Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Adasa UG to OC
(b)Name of the Company / Organisation Western Coalfields Limited
(c)Registered Address Coal Estate Civil lines, Nagpur-440001,Coal Estate Civil lines, Nagpur-440001,Nagpur,Maharashtra-440001
(d)Legal Status of the Company Central PSU
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Kaushik Chakraborty
(b)Designation (Owner/ Partner/ CEO) G.M (MINING)/ ENVIRONMENT.
(c)Address NIL
(d)Pin code 440001
(e)E-mail gmenvironment.wcl@coalindia.in
(f)STD Code. 712(f)Telephone No. 2510151
(g)Fax No. 2510151
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity1(a) Mining of minerals
Minor Activity2(b) Mineral beneficiation
(b)Category A
(c)Proposal Number IA/MH/CMIN/108663/2019
(d)Master Proposal Number(Single Window) SW/108657/2019
(e)EAC concerned (for category A Projects only) Coal Mining
(f)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Latitudes : 21° 19' 29'' N to 21° 21' 4'' N Longit
(b)Pincode 441107
(c)Bounded Latitudes (North)
From
Degree 21.32472222
Minutes
Second
From
Degree 21.35111111
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 78.94111111
Minutes
Second
From
Degree 78.97944444
Minutes
Second
(e)Survey of India Topo Sheet No. 55 K/15
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 313.75
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 0.1
(j)Seismic Zone 2
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Maharashtra
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number J-11015/387/2015.IA-II(M)
(c)Date of Issue of TOR 19 Jun 2019
(f)Previous TOR Letter Copy of Previous TOR letter
(b)Date of Apply of EC 19 Sep 2019
(c)Date of Issue of EC 03 Feb 2020
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :05 Jan 2019
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :06 Feb 2019
Distance of Public Hearing Venue from the Proposed Project :0
Mine manager Office, Adasa UG Mine, Kotodi Village, PO – Patkhakhedi, Tahsil-Saoner, Nagpur
State :Maharashtra
District :Nagpur
Tehsil :Savner
Village :Kotodi
200Employement, Health Facility, Compensation against land, etcOthersADM
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Nagpur
(iii)Letter No. 3-6/2012(ENV)
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit Sep 16 2016 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Coal0.501.351.85OthersMillion tonnes per annumRail
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)Coal MineUnderground mineOpencast mineOpencast mine
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 08 Jun 2017
(iv)Valid Upto 31 Jan 2021
(v)File No. BO/JD(APC)/UAN NO. 2082/CC-1706000437 DATED 08.06.
(vi)Application No. UAN NO. MPCB-CONSENT-2082 dated 29.03.2016
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 333.4393
(b) Funds Allocated for Environment Management (Capital) (in Crores) 22.0919
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 2.33
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 1.11
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 1.35
(b)Existing quantity of raw material/fuel 0.50
(c)Total quantity of raw material/fuel 1.85
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Diesel656757OthersLitreIOCRoad10 Fuel Supply AgreementCopy of Linkage
(2.)Explosives4718667OthersKg/yearCIL approved vendorsRoad10 Fuel Supply AgreementCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Oct 2016 To 31 Dec 2016
(b)Season Post-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 6
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube714670.5100
(2.)SO2Micro Gram per Meter Cube15.211.515.280
(3.)OthersNilNA0000
(4.)PM2.5Micro Gram per Meter Cube452544.560
(5.)NOxMicro Gram per Meter Cube25.314.225.280
    14.2.     No. of Ground Water monitoring locations : 2
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA7.37.16.58.5
(2.)TDSmg/l4704605002000
(3.)Total HardnessOthersmg/L as CaCo327026075200
(4.)Heavy MetalsZincOthersZn0.30.255.015
(5.)OthersSulphateOthersSO46055200400
(6.)TSSmg/l181600
(7.)FluorideOthersas F0.50.31.01.5
(8.)ChloridesOthersas Cl25202501000
    14.3.     No. of Surface Water monitoring locations : 2
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHOthersNA7.77.6C
(2.)DOOthersNA6.86.4C
(3.)BODmg/l2.82.0C
(4.)CODmg/l6.56.4C
(5.)OthersChloridesmg/l7065C
    14.4.     No. of Ambient Noise monitoring locations : 6
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))53.750.155
(2.)Leq(Night)A-weighted decibels(dB(A))46.245.245
    14.5.     No. of Soil Sample Monitored locations : 3
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)N(Nitrogen)Kilogram per hectare320.1315.5
(2.)P(Phosphorus)Kilogram per hectare22.320.1
(3.)K(Potassium)Kilogram per hectare155.2148.7
(4.)pH6.66.2
(5.)Electric ConductivityOthersm-mhos/cm at 20 degree celcius0.650.62
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 14.55 To 8.20
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 14.35 To 7
(c)Whether Ground Water Intersection will be there ? Yes
(d)Upload Copy of Central Ground Water Authority Letter Copy of Central Ground Water Authority Letter
(e)Letter No. 21-4/812/MH/MIN/2017 (Application under process))
(f)Date of Issue 27 Feb 2017
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersMine water36400Copy of Permission LetterPipelineOthersMine water21-4/812/MH/MIN/2017 (Application under process))27 Feb 20173640
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Mine discharge9735.09735.0SedimentationDischarge into Surface Water Body,Reuse within the Plant & Recycling36406095
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 9735
(b)Total Discharged Water (Kilolitre per Day) 6095
(c)Total Reused Water (Kilolitre per Day) 3640
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Over BurdenOthersOver burden qantity in Million cubic meter11.60Tons0.8OthersInternal Haul roadsOthersInternal backfilling
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM2.5Microgram per Meter Cube44.51.91.0845.5960
(2.)SO2Microgram per Meter Cube0000.10
(3.)NOxMicrogram per Meter Cube0000.10
(4.)PM10Microgram per Meter Cube57.61.831.4989.56100
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)Not ApplicableNot Applicable00NOx0
(2.)Not ApplicableNot applicable00PM100
(3.)Not applicableNot applicable00SO20
(4.)Not ApplicableNot applicable00OthersNA0
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 1444
(b)Source MSEDCL
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 0
(e)Stack Height (in m) 0
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 534.49
(c)Government Land (ha.) 29.92
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 30.0
    Total Land (ha.) 594.41
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 534.49
(b)Waste/Barren Land (ha.) 29.92
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 0
(e)Settlements (ha.) 0
(f)Industrial (ha.) 0
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : land for Rehabilation of villages 30.0
    Total (ha.) 594.41
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Quarry Area287.58
(2.)OB Dump Area85.0External OB Dump area
(3.)Main Plant12.0Infrastructure
(4.)OthersEmbankment24.0
(5.)Safety Zone152.83Area needed for rationalization and blasting zone
(6.)Township3.0Roads
(7.)Built Up Area30.0land for Rehabilation of villages
Total (ha.) 594.41
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaNot Applicable0Not falls in Critically Polluted areas
(2.)CorridorsNot Applicable0Nil
(3.)WLSNot Applicable0Nil
(4.)Wildlife CorridorsNot Applicable0Nil
(5.)ESAsNot Applicable0Nil
(6.)NPANot Applicable0Nil
(7.)ESZsNot Applicable0Nil
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Archaeological SitesNot Applicable0Nil
(2.)Defence InstallationsNot Applicable0Nil
(3.)ForestNot Applicable0Nil
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) Not Applicable
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 12.66
(b)Land yet to be acquired(Ha) 581.75
(c)Status of Land acquisition if not acquired under progress
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 2
(b)No. of Households 474
(c)No. of PDFs (Project Displaced Families) 474
(d)No. of PAFs (Project Affected Families) 797
(e)Funds Allocated for R&R(in INR) (in Lacs) 9433
(f)Status of R&R Yet To Start
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? Yes
(i)Details of Water Bodies in Core Area In the dip side (south side) of Adasa block property, a seasonal nalla is passing through coal bearing area, which is required to be diverted to release coal. Provision of Rs 10.71 crore has been made for diversion of seasonal nalla passing through Adasa block along dipside quarry boundary of proposed Adasa UG to OC.
(b)Whether there is Diversion Required ? Yes
(i)Details of Diversion Required In the dip side (south side) of Adasa block property, a seasonal nalla is passing through coal bearing area, which is required to be diverted to release coal. Provision of Rs 10.71 crore has been made
(ii)Details of Study Conducted Yet to be conducted. CDO Nasik has been requested
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Chandrabhaga Nadi (Seasonal nallah) Kolar River Kanhan River
(ii)Direction of Water Bodies in Buffer Area West
(iii)Distance of Water Bodies in Buffer Area 1.50
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 155
(b)Permanent Employment-During Operation 155
(c)Temporary Employment- During Construction 70
(d)Temporary Employment- During Operation 70
(e)No. of working days 330
(f)Total Manpower 450
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt1.0360.03361.03
(2.)No. of Plants2500900080902580
(3.)Percentage of Total Project Area0.2799.73100
(4.)Funds Allocated02.332.33
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialThe project will lead to development of roads, ancillary industries, Improvement in social & living standards by providing opportunities of direct & indirect employment to local community
(2.)EnvironmentalConservation of coal. Also it will lead to positive environmental impacts like green cover, mine water utilization , etc.
(3.)FinancialA substantial percentage of population is dependent on mining industry directly or indirectly. Because of this mining project some of the local population may take direct employment but a substantial impact will be on creation of indirect job opportunities and employment.
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For Coal Mining
S. No.Item Details
     1.       No. of Mineral(s) to be Mined : 1
S. No.Mineral(s) to be Mined Major or Minor Mineral
(1.)CoalMajor
(2.)CoalMinor
2.
Mine Capacity in ROM (Run of Mine) 1.85
3.
Uploaded 500 meters Cluster Certificate from State Mines and Geology in case of minor minerals Copy of 500 meters Cluster Certificate from State Mines and Geology
4.
Mining Plan:
(a)Approval Letter No. WCL/BD/SECTT/BM-306/2018/731
(b)Date of Approval 24 Nov 2018
(c)Approved Letter Copy of Approved Letter
(d)Approved By State Mining and Geology Department WCL Board
(e)Approved Mining Lease Area 594.41
(f)Approved Capacity 1.85
5.
Technical Details:
(a)Total Geological Reserves (Million Ton) 29.46
(b)Mineable Reserves (Million Ton) 23.61
(c)Extractable Reserves(Million Ton) 22.06
(d)Percent(%) of Extraction 93.35
(e)Grade of Coal /Ore /Mineral G8
(f)Stripping Ratio 1 : 6.64
(g)Category of Gaseousness (Only for Coal Mining, Others may Write NA) Not applicable as it is opencast mine
(h)Average Gradient(Degree) 1 in 6.5
(i)Mining Method Opencast
(j)Life of Mine (Years) 18
6.
Details of Beneficiations:
(a)Whether it is proposed to install beneficiation plant/Coal washery within the mining lease area No
(b)Whether it is proposed to install crusher within the mining lease area Yes
(c)No. of crushers 2
     6.1.    Details of crusher:
S. No.Crusher ID Capacity (in PH)Remarks
(1.)11200
(2.)2600
7.
Details of Seams:
(a)Whether details of seam applicable Yes
(b)No. of seams 5
(c)Thickness of seams to be worked on 7.42
(d)Maximum Thickness of Seams (metres) 7.42
8.
Details of Mining Lease:
(a)Mining Lease Area (in Hectare) 594.41
(b)Whether obtained Letter of Intent (LOI) from the state government ? No
(i)Reason thereof Land acquired as per CBA, 1957
(c)Whether Lease Deed Executed ? No
(i)Reason thereof Land acquired as per CBA, 1957
(d)Whether Lease Deed Renewed ? No
(i)Reason thereof Land acquired as per CBA, 1957
9.
OB (Over Burden) Management:
(a) Details of External Dumps:
(i)No. of OB Dumps
(ii)Total Area (in Hectare)
(iii)Height (in meter)
(iv)Quantity (in Million Cubic meter)
(v)No. of year back fill up
(b) Details of Internal Dumps:
(i)No. of Internal Dumps
(ii)Total Area (in Hectare)
(iii)Height (in meter)
(iv)Quantity (in Million Cubic meter)
10.
Details of Topsoil Management:
(a)Quantity of Topsoil excavated during the entire life of the mine (in Million Cubic metre) 21.50
(b)Quantity of Topsoil proposed for utilization for reclamation during the entire life of the mine (in Million Cubic metre) 21.50
(c)Quantity of Topsoil proposed for utilization for other activities during the entire life of the mine (in Million Cubic metre) 0
11.
Details of Final Mine Void:
(a)Area (in Hectare)
(b)Depth (in meter)
(c)Volume (in Million Cubic meter)
12.
Details of Quarry:
(a)Final Void of 139.55 (hectare) at a Depth of 114 meter which is Proposed to be Converted into a Water Body.
(b)Total Quarry Area (ha) 287.58
13.
Details of Transportation:
(a)In Pit/Underground to Surface Dumper
(b)Surface to Siding/Loading tipper
(c)Transportation / Conveyor Details Road transportation, Rail
     14.      Details of Land Usage (Pre-Mining)
S. No.LAND USE Other LAND USEWITHIN ML AREA (Hectare)OUTSIDE ML AREA (Hectare)TOTAL (Hectare)
(1.)OTHERS(Specify)Government land29.92029.92
(2.)SETTLEMENTS000
(3.)GRAZING LAND000
(4.)WASTE LAND000
(5.)FOREST LAND000
(6.)AGRICULTURE LAND534.490534.49
(7.)SURFACE WATER BODIES000
TOTAL564.410564.41
     15.      Details of Land Usage (Post-Mining)
S. No.LAND USE Other LAND USEPlantation (ha)Water Body (ha)Public Use (ha)Undisturbed (ha)Total
(1.)GREEN BELT0000
(2.)INTERNAL OB DUMPS0000
(3.)BUILT UP AREA (COLONY/OFFICE)1089
(4.)EXCAVATION/QUARRY148.03139.550287.58
(5.)TOP SOIL STORAGE0000
(6.)ROADS1023
(7.)VIRGIN AREA120035.83155.83
(8.)EXTERNAL OB DUMPS85.00085
(9.)OtherEmbankment601824
TOTAL361.03139.5563.830564.41
16.
Details of Reclamation:
Total Afforestation Plan shall be Implemented Covering of Mining.
This will Include:
(a)External OB Dump(in hectare) 85.0
(b)Internal Dump(in hectare) 148.03
(c)Quarry(in hectare) 287.58
(d)Safety Zone(in hectare) 152.083
(e)Final Void of 139.55 (hectare) at a Depth of 114 meter which is Proposed to be Converted into a Water Body.
(f)Density of Tree Plantation per ha (in no.) 2500
(g)Others in ha (such as Excavation Area along ML Boundary, along Roads and Infrastructure, Embankment Area and in Township Located Outside the Lease etc) 66
(h)Total afforestation plant (in hectare) 361.03
17.
Status of progressive Mining Closure Plan:
Copy of Implementation of Various Activities as per Approved Progressive Mine Closure Plan Copy of Implementation of Various Activities as per Approved Progressive Mine Closure Plan
Any Deviation from the Approved Progressive Mine Closure Plan No
Total Area Excavated (in hectare) 0
Total Area Backfilled after Excavation (in hectare) 0
Total Area Reclaimed (in hectare) 0
     18.      Details of Actual Coal/ ORE Production vis-a-vis Sanctioned Capacity since the Inception:
S. No.Financial Year Sanctioned Capacity as per EC (MTPA)Sanctioned Capacity as per CTOSanctioned Capacity as per approved mining planActual Production Excess Production Beyond the EC / CTO/ Mining Plan Sanctioned Capacity (MTPA)
(1.)20120.50.50.50.3180
(2.)20130.50.50.50.3240
(3.)20150.50.50.50.3040
(4.)20110.500.500.500.2910
(5.)20140.50.50.50.3190
(6.)20170.50.50.50.1390
(7.)20180.500.500.500.0960
(8.)20090.50.50.50.2860
(9.)20100.500.500.500.2870
(10.)20160.50.50.50.2440
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1720/RA 0092
(ii)Name of the EIA Consultant CMPDI
(iii)Address Gondwana Place, Kanke Road, Ranchi-834031
(iv)Mobile No. 6512231850
(v)Landline No. 0651223185
(vi)Email Id Gmenv.cmpdi@coalindia.in
(vii)Category of Accreditation A
(viii)Sector of Accreditation Coal Mining
(ix)Validity of Accreditation 01 Oct 2020
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAPresent CTO dated 8/6/2017 is for production capacity of 0.21 MTPA (UG) in an area of 1554.36 ha. Please inform about the CTO for UG capacity of 0.5 MTPA against EC dated 15/7/2009 granted by the Ministry. 11 Aug 2019
2.NAThe correction have been made as per the instruction received 13 Aug 2019
3.NAYou are requested to submit the following information 1. The green belt plan submitted in the form-2 is not proper. You are requested to submit the green belt plan showing the complete details 2. Kindly refer to the page no. (ii) of the EMP report, it was mentioned that the ATR of the public hearing is given at annexure-VIII. But there is no such annexure attached. Therefore, you are requested to provide time bound action plan for the issues raised during the public consultation along with the budgetary provisions 3. May kindly refer to the Chapter-7, the details regarding public consultation is not complete. Integration of the of the issues raised in the public consultation in the EMP. 4. Signatures of the participants attended during the public hearing 5. Mining plan approval for the proposed capacity i.e. 1.675 MTPA in place of the 1.5 MTPA submitted with the application 6. Action taken report on the non-compliance and partial compliance reported in the certified compliance report dated 22.11.2016 7. May kindly refer to the chapter-8, the project benefits provided is generic in nature. You are requested to provide social and environmental benefits by the project inter alia including fund provision for CER along with the proposed activities based on the issues raised during the PH in complaince with the Ministry's OM dated 1st May 2018. 18 Sep 2019
4.NAThe correction have been made as per the instruction received 19 Sep 2019
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1. ADS Reply LetterPlease find attached herewith, the detailed compliance report against the 49th EAC meeting's directives held on 22.10.2019. This is submitted for your kind perusal. 19 Nov 2019
2.NA

ok

11 Nov 2019
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantKaushik Chakraborty
DesignationG.M (MINING)/ ENVIRONMENT.
Name of Company (Applicant Name should not be given here)Western Coalfields Limited
AddressCoal Estate Civil lines, Nagpur-440001
Print