Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Industrial Model Township, Kharkhoda, Sonepat, Haryana
(b)Name of the Company / Organisation HARYANA STATE INDUSTRIES AND INFRASTRUCTURE DEVELOPMENT CORPORATION HSIIDC
(c)Registered Address HSIIDC, Plot No C-13-14, Sector-6, panchkula, haryana,,Panchkula,Haryana-134109
(d)Legal Status of the Company State PSU
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant HSIIDC Haryana
(b)Designation (Owner/ Partner/ CEO) GM
(c)Address HSIIDC, Kharkhoda, SOnepat, Haryana,,Kharkhoda,Sonipat,Haryana-131001
(d)Pin code 131001
(e)E-mail infosmiakundli@gmail.com
(f)STD Code. 130(f)Telephone No. 2370586
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity7(c) Industrial estates/ parks/ complexes/ areas, export processing Zones
Minor Activity7(c) Industrial estates/ parks/ complexes/ areas, export processing Zones
(b)Category A
(c)Proposal Number IA/HR/NCP/62795/2017
(d)Master Proposal Number(Single Window) SW/108752/2019
(e)EAC concerned (for category A Projects only) INFRA-1
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Kharkhoda
(b)Pincode 131402
(c)Bounded Latitudes (North)
From
Degree 284935.92
Minutes
Second
From
Degree 285003.98
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 765442.38
Minutes
Second
From
Degree 765812.05
Minutes
Second
(e)Survey of India Topo Sheet No. 53D13
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 222
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 4
(j)Seismic Zone 4
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Haryana
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)HaryanaSonipatKharkhoda
6.
Details of Terms of Reference (ToR):
(a)Whether TOR is mandatory for submitting application Yes
(b)MoEF&CC / SEIAA File Number 21-237/2017-IA.III
(c)Date of Apply of TOR 09 Jun 2017
(d)Date of Issue of TOR / Standard ToR 23 Aug 2017
(e)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :17 Jan 2019
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :08 Mar 2019
Distance of Public Hearing Venue from the Proposed Project :0
Kharkhoda
State :Haryana
District :Sonipat
Tehsil :Kharkhoda
Village :Kharkhoda
31Basic issues related to employment and social developmentDeputy Commissioner
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Industrial Model Township Kharkhoda1301.95 hectare
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)1301.951301.95HectaresRoad,Rail
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 4000
(b) Funds Allocated for Environment Management (Capital) (in Crores) 0.46
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 80
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.46
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? Yes
d)Inter-State boundaries and international boundaries Yes
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 0
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 0
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Coarse Sand0Tons per AnnumNearby AreaRoad10 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Oct 2017 To 31 Dec 2017
(b)Season Post-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 10
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube255.9133.3253.6100
(2.)SO2Micro Gram per Meter Cube14.17.21480
(3.)NOxMicro Gram per Meter Cube4724.345.980
(4.)PM2.5Micro Gram per Meter Cube129.764.7128.560
    14.2.     No. of Ground Water monitoring locations : 6
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)TDSmg/l218112605002000
(2.)Total Hardnessmg/l810450200600
(3.)Fluoridemg/l1.20.711.5
(4.)TSSmg/l218112605002000
(5.)Heavy MetalsZincmg/l10.6515
(6.)Chloridesmg/l5623302501000
(7.)pHNA8.127.096.58.5
    14.3.     No. of Surface Water monitoring locations : 3
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)BODmg/l4.12.8A
(2.)pHNA7.927.02A
(3.)CODmg/l1610A
(4.)DOmg/l75.4A
    14.4.     No. of Ambient Noise monitoring locations : 6
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))63.448.375
(2.)Leq(Night)A-weighted decibels(dB(A))55.739.165
    14.5.     No. of Soil Sample Monitored locations : 10
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)P(Phosphorus)Milligram per Kilogram10.37.1
(2.)K(Potassium)Milliequivalents per 100 Gram0.450.28
(3.)Electric ConductivityMillisiemens per Centimetre16.413.4
(4.)N(Nitrogen)Percent39.933.5
(5.)pH8.167.56
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 1.57 To 24.84
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 0.64 To 22.46
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)Surface872755.2Copy of Permission LetterCanalOthersCanal1170-73/Const14 Jun 201166150
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Waste Water From Site6390063900CETPReuse within the Plant & Recycling,Green Belt Renewal Plant63900
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 63900
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 63900
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Solid WasteIndustrial WasteDomestic Waste131Tons0RoadOthersTSDF, Authorised Recycler
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube255.90.70.22256.13100
(2.)PM2.5Microgram per Meter Cube129.70.70.22129.9360
(3.)NOxMicrogram per Meter Cube51.20.76.557.880
(4.)SO2Microgram per Meter Cube14.10.70.815.080
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)DG SetDiesel300.332PM100.0375
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 500
(b)Source State Electricity Board
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 1890 KVA
(e)Stack Height (in m) 30
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 1301.95
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 1301.95
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 41900.74
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 255.74
(e)Settlements (ha.) 3396.04
(f)Industrial (ha.) 0
(g)Forest (ha.) 232.8
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : Open Land, Open Scrub, Vegetation 2363.18
    Total (ha.) 48148.5
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)OthersIndustrial Model Township1301.95Hectare
Total (ha.) 1301.95
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaNil0Nil
(2.)ESZsNil0Nil
(3.)CorridorsNil0Nil
(4.)Wildlife CorridorsNil0Nil
(5.)ESAsNil0Nil
(6.)WLSNil0Nil
(7.)NPANil0Nil
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Archaeological SitesNil0Nil
(2.)Defence InstallationsNil0Nil
(3.)ForestSultanpur Dabas8Reserve Forest
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 1301.95
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired Aquired
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 10
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 5100
(f)Status of R&R In-Progress
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? No
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 50000
(c)Temporary Employment- During Construction 600
(d)Temporary Employment- During Operation 49400
(e)No. of working days 365
(f)Total Manpower 100000
32.
Green Belt in Ha:
(a)Total Area of Green Belt 433.62
(b)Percentage of Total Project Area 33.31
(c)No. of Plants to be Planted 202400
(d)Funds Allocated for Plantation 20240000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.       Project Benefits
S. No. Type of Project BenefitsDetails of Project Benefits
NIL
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For INFRA-1
S. No.Item Details
1.
Details of Building Construction:
(a)Maximum Height of the Building (Meters) 100
(b)Total No. of Flats to be Build 1379
(c)No. of Buildings 3109
(d)Total plot area (sqm) 13019506
(e)Total built up area (sqm) 4449721
2.
Foreshore Facilities and/or Marine Disposal:
(a)Whether Project Involves Foreshore Activities and/or marine Disposal? No
3.
Rain Water Harvesting:
(a)No. of Storage 0
(b)Capacity 0
(c)No. of Recharge Pits 32
(d)Capacity 3200
4.
Parking:
(a)Details of 4 Wheeler/ 2 Wheeler Parking 5947
5.
Energy Saving Measures:
(a)Source/Mode LED CFL SOLAR
(b)Percentage 2
(c)Quantity 10
6.
Other details:
(a)Details of impact on Water Bodies and Drainage patters of catchment area Nil
(b)Details of Traffic Density Impact Assessment and Modelling Study Copy of Details of Traffic Density Impact Assessment and Modelling Study
(c)In case Underground Tunnel Project below the Forest Land - Subsidence Impact Study report Copy of Underground Tunnel Project below the Forest Land - Subsidence Impact Study report
     7.       Type of Industries to be established with Industrial Estate as per their category A/B
S. No.Type of IndustryNo. of UnitsCategory A/B
(1.)Category B as per EIA Notification2614B
(2.)Category A as per EIA Notification475A
8.
Length of the alignment N/A
9.
Details Bridges/ROB/Interchanges,Flyovers,Vehicle Underpass and Pedestrian Underpass
Details Not Applicable
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1619/RA 0064
(ii)Name of the EIA Consultant Grass Roots Research and Creation India Pvt. Ltd.
(iii)Address F-375, Sector-3, Noida
(iv)Mobile No. 9811554031
(v)Landline No. 0120404463
(vi)Email Id eia@grc-india.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation INFRA-1
(ix)Validity of Accreditation 04 Dec 2019
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NACopy of documents in support of the competence/authority is not submitted. Please submit the copy of documents in support of the competence/ authority 12 Jul 2019
2.NAThe correction have been made as per the instruction received 16 Jul 2019
3.NA1) In Form 2 application at SI. NO. 20 and SI. No. 22(1) units of land not mentioned 2) In Form -2 application at Serial No. 27 R&R details like No of house, PDF, PAF are mentioned Zero and fund allocated for R&R whether it is Lakhs/Crore please clarify. 3) As per the ToR Condition Green belt should be 33%, but in Form2 application it was mentioned 15.55 % please clarify. 4) No Declaration from EIA consultant organization about who prepared EIA/EMP report and experts involved in preparation with their signature are not available in EIA/EMP report. Please submit the report with above declaration with signature. 5) ToR conditions wise compliance document also not find in EIA/EMP report 18 Jul 2019
4.NAThe correction have been made as per the instruction received 31 Jul 2019
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1. ADS Reply LetterADS REPLY IMT KHARKHODA 20 Jul 2020
2.NAPlease submit following information as per Minutes of 237th EAC meeting held on 29.06.2020: (i) The proponent is required to submit a detailed scheme for utilization of treated effluent and sewage as well for achieving zero discharge into drain leading to river Yamuna. (ii) Revised layout plan to be submitted by excluding Rampur village within the project boundaries. 13 Jul 2020
3. ADS Reply LetterReply of ADS by MS 09 Jun 2020
4.NA