Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Urmila Chemopharma Pvt. Ltd.
(b)Name of the Company / Organisation URMILA CHEMOPHARMA PRIVATE LIMITED
(c)Registered Address Plot No.: F-24, MIDC Chincholi Industrial area, Chincholi village, Mohal Taluk,Solapur District, Maharashtra state,Solapur,Maharashtra-413255
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Chinnabutchiraju Shriramarajulolabhattu
(b)Designation (Owner/ Partner/ CEO) ManagingDirector
(c)Address Plot No. F-24, MIDC Chincholi Industrial area, Chincholi village,,Mohol,Solapur,Maharashtra-413255
(d)Pin code 413255
(e)E-mail urmilachemopharma@gmail.com
(f)STD Code. 8421(f)Telephone No. 447101
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
Minor Activity
(b)Category A
(c)Proposal Number IA/MH/IND2/108626/2018
(d)Master Proposal Number(Single Window) SW/108624/2019
(e)EAC concerned (for category A Projects only) Industrial Projects - 2
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Plot No.: F-24
(b)Pincode 413255
(c)Bounded Latitudes (North)
From
Degree 17
Minutes
Second
From
Degree 17
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 75
Minutes
Second
From
Degree 75
Minutes
Second
(e)Survey of India Topo Sheet No. 47 O/9, 10, 13 and 14
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 476
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 6.7
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Maharashtra
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number IA-J-11011/345/2018-IA-II(I)
(b)Date of Apply of TOR 24 Oct 2018
(c)Date of Issue of TOR / Standard ToR 01 Apr 2019
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason Located in Notified Industrial Estate - MIDC Chinc
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)D G Set1 x 125 KVA
(2.)Coal Fired Boiler2.0 TPH
(3.)Cooling Tower1 x 150 TR
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)3-Carbamoylmethyl-5-Methyl-hexanoic acid5.0OthersMT/ MonthRoad
(2.)3,5 Dimethyl 4–Nitro pyridine – N-Oxide5.0OthersMT/ MonthRoad
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 2.5
(b) Funds Allocated for Environment Management (Capital) (in Crores) 0.56
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.05
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.11
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? Yes
a)Protected areas notified under the wildlife (Protection) Act, 1972 Yes
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 100
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 100
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Hydrogen peroxide (50%)30Tons per AnnumWithin the countryRoad10 LinkageCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Mar 2019 To 31 May 2019
(b)Season Summer
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube65.15364100
(2.)PM2.5Micro Gram per Meter Cube29.522.129.460
(3.)NOxMicro Gram per Meter Cube23.819.723.780
(4.)SO2Micro Gram per Meter Cube16.412.316.380
(5.)OthersCOMili Gram per Meter Cube0.880.110.872.0
    14.2.     No. of Ground Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA8.047.346.58.5
(2.)TSSmg/l0000
(3.)Total Hardnessmg/l536183200600
(4.)Chloridesmg/l232482501000
(5.)Fluoridemg/l0.50.511.5
(6.)TDSmg/l9452805002000
(7.)Heavy MetalsZincmg/l0.50.5515
    14.3.     No. of Surface Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)BODmg/l10.24.8E
(2.)CODmg/l2512E
(3.)DOmg/l5.85.0E
(4.)pHNA8.097.16E
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))66.140.375
(2.)Leq(Night)A-weighted decibels(dB(A))54.33270
    14.5.     No. of Soil Sample Monitored locations : 8
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pH8.427.32
(2.)N(Nitrogen)Kilogram per hectare1.461.16
(3.)Electric ConductivityMillisiemens per Centimetre0.5450.112
(4.)P(Phosphorus)Kilogram per hectare15.410.6
(5.)K(Potassium)Kilogram per hectare43.3414.18
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 20 To 40
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 15 To 36
(c)Whether Ground Water Intersection will be there ? NA
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersMIDC Water supply35.4310 Not Appliacble PipelineOthersPipelineNA01 Apr 201935.43
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Process and Domestic10.8215ZLD SystemReuse within the Plant & Recycling,Green Belt Renewal Plant10.82
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 10.82
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 10.82
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Spent CarbonHazardous Waste (as per Hazardous and Other Waste Management rules 2016)0.9Tons10RoadOthersWill be sent to Cement Industry
(2.)MEE SaltsHazardous Waste (as per Hazardous and Other Waste Management rules 2016)59.1Tons10RoadTreatment, Storage and Disposal Facility(TSDF)
(3.)Used OilsHazardous Waste (as per Hazardous and Other Waste Management rules 2016)0.5Kilolitre10RoadAuthorized Recyclers
(4.)Ash from BoilerBottom Ash840Tons10RoadOthersWill be sent to Brick Manufacturers
(5.)Organic distillate from stripperHazardous Waste (as per Hazardous and Other Waste Management rules 2016)9.0Tons10RoadOthersWill be sent to Cement Industry
(6.)ETP SludgeHazardous Waste (as per Hazardous and Other Waste Management rules 2016)15Tons10RoadTreatment, Storage and Disposal Facility(TSDF)
(7.)Organic Solid WasteHazardous Waste (as per Hazardous and Other Waste Management rules 2016)40.2Tons10RoadOthersWill be sent to Cement Industry
(8.)Solvent Distillation ResidueHazardous Waste (as per Hazardous and Other Waste Management rules 2016)3.0Tons10RoadOthersWill be sent to Cement Industry
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube640.050.464.41100
(2.)PM2.5Microgram per Meter Cube29.40.050.129.5160
(3.)SO2Microgram per Meter Cube16.30.050.8517.15180
(4.)NOxMicrogram per Meter Cube23.70.051.5525.25180
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)Coal Fired BoilerCoal200.3SO20.59
(2.)Coal Fired BoilerCoal200.3NOx1.22
(3.)Coal Fired BoilerCoal200.3PM100.13
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 200
(b)Source Maharashtra State Electricity Distribution Company
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 1 x 125 KVA
(e)Stack Height (in m) 8.0
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 0
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0.6
    Total Land (ha.) 0.6
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 22419.6
(b)Waste/Barren Land (ha.) 3705.2
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 1193.2
(e)Settlements (ha.) 910.6
(f)Industrial (ha.) 2135.2
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : Bird Sanctuary 1036.2
    Total (ha.) 31400
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Main Plant0.6
Total (ha.) 0.6
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaNA0NA
(2.)ESAsNA0NA
(3.)WLSGreat Indian Bird Sanctuary, Kondi (Gat no. 104)2.45Wildlife application submitted to Standing Committee of NBWL/ SBWL which is under process
(4.)CorridorsNA0NA
(5.)NPANA0NA
(6.)ESZsNA0NA
(7.)Wildlife CorridorsNA0NA
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Defence InstallationsNA0NA
(2.)ForestNA0Na
(3.)Archaeological SitesNA0NA
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? Selec
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) Not Applicable
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 0.6
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired NA
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Yet To Start
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Sina River
(ii)Direction of Water Bodies in Buffer Area South West
(iii)Distance of Water Bodies in Buffer Area 6.7
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 65
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 0
(e)No. of working days 300
(f)Total Manpower 65
32.
Green Belt in Ha:
(a)Total Area of Green Belt 0.2148
(b)Percentage of Total Project Area 35.80
(c)No. of Plants to be Planted 360
(d)Funds Allocated for Plantation 400000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialEmployment generation to local people
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1821/RA 0100
(ii)Name of the EIA Consultant Rightsource Industrial Solutions Pvt. Ltd.
(iii)Address Plot No: 203, H.No:5-36/203, Prashanthi Nagar, IDA, Kukatpally, Hyderabad
(iv)Mobile No. 9885560011
(v)Landline No. 0402307569
(vi)Email Id info@rightsource.co.in
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 25 Feb 2021
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAApplicability of general condition (Project site at 2.45 km from the nearest boundary of WLS) needs to be established along with supporting documents duly certified by the concerned regulatory authority. Please inform about other industrial units operating at the same premises. 27 Jul 2019
2.NAThe correction have been made as per the instruction received 01 Aug 2019
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantChinnabutchiraju Shriramarajulolabhattu
DesignationManagingDirector
Name of Company (Applicant Name should not be given here)URMILA CHEMOPHARMA PRIVATE LIMITED
AddressPlot No.: F-24, MIDC Chincholi Industrial area, Chincholi village, Mohal Taluk