | | 0.85 | 0.26 | 1.0 | 1.5 | |
14.3. No. of Surface Water monitoring locations : 3 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | pH | | NA | | 7.89 | 7.73 | E | (2.) | DO | | mg/l | | 6.4 | 3.6 | E | (3.) | COD | | mg/l | | 126.9 | 7.9 | E | (4.) | BOD | | mg/l | | 26.4 | 2.3 | E | |
14.4. No. of Ambient Noise monitoring locations : 9 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Day) | A-weighted decibels(dB(A)) | 73.9 | 52.8 | Industrial- 75 Residential -55 | (2.) | Leq(Night) | A-weighted decibels(dB(A)) | 67.4 | 42.8 | Industrial - 70 Residential -45 | |
14.5. No. of Soil Sample Monitored locations : 6 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | pH | | | 8.06 | 7.16 | (2.) | N(Nitrogen) | Kilogram per hectare | | 258.92 | 137.85 | (3.) | Electric Conductivity | Millisiemens per Centimetre | | 0.67 | 0.21 | (4.) | P(Phosphorus) | Kilogram per hectare | | 117.58 | 50.38 | (5.) | K(Potassium) | Kilogram per hectare | | 155.03 | 42.21 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 2.6 To 9.17 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 0.82 To 8.95 | (c)Whether Ground Water Intersection will be there ? | NA | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity (Kilolitre per Day (Kld)) | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | GroundWater | | 16560 | 0 | Copy of Permission Letter | Pipeline | | Tube Well | | CGWA/NOC/IND/REN/2/2019/5562 | 18 Jun 2019 | 16560 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | Industrial Process | 13000 | 13000 | Effluent Treatment Plant | Others | Irrigation | 0 | 13000 | |
|
16.1. | (a)Total Waste Water Generation (Kilolitre per Day) | 13000 | (b)Total Discharged Water (Kilolitre per Day) | 13000 | (c)Total Reused Water (Kilolitre per Day) | 0 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | Ash | Fly Ash | | 65340 | Tons | 0 | Others | Given to farmers as manure and brick manufacturing | Others | Given to farmers as manure and brick manufacturing | (2.) | ETP sludge | Industrial Waste | | 5280 | Tons | 0 | Others | Burnt in boiler as fuel | Others | Dried and burnt in boiler as fuel | (3.) | Lime sludge | Industrial Waste | | 76560 | Tons | 0 | Others | Burnt in lime kiln | Others | Burnt in lime kiln | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | SO2 | | Microgram per Meter Cube | 16.6 | 1 | 0 | 18.69 | 80 | (2.) | PM10 | | Microgram per Meter Cube | 84.4 | 1 | 0 | 85.85 | 100 | (3.) | NOx | | Microgram per Meter Cube | 30.3 | 1 | 0 | 33.65 | 80 | (4.) | PM2.5 | | Microgram per Meter Cube | 52.6 | 1 | 0 | 53.06 | 60 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | Proposed 60 TPH Boiler | Coal | 72 | 2.0 | PM10 | | 30 | (2.) | 90 TPH recovery boiler | Black liquor | 70 | 2.8 | PM10 | | 100 | (3.) | Existing 80 TPH boiler | Rice husk/coal with pith and sludge | 65 | 2.8 | PM10 | | 100 | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 26250 | (b)Source | Existing 12 MW CPP and proposed 18 MW CPP (Co-gen | (c)Uploaded Copy of Agreement | Copy of Agreement | (d)Standby Arrangement (Details of DG Sets) | 0 | (e)Stack Height (in m) | 0 | |
|
20. | Land Ownership Pattern: | (a)Forest Land (ha.) | 0 | (b)Private Land (ha.) | 0 | (c)Government Land (ha.) | 0 | (d)Revenue Land (ha.) | 0 | (e)Other Land (ha.) | 24 | Total Land (ha.) | 24 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area (ha.) | 24585.07 | (b)Waste/Barren Land (ha.) | 2313.86 | (c)Grazing/ Community Land (ha.) | 1221.54 | (d)Surface Water Bodies (ha.) | 895.73 | (e)Settlements (ha.) | 2859.53 | (f)Industrial (ha.) | 893.38 | (g)Forest (ha.) | 0 | (h)Mangroves (ha.) | 0 | (i)Marine Area (ha.) | 0 | (j)Others (ha.) : No other land | 0 | Total (ha.) | 32769.11 | |
|
22. Land requirement for various activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement (ha.) | Remarks |
---|
(1.) | Main Plant | | 5.81 | Machinery, utilities and storage area | (2.) | Green belt | | 7.9 | | (3.) | Others | Admin/excise office,road/ paved area and open area | 10.29 | Admin/excise office,road/ paved area and open area | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Critically Polluted Area | Not applicable | 0 | No CPA within 10 km radius | (2.) | ESAs | Not applicable | 0 | No ESAs within 10 km radius | (3.) | ESZs | Not applicable | 0 | No ESZs within 10 km radius | (4.) | Wildlife Corridors | Not applicable | 0 | No Wildlife Corridors within 10 km radius | (5.) | NPA | Not applicable | 0 | No NPA within 10 km radius | (6.) | WLS | Not applicable | 0 | No WLS within 10 km radius | (7.) | Corridors | Not applicable | 0 | No Corridors within 10 km radius | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Forest | | Not applicable | 0 | No Forest within 10 km radius | (2.) | Archaeological Sites | | Not applicable | 0 | No archaeological sites in 10 km radius | (3.) | Defence Installations | | Not applicable | 0 | No defence installations in 10 km radius | |
|
23.3. | (a)Whether Noc / Permission from the competent authority is required? | No | (b)Whether NBWL recommendation is required? | No | |
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
25. | Tree Cutting: | (a)No. of Trees Cut for the Project (if Forest Land not Involved) | 0 | (b)Details of Tree Cutting and Planting of Trees | Not Applicable | |
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 24 | (b)Land yet to be acquired(Ha) | 0 | (c)Status of Land acquisition if not acquired | Already acquired | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | 0 | (b)No. of Households | 0 | (c)No. of PDFs (Project Displaced Families) | 0 | (d)No. of PAFs (Project Affected Families) | 0 | (e)Funds Allocated for R&R(in INR) (in Lacs) | 0 | (f)Status of R&R | Completed | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | No | (b)Whether conservation plan for Schedule-I Species has been prepared ? | No | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | No | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | No | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | Yes | (i)Details of Water Bodies in Buffer Area | Deoha or Garra River | (ii)Direction of Water Bodies in Buffer Area | South East | (iii)Distance of Water Bodies in Buffer Area | 3.7 | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 10 | (b)Permanent Employment-During Operation | 361 | (c)Temporary Employment- During Construction | 600 | (d)Temporary Employment- During Operation | 180 | (e)No. of working days | 330 | (f)Total Manpower | 1151 | |
|
|
S. No. | Description | Existing | Proposed | Total |
---|
(1.) | Total Area of Green Belt | 7.9 | 0 | 7.9 | (2.) | Percentage of Total Project Area | 33 | 0 | 33 | (3.) | No. of Plants | 10048 | 1800 | 11848 | (4.) | Funds Allocated | 10000000 | 5000000 | 15000000 | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Environmental | Utilization of agricultural waste as raw material and fuel | (2.) | Social | Employment generation and CER activities | (3.) | Financial | Improved livelihood with increased business opportunities | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details : NOT APPLICABLE |
35. Sector Specific Details For Industrial Projects - 1 |
|
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | No | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | No | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | NABET/EIA/1619/RA 0069 | (ii)Name of the EIA Consultant | J.M. EnviroNet Pvt. Ltd. | (iii)Address | JM EnviroNet Pvt. Ltd., 202A, ABW Tower, Near Iffco Chowk, Sector 25, Gurugram (Haryana) | (iv)Mobile No. | 9015209362 | (v)Landline No. | 9015209362 | (vi)Email Id | jmenviron@hotmail.com | (vii)Category of Accreditation | A | (viii)Sector of Accreditation | Industrial Projects - 1 | (ix)Validity of Accreditation | 07 Feb 2020 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Detail Sought : NIL |
Additional Detail Sought: |
---|
Sno. | ADS Letter | Remarks | Date of ADS |
---|
1. | ADS Reply Letter | We request your good self to kindly consider our proposal for EC proceedings. | 03 Oct 2019 | 2. | NA | Proposal deferred for want of additional information | 16 Aug 2019 | |
| Undertaking |
| I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. |
| Name of Applicant | Jitendra Prakash Gupta | Designation | SrVP | Name of Company (Applicant Name should not be given here) | KR PULP & PAPERS LIMITED | Address | 304, Roots Tower, District Centre, Laxmi Nagar, New Delhi |
|