1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | Proposed Limestone Mine (ML Area: 582.962 ha) with Limestone Production Capacity of 3.9 Million TPA and waste/ topsoil 225000 CuM per annum (Maximum) with installation of Crusher of 1000 TPH Capacity | (b)Name of the Company / Organisation | ACC LTD | (c)Registered Address | ACC LTD
JAMUL CEMENT WORKS
JAMUL VILLAGE
PO JAMUL CEMENT WORKS ,,Durg,Chhattisgarh-490024 | (d)Legal Status of the Company | Private | (e)Joint Venture | No | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | VINAY SARAN KAPUR | (b)Designation (Owner/ Partner/ CEO) | GM ENVIRONMENT | (c)Address | ACC LIMITED
JAMUL CEMENT WORKS
JAMUL VILLAGE
PO JAMUL CEMENT WORKS,,Durg,Durg,Chhattisgarh-490024 | (d)Pin code | 490024 | (e)E-mail | anilkumar.sahu.ext@adani.com | (f)STD Code. | 788(f)Telephone No. | 2286427 | (g)Fax No. | | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a.I)Project/Activity | 1(a) Mining of minerals 2(b) Mineral beneficiation
| Minor Activity | 2(b) Mineral beneficiation
| (b)Category | A | (c)Proposal Number | IA/CG/MIN/109258/2018 | (d)Master Proposal Number(Single Window) | SW/109256/2019 | (e)EAC concerned (for category A Projects only) | Non-Coal Mining | (f)Project Type | Fresh EC |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | Khasra Map is enclosed | (b)Pincode | 490024 | (c)Bounded Latitudes (North) | | From | | Degree | 214530.50 | Minutes | | Second | | From | | Degree | 215408.67 | Minutes | | Second | | (d)Bounded Longitudes (East) | | From | | Degree | 821402.99 | Minutes | | Second | | From | | Degree | 822138.95 | Minutes | | Second | | (e)Survey of India Topo Sheet No. | Core zone - 64 K/5 & Buffer zone - 64 K/1, 64 K/2, | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 263 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 0.25 | (j)Seismic Zone | 2 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Chhattisgarh | |
|
|
Details of State of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
NIL | |
|
6. | Details of Terms of Reference (ToR): | (a)MoEF&CC / SEIAA File Number | J-11015/45/2018-IA.II (M) | (b)Date of Apply of TOR | 28 Apr 2018 | (c)Date of Issue of TOR / Standard ToR | 17 Jul 2018 | (d)Previous TOR Letter | Copy of Previous TOR letter | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | No | (b)Whether details of Public Hearing available? | Yes | (c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above | Yes | |
|
7.1. Details of Public Hearing |
---|
|
S. No. | Details of Advertisement | Details of Public Hearing | Venue | Location Details | No. of People Attended | Issues Raised | Designation of Presiding Officer | Other Designation of Presiding Officer |
---|
(1.) | | Copy of Public Hearing : | Copy of Public Hearing | Date : | 07 Jun 2019 | Distance of Public Hearing Venue from the Proposed Project : | 1.3 |
| Play ground near village Bohardih adarsh aanganbadi house no. 1 gram panchayat Bohardih, Tehsil Masturi, District Bilaspur, Chhattisgarh | State : | Chhattisgarh | District : | Bilaspur | Tehsil : | Masturi | Village : | Bidiyadih, Bhurkunda, Godadih & Bohardih |
| 600 | Regarding Employment Generation, Women Empowerment, Infrastructure Development, Skill Development, Health Education, Water Facility etc. | Others | Additional District Magistrate | |
8. | Details of Project Configuration/Product: | |
|
8.1. Project Configuration |
---|
S. No. | Plant/Equipment/Facility | Configuration | Remarks |
---|
(1.) | Hydraulic backhoe with rock breaker | 01 | 3.0 CuM Backhoe/60T class machine | (2.) | Hydraulic Drill | 02 | 115/152 mm dia | (3.) | Dozer | 01 | - | (4.) | Water tanker | 01 | 20 KL | (5.) | Mobile Service Van | 01 | - | (6.) | Hydraulic shovel | 01 | 3.0 CuM | (7.) | Dumper | 07 | 60 T | (8.) | Tipper | 06 | 15 T | (9.) | Pay loader | 01 | 5.0 CuM Bucket | (10.) | Pickup Van | 01 | - | (11.) | Mobile Crusher (s) | - | 1000 TPH | (12.) | Hydraulic shovel | 03 | 5.0 CuM | (13.) | Hydraulic shovel | 03 | 5.0 CuM | (14.) | Hydraulic shovel | 03 | 5.0 CuM | (15.) | Hydraulic shovel | 03 | 5.0 CuM | (16.) | Explosive Van | 01 | 10 Tonne | (17.) | Diesel tanker | 01 | 3 KL | |
8.2. Product |
---|
S. No. | Product/Activity (Capacity/Area) | Quantity | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | Lime stone | 3900000 | Tons per Annum | | Road,Conveyor Belt | | (2.) | Waste/Top Soil | 225000 | Others | Cubic Meter per Annum | Others | Through haul road | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | Details Not Applicable | |
|
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | N/A | (iv)Valid Upto | N/A | (v)File No. | NA | (vi)Application No. | NA | (vii)Copy of Consent to operate valid as on date | NA | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in Crores) | 125 | (b) Funds Allocated for Environment Management (Capital) (in Crores) | 12.5 | (c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) | 2.5 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) | 1.0 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | No | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 640100 | (b)Existing quantity of raw material/fuel | N/A | (c)Total quantity of raw material/fuel | 640100 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | HSD | 6500 | Others | KL | Bilaspur | Road | | 45 | Open Market | | Copy of Linkage | (2.) | EXPLOSIVE | 633600 | Others | Kilogram | Bilaspur | Road | | 45 | Open Market | | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 01 Mar 2018 To 31 May 2018 | (b)Season | Summer | |
|
14.1. No. of ambient Air Quality (AAQ) monitoring locations : 12 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | PM10 | | Micro Gram per Meter Cube | 87.6 | 53.8 | 86.92 | 100 | (2.) | SO2 | | Micro Gram per Meter Cube | 14.0 | 6.2 | 13.84 | 80 | (3.) | NOx | | Micro Gram per Meter Cube | 22.2 | 11.8 | 21.99 | 80 | (4.) | PM2.5 | | Micro Gram per Meter Cube | 42.3 | 23.7 | 41.92 | 60 | |
14.2. No. of Ground Water monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | TSS | | | NA | | 0.0 | 0.0 | 0.0 | 0.0 | (2.) | pH | | | Others | others | 8.09 | 7.29 | 6.5 | 8.5 | (3.) | Fluoride | | | mg/l | | 0.85 | 0.40 | 1.0 | 1.5 | (4.) | TDS | | | mg/l | | 598.0 | 231.0 | 500 | 2000 | (5.) | Chlorides | | | mg/l | | 308.77 | 26.13 | 250 | 1000 | (6.) | Total Hardness | | | mg/l | | 535.50 | 117.30 | 200 | 600 | |
14.3. No. of Surface Water monitoring locations : 3 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | pH | | Others | others | 7.75 | 7.39 | D | (2.) | DO | | mg/l | | 5.60 | 4.70 | D | (3.) | BOD | | mg/l | | 9.10 | 4.30 | D | (4.) | COD | | mg/l | | 24.30 | 14.20 | D | |
14.4. No. of Ambient Noise monitoring locations : 12 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Night) | A-weighted decibels(dB(A)) | 44.3 | 40.9 | I 70-75, C 55-65, R 45-55, S 40-50 | (2.) | Leq(Day) | A-weighted decibels(dB(A)) | 54.5 | 51.4 | I 70-75, C 55-65, R 45-55, S 40-50 | |
14.5. No. of Soil Sample Monitored locations : 8 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | P(Phosphorus) | Kilogram per hectare | | 32.14 | 12.36 | (2.) | pH | Others | Others | 7.78 | 7.02 | (3.) | Electric Conductivity | Others | ms/cm | 0.44 | 0.11 | (4.) | N(Nitrogen) | Kilogram per hectare | | 348.17 | 198.65 | (5.) | K(Potassium) | Kilogram per hectare | | 391.49 | 205.14 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 04.5 To 11.0 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 03.9 To 15.0 | (c)Whether Ground Water Intersection will be there ? | Yes | (d)Upload Copy of Central Ground Water Authority Letter | Copy of Central Ground Water Authority Letter | (e)Letter No. | 21-4/2596/CT/MIN/2019 | (f)Date of Issue | 26 Jun 2019 | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity (Kilolitre per Day (Kld)) | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | Surface | | 330 | 0.25 | Copy of Permission Letter | Pipeline | | Others | Lilager River | 6208/F 4-231/S-2/31/OJapra/13 | 12 Sep 2018 | 5267 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | Drinking & sanitation | 5 | 5 | Soak Pit via septic tank | Others | Soak pit via septic tank | 0 | 5 | (2.) | workshop effluent | 9.0 | 20 | Oil water separator | Others | Oil and water separator | 9 | 0 | |
|
16.1. | (a)Total Waste Water Generation (Kilolitre per Day) | 14 | (b)Total Discharged Water (Kilolitre per Day) | 5 | (c)Total Reused Water (Kilolitre per Day) | 9 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | Soil | Others | Mine waste | 90000 | Tons | 0 | Others | Dumpers/Tippers | Others | Used for backfilling/Bund | (2.) | Over Burden | Others | Mine waste | 360000 | Tons | 0 | Others | Dumpers/Tippers | Others | Used for backfilling/Bund | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | PM2.5 | | Microgram per Meter Cube | 42.3 | 0 | 1.12 | 43.43 | 60 | (2.) | SO2 | | Microgram per Meter Cube | 14.0 | 0 | 1.39 | 15.40 | 80 | (3.) | NOx | | Microgram per Meter Cube | 17.6 | 0 | 1.58 | 19.19 | 80 | (4.) | PM10 | | Microgram per Meter Cube | 87.6 | 0 | 4.34 | 91.95 | 100 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | Crusher (s) | - | 30 | 1.1 | PM10 | | 36.5 | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 2500 | (b)Source | Chhattisgarh State Power Distribution& Proposed Ca | (c)Uploaded Copy of Agreement | Not Applicable | (d)Standby Arrangement (Details of DG Sets) | NA | (e)Stack Height (in m) | . | |
|
20. | Land Ownership Pattern: | (a)Forest Land (ha.) | 0 | (b)Private Land (ha.) | 505.167 | (c)Government Land (ha.) | 77.795 | (d)Revenue Land (ha.) | 0 | (e)Other Land (ha.) | 0 | Total Land (ha.) | 582.962 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area (ha.) | 505.167 | (b)Waste/Barren Land (ha.) | 0 | (c)Grazing/ Community Land (ha.) | 0 | (d)Surface Water Bodies (ha.) | 0 | (e)Settlements (ha.) | 0 | (f)Industrial (ha.) | 0 | (g)Forest (ha.) | 0 | (h)Mangroves (ha.) | 0 | (i)Marine Area (ha.) | 0 | (j)Others (ha.) : grass land | 77.795 | Total (ha.) | 582.962 | |
|
22. Land requirement for various activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement (ha.) | Remarks |
---|
(1.) | Quarry Area | | 360 | backfilled-54 ha and 306 water reservoir | (2.) | Green belt | | 73 | Lease periphery-73 ha and Non Mineralized 30 ha | (3.) | Built Up Area | | 13 | Road and Builtup area | (4.) | Others | Virgin area | 136.962 | | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | NPA | None | . | No NPA within 10 km of mine site | (2.) | ESZs | None | . | No ESZs within 10 km of mine site | (3.) | Corridors | None | . | No Corridors within 10 km of mine site | (4.) | Wildlife Corridors | None | . | No wILDLIFE Corridors within 10 km of mine site | (5.) | Critically Polluted Area | None | . | No CPA within 10 km of mine site | (6.) | WLS | None | . | No WLS within 10 km of mine site | (7.) | ESAs | None | . | No ESAs within 10 km of mine site | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Forest | | None | . | None | (2.) | Archaeological Sites | | None | . | no | (3.) | Defence Installations | | None | . | No | |
|
23.3. | (a)Whether Noc / Permission from the competent authority is required? | No | (b)Whether NBWL recommendation is required? | No | |
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
25. | Tree Cutting: | (a)No. of Trees Cut for the Project (if Forest Land not Involved) | . | (b)Details of Tree Cutting and Planting of Trees | Not Applicable | |
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 82.247 | (b)Land yet to be acquired(Ha) | 422.92 | (c)Status of Land acquisition if not acquired | In progress | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | 4 | (b)No. of Households | 1478 | (c)No. of PDFs (Project Displaced Families) | 10 | (d)No. of PAFs (Project Affected Families) | 722 | (e)Funds Allocated for R&R(in INR) (in Lacs) | 273.985 | (f)Status of R&R | In-Progress | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | No | (b)Whether conservation plan for Schedule-I Species has been prepared ? | No | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | No | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | Yes | (i)Details of Water Bodies in Core Area | Proposed and existing canal | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | Yes | (i)Details of Water Bodies in Buffer Area | Lilager River, Seonath River and nalah | (ii)Direction of Water Bodies in Buffer Area | East | (iii)Distance of Water Bodies in Buffer Area | 0.25 | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 0 | (b)Permanent Employment-During Operation | 56 | (c)Temporary Employment- During Construction | 0 | (d)Temporary Employment- During Operation | 0 | (e)No. of working days | 300 | (f)Total Manpower | 56 | |
|
32. | Green Belt in Ha: | (a)Total Area of Green Belt | 127 | (b)Percentage of Total Project Area | 21.79 | (c)No. of Plants to be Planted | 317500 | (d)Funds Allocated for Plantation | 50800000 | (e)Uploaded Green Belt plan | Copy of Green Belt Plan | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Social | Proposed project will result in growth of the surrounding areas by increased direct and indirect employment opportunities in the region including ancillary development and supporting infrastructure. Beside this, Royalty and other taxes would be additional benefit and it will be utilized by local administration for the development of socio-economic infrastructure and well being of the local population. The various activities proposed through CER (Corporate Environment Responsibility) would help i | (2.) | Environmental | At the conceptual stage, out of the total mining lease area (i.e. 582.962 ha), total mined-out area will be 360 ha; out of which, 54 ha will be backfilled and remaining 306 ha will be developed as water reservoir. Water stored in these reservoirs will also help in ground water recharge and agriculture.
At the end of the life of mine total 127 ha (54 ha on backfilled area, 43 ha around lease periphery and 30 ha on non-mineralized area) area will be covered under greenbelt and plantation. | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details For Non-Coal Mining |
|
1. No. of Mineral(s) to be Mined : 1 |
---|
S. No. | Mineral(s) to be Mined | Major or Minor Mineral |
---|
(1.) | Limestone | Major | (2.) | Limestone | Major | |
|
2. | Mine Capacity in ROM (Run of Mine) | 3900000 | |
|
|
4. | Mining Plan: | (a)Approval Letter No. | BLS/LST/MPLN-1187/2019 | (b)Date of Approval | 04 Feb 2019 | (c)Approved Letter | Copy of Approved Letter | (d)Approved By State Mining and Geology Department | IBM | (e)Approved Mining Lease Area | 582.962 | (f)Approved Capacity | 3900000 | |
|
5. | Technical Details: | (a)Total Geological Reserves (Million Ton) | 182.74 | (b)Mineable Reserves (Million Ton) | 145.11 | (c)Extractable Reserves(Million Ton) | 145.11 | (d)Percent(%) of Extraction | 100 | (e)Grade of Coal /Ore /Mineral | cement grade | (f)Stripping Ratio | 1 : 0.1 | (g)Category of Gaseousness (Only for Coal Mining, Others may Write NA) | na | (h)Average Gradient(Degree) | 45 | (i)Mining Method | Opencast | (j)Life of Mine (Years) | 40 | |
|
6. | Details of Beneficiations: | (a)Whether it is proposed to install beneficiation plant/Coal washery within the mining lease area | No | (b)Whether it is proposed to install crusher within the mining lease area | Yes | (c)No. of crushers | 1 | |
|
6.1. Details of crusher: |
---|
S. No. | Crusher ID | Capacity (in PH) | Remarks |
---|
(1.) | 1 | 1000 | | |
|
7. | Details of Seams: | (a)Whether details of seam applicable | No | |
|
8. | Details of Mining Lease: | (a)Mining Lease Area (in Hectare) | 582.962 | (b)Whether obtained Letter of Intent (LOI) from the state government ? | No | (i)Reason thereof | Lease granted | (c)Whether Lease Deed Executed ? | Yes | (i)Copy of Executed Lease deed valid as on Date | Copy of Executed Lease deed | (ii)Provide area in Hectare as per executed lease deed (initial) document | 582.962 | (iii)Validity of the lease deed | From : 21 Oct 2009 To : 20 Oct 2059 | (iv)Date of Execution of Mining Lese | 21 Oct 2009 | (v)Reference Number | nil | (d)Whether Lease Deed Renewed ? | No | (i)Reason thereof | Lease valid till 2059 | |
|
9. | OB (Over Burden) Management: | (a) Details of External Dumps: | (i)No. of OB Dumps | 0 | (ii)Total Area (in Hectare) | 0 | (iii)Height (in meter) | 0 | (iv)Quantity (in Million Cubic meter) | 0 | (v)No. of year back fill up | 0 | (b) Details of Internal Dumps: | (i)No. of Internal Dumps | 1 | (ii)Total Area (in Hectare) | 54 | (iii)Height (in meter) | 17 | (iv)Quantity (in Million Cubic meter) | 918 | |
|
10. | Details of Topsoil Management: | (a)Quantity of Topsoil excavated during the entire life of the mine (in Million Cubic metre) | 1.8 | (b)Quantity of Topsoil proposed for utilization for reclamation during the entire life of the mine (in Million Cubic metre) | 1.8 | (c)Quantity of Topsoil proposed for utilization for other activities during the entire life of the mine (in Million Cubic metre) | 0 | |
|
11. | Details of Final Mine Void: | (a)Area (in Hectare) | 360 | (b)Depth (in meter) | 18 | (c)Volume (in Million Cubic meter) | 55.08 | |
|
12. | Details of Quarry: | (a)Final Void of 306 (hectare) at a Depth of 18 meter which is Proposed to be Converted into a Water Body. | (b)Total Quarry Area (ha) | 582.962 | |
|
13. | Details of Transportation: | (a)In Pit/Underground to Surface | From working face to crusher hopper will be transp | (b)Surface to Siding/Loading | Loading will be done by Dumpers | (c)Transportation / Conveyor Details | Crushed limestone will be supplied to the proposed | |
|
|
14. Details of Land Usage (Pre-Mining) |
---|
S. No. | LAND USE | Other LAND USE | WITHIN ML AREA (Hectare) | OUTSIDE ML AREA (Hectare) | TOTAL (Hectare) |
---|
(1.) | AGRICULTURE LAND | | 505.167 | 0 | 505.167 | (2.) | FOREST LAND | | 0 | 0 | 0 | (3.) | GRAZING LAND | | 0 | 0 | 0 | (4.) | SETTLEMENTS | | 0 | 0 | 0 | (5.) | OTHERS(Specify) | Grass land | 77.795 | 0 | 77.795 | (6.) | SURFACE WATER BODIES | | 0 | 0 | 0 | (7.) | WASTE LAND | | 0 | 0 | 0 | |
TOTAL | 582.962 | 0 | 582.962 | |
|
15. Details of Land Usage (Post-Mining) |
---|
S. No. | LAND USE | Other LAND USE | Plantation (ha) | Water Body (ha) | Public Use (ha) | Undisturbed (ha) | Total |
---|
(1.) | ROADS | | 0 | 0 | 10 | | 10 | (2.) | BUILT UP AREA (COLONY/OFFICE) | | 0 | 0 | 3.0 | | 3 | (3.) | GREEN BELT | | 73 | 0 | 0 | | 73 | (4.) | VIRGIN AREA | | 0 | 0 | 136.962 | | 136.962 | (5.) | EXCAVATION/QUARRY | | 54 | 306 | 0 | | 360 | (6.) | EXTERNAL OB DUMPS | | 0 | 0 | 0 | | 0 | (7.) | INTERNAL OB DUMPS | | 0 | 0 | 0 | | 0 | (8.) | TOP SOIL STORAGE | | 0 | 0 | 0 | | 0 | |
TOTAL | 127 | 306 | 149.962 | 0 | 582.962 | |
16. | Details of Reclamation: | Total Afforestation Plan shall be Implemented Covering of Mining.This will Include: | (a)External OB Dump(in hectare) | 0 | (b)Internal Dump(in hectare) | 0 | (c)Quarry(in hectare) | 360 | (d)Safety Zone(in hectare) | 43 | (e)Final Void of 54 (hectare) at a Depth of 18 meter which is Proposed to be Converted into a Water Body. | (f)Density of Tree Plantation per ha (in no.) | 2500 | (g)Others in ha (such as Excavation Area along ML Boundary, along Roads and Infrastructure, Embankment Area and in Township Located Outside the Lease etc) | 13.0 | (h)Total afforestation plant (in hectare) | 127 | |
|
17. | Status of progressive Mining Closure Plan: | Details Not Applicable | |
|
18. Details of Actual Coal/ ORE Production vis-a-vis Sanctioned Capacity since the Inception: |
---|
S. No. | Financial Year | Sanctioned Capacity as per EC (MTPA) | Sanctioned Capacity as per CTO | Sanctioned Capacity as per approved mining plan | Actual Production | Excess Production Beyond the EC / CTO/ Mining Plan Sanctioned Capacity (MTPA) |
---|
(1.) | 0 | 0 | 0 | 0 | 0 | 0 | |
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | Yes | (b)Name of the Court | High Courts | (c)Name of the Sub Court | Chhattisgarh | (d)Case No. | 1090 of 2014 | (e)Orders/Directions of the court ,if any and its relevance with the proposed project | • In view of the above, the writ petition is dispo | (f)Case Details | ? High Court of Chhattisgarh at Bilaspur under Wri | (g)Uploaded Court Order | Copy of Court Order | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | No | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | NABET/EIA/1619/RA 0069 | (ii)Name of the EIA Consultant | JM EnviroNet Pvt Ltd | (iii)Address | J.M EnviroNet Pvt. Ltd., 202-A, ABW Tower, M.G. Road, Near IFFCO Chowk,, Gurugram - 122 001 (Haryana) | (iv)Mobile No. | 9730254462 | (v)Landline No. | 0124414192 | (vi)Email Id | jmenviron@hotmail.com | (vii)Category of Accreditation | A | (viii)Sector of Accreditation | Non-Coal Mining | (ix)Validity of Accreditation | 02 Feb 2020 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Detail Sought : NIL |
Additional Detail Sought: |
---|
Sno. | ADS Letter | Remarks | Date of ADS |
---|
1. | ADS Reply Letter | We are herewith submitting ADS Reply | 30 Sep 2019 | 2. | NA | The proposal was placed in before the EAC and PP made presented
about the project, findings of their study and EMP. Based on the deliberation
by EAC and presentation made by PP, the Committee
deferred the proposal and asked the PP to submit the following information
for further consideration and assessment.