Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) PROPOSED CONSTRUCTION OF ADVANCED NEUROSCIENCE CENTER by PGIMER, Chandigarh
(b)Name of the Company / Organisation HSCC LIMITED
(c)Registered Address E-6(A), Sector - 1, NOIDA,,Gautam Buddha Nagar,Uttar Pradesh-201301
(d)Legal Status of the Company Central PSU
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant NARENDRA MALIK
(b)Designation (Owner/ Partner/ CEO) ENGINEER
(c)Address PGIMER, SECTOR-12, CHANDIGARH,,Chandigarh,Chandigarh,Chandigarh-160012
(d)Pin code 160012
(e)E-mail santosh.appana789@gmail.com
(f)STD Code. 120(f)Telephone No. 2542436
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity8(a) Building and Construction projects
Minor Activity
(b)Category B2
   Reason for Applying at Ministry SEIAA
(c)Proposal Number IA/CH/MIS/110034/2019
(d)Master Proposal Number(Single Window) SW/110033/2019
(e)EAC concerned (for category A Projects only) INFRA-2
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Sector-12, Chandigarh
(b)Pincode 160012
(c)Bounded Latitudes (North)
From
Degree 30.45
Minutes
Second
From
Degree 30.46
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 76.46
Minutes
Second
From
Degree 76.47
Minutes
Second
(e)Survey of India Topo Sheet No. 405-105 D 97 ( N W C 57 - 1 40000)-5023
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 359
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 11
(j)Seismic Zone 4
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Chandigarh
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)GujaratPanchmahalKalolMadhvas
6.
Details of Terms of Reference (ToR):
(a)Whether TOR is mandatory for submitting application No
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason Government Hospital Project
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)300 Bedded Hospital Building3B+G+6 storey (Built-up area - 47648.6 Sqm.)
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)47648.6 Sqm.0Kilo Litre per DayOthersNA
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 236.50
(b) Funds Allocated for Environment Management (Capital) (in Crores) 2.09
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.91
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.34
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 47000
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 47000
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)CONSTRUCTION MATERIAL47000OthersTotal Qty in MTLocal MarketRoad50 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Apr 2019 To 30 Jun 2019
(b)Season Summer
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 1
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)SO2Mili Gram per Meter Cube14141480
(2.)NOxMili Gram per Meter Cube29292980
(3.)PM2.5Mili Gram per Meter Cube52525260
(4.)PM10Micro Gram per Meter Cube868686100
    14.2.     No. of Ground Water monitoring locations : 1
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)TSSOthersNTU0.10.10.11
(2.)pHNA6.956.9578.5
(3.)TDSmg/l391391400500
(4.)Fluoridemg/l0.180.1811.5
(5.)Heavy MetalsLeadmg/l0.010.010.010.01
(6.)Chloridesmg/l181850250
(7.)Total Hardnessmg/l272272272600
    14.3.     No. of Surface Water monitoring locations : 1
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA6.956.95A
(2.)DOmg/l1010A
(3.)BODOthersppm55A
(4.)CODNA00A
    14.4.     No. of Ambient Noise monitoring locations : 1
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))636365
(2.)Leq(Night)A-weighted decibels(dB(A))535355
    14.5.     No. of Soil Sample Monitored locations : 1
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)P(Phosphorus)Milligram per Kilogram166.4166.4
(2.)pH7.547.54
(3.)N(Nitrogen)Percent1.11.1
(4.)K(Potassium)Milligram per Kilogram7171
(5.)Electric ConductivityMillisiemens per Centimetre0.3350.335
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 100 To 80
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 100 To 80
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersMunicipal Corporation3673 Not Appliacble PipelineOthersMunicipal Corporation415516 Apr 2019400
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Sewer278300STP ETPReuse within the Plant & Recycling278
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 278
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 278
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Municipal solid wasteMunicipal Solid Waste358Tons10RoadAuthorized Recyclers
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM2.5Microgram per Meter Cube00010
(2.)NOxMicrogram per Meter Cube00010
(3.)PM10Microgram per Meter Cube00010
(4.)SO2Microgram per Meter Cube00010
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)naNA00OthersNANA
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 7349.48
(b)Source State Electricity Board
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 1010
(e)Stack Height (in m) 30
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 0
(c)Government Land (ha.) 112.09
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 112.09
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 0
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 0
(e)Settlements (ha.) 0
(f)Industrial (ha.) 0
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : Open 1.145
    Total (ha.) 1.145
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Built Up Area1.145
Total (ha.) 1.145
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)WLSSukhna Wildlife Sactuary88 Km from project site
(2.)Critically Polluted AreaNA0NA
(3.)NPANA0NA
(4.)ESAsNA0NA
(5.)ESZsNA0NA
(6.)CorridorsNA0NA
(7.)Wildlife CorridorsNA0NA
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)OthersNANA0NA
(2.)Defence InstallationsNA0NA
(3.)Archaeological SitesNA0NA
(4.)ForestNA0NA
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 61
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 1.145
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired NA
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? No
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 100
(b)Permanent Employment-During Operation 200
(c)Temporary Employment- During Construction 100
(d)Temporary Employment- During Operation 100
(e)No. of working days 365
(f)Total Manpower 500
32.
Green Belt in Ha:
(a)Total Area of Green Belt 0.1151
(b)Percentage of Total Project Area 0.10
(c)No. of Plants to be Planted 305
(d)Funds Allocated for Plantation 500000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialHospital Project
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For INFRA-2
S. No.Item Details
1.
Details of Building Construction:
(a)Maximum Height of the Building (Meters) 28
(b)Total No. of Flats to be Build 0
(c)No. of Buildings 1
(d)Total plot area (sqm) 11450
(e)Total built up area (sqm) 47648.6
2.
Foreshore Facilities and/or Marine Disposal:
(a)Whether Project Involves Foreshore Activities and/or marine Disposal? No
3.
Rain Water Harvesting:
(a)No. of Storage 0
(b)Capacity 0
(c)No. of Recharge Pits 2
(d)Capacity 77.65
4.
Parking:
(a)Details of 4 Wheeler/ 2 Wheeler Parking 476
5.
Energy Saving Measures:
(a)Source/Mode LED AND SOLAR PANELS
(b)Percentage 10
(c)Quantity 112
6.
Other details:
(a)Details of impact on Water Bodies and Drainage patters of catchment area 0
(b)Details of Traffic Density Impact Assessment and Modelling Study Copy of Details of Traffic Density Impact Assessment and Modelling Study
(c)In case Underground Tunnel Project below the Forest Land - Subsidence Impact Study report Copy of Underground Tunnel Project below the Forest Land - Subsidence Impact Study report
     7.       Type of Industries to be established with Industrial Estate as per their category A/B
S. No.Type of IndustryNo. of UnitsCategory A/B
NIL
8.
Length of the alignment N/A
9.
Details Bridges/ROB/Interchanges,Flyovers,Vehicle Underpass and Pedestrian Underpass
Details Not Applicable
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1720/IA0029
(ii)Name of the EIA Consultant GREEN CIRCLE INC., VADODARA
(iii)Address Green Empire(Anupusham), Above Axis Bank, Near Yash Complex, Gotri Main Road, Vadodara
(iv)Mobile No. 7678671073
(v)Landline No. 0265237126
(vi)Email Id eia1@greenircleinc.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation INFRA-2
(ix)Validity of Accreditation 04 Jun 2020
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1. Eds Raise LetterKindly see the attached file for more details and submit the following: (i) Application through Accredited Consultant alongwith accreditation Certificated. (ii) There is a discrepancy in the Plot area and Built-up area mentioned in the Form-1 and 1-A. Please rectify it. (iii) Plan for Corporate Environment Responsibility (CER) as specified under Ministry’s Office Memorandum vide F.No. 22-65/2017-IA.III dated 1st May 2018. . 08 Jul 2019
2.NAThe correction have been made as per the instruction received 08 Jul 2019
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantNARENDRA MALIK
DesignationENGINEER
Name of Company (Applicant Name should not be given here)HSCC LIMITED
AddressE-6(A), Sector - 1, NOIDA
Print