Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) MARINE SYNDICATE PVT.LTD.
(b)Name of the Company / Organisation MARINE SYNDICATE LTD
(c)Registered Address Neelshri Thiba palace Read Ratnagiri i,,Ratnagiri,Maharashtra-415612
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Dilip Bhatkar
(b)Designation (Owner/ Partner/ CEO) Director
(c)Address Marine Syndicate Pvt. Ltd. Neelshri Thiba palace Road Ratnagiri,,Ratnagiri,Ratnagiri,Maharashtra-415612
(d)Pin code 415612
(e)E-mail marinesyndicate1@gmail.com
(f)STD Code. 2352(f)Telephone No. 223814
(g)Fax No. 270232
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity7(b) All ship breaking yards including ship breaking units
Minor Activity
(b)Category A
(c)Proposal Number IA/MH/MIS/27767/2015
(d)Master Proposal Number(Single Window) SW/108078/2019
(e)EAC concerned (for category A Projects only) INFRA-1
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. S. No. 41 & 42, H. No. 18 & 19/1
(b)Pincode 415613
(c)Bounded Latitudes (North)
From
Degree 17.290526
Minutes
Second
From
Degree 73.276691
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 17.289443
Minutes
Second
From
Degree 73.279753
Minutes
Second
(e)Survey of India Topo Sheet No. E43N3 E43N7 E43N4 E43N8
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 49
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 15
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Maharashtra
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)MaharashtraRatnagiriGuhagar
(2.)SikkimManganMangansalim pakyel
6.
Details of Terms of Reference (ToR):
(a)Whether TOR is mandatory for submitting application Yes
(b)MoEF&CC / SEIAA File Number 11-17/2015-IA-III
(c)Date of Apply of TOR 20 May 2015
(d)Date of Issue of TOR / Standard ToR 12 Nov 2015
(e)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :04 Aug 2018
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :05 Sep 2018
Distance of Public Hearing Venue from the Proposed Project :9.5
Lokshikshan Mandal Abloli, Sabhagruh,Gonbarewadi, Khodade
State :Maharashtra
District :Ratnagiri
Tehsil :Guhagar
Village :Katale
150During the Public hearing all the people were in favor of the project. But some of the issues discussed by the by the local people related to the proposed activity such as Employment should be given tOthersAdditional District Magistrate
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Ship breaking Facility-10-15 Ships breaking per year
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Ship Barges breaking15OthersNoOthersSEA
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 2.43
(b) Funds Allocated for Environment Management (Capital) (in Crores) 0.66
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.048
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.35
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 00
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 0
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)NA00OthersNot Applicable--OthersSea0 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Oct 2016 To 31 Dec 2016
(b)Season Post-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 5
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM2.5Micro Gram per Meter Cube27.820.227.360
(2.)PM10Micro Gram per Meter Cube62.244.261.1100
(3.)SO2Micro Gram per Meter Cube10.68.110.280
(4.)NOxMicro Gram per Meter Cube15.611.915.580
(5.)OthersCOMicro Gram per Meter Cube0.30.10.30.4
    14.2.     No. of Ground Water monitoring locations : 2
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA7.387.248.58.5
(2.)TDSmg/l2342225002000
(3.)Total Hardnessmg/l198185200600
(4.)OthersTotal ColiformOthersMPN/100ml0000
(5.)Fluoridemg/l0.00020.00011.01.5
(6.)Chloridesmg/l74.660.82501000
(7.)TSSmg/l8500
    14.3.     No. of Surface Water monitoring locations : 3
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)CODmg/l10.29.4B
(2.)pHNA8.88.5B
(3.)BODmg/l2.82.4B
(4.)DOmg/l5.84.2B
    14.4.     No. of Ambient Noise monitoring locations : 5
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))53.640.355
(2.)Leq(Night)A-weighted decibels(dB(A))42.637.145
    14.5.     No. of Soil Sample Monitored locations : 2
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)P(Phosphorus)Milligram per Kilogram23.49.0
(2.)Electric ConductivityMillisiemens per Centimetre24001600
(3.)K(Potassium)Milligram per Kilogram768681
(4.)pH8.047.11
(5.)N(Nitrogen)Milligram per Kilogram176124
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 12 To 30
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 12 To 6
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)Otherswell water +Tanker water105 Not Appliacble PipelineOpen WellNA22 May 201910
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)ETP (for Bilge and slop water)810Equalisation tank + Primary settling tank + Aerobic Treatment (SAFF or FAB media and fine bubble diffuser membranes)+ Final Settling Tank + Disinfection+ Multi grade Sand Filter & Activated Carbon FilterReuse within the Plant & Recycling8
(2.)STP (for Domestic sewage)4.310Phytorid technologyReuse within the Plant & Recycling4.3
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 12.3
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 12.3
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Municipal Solid WasteMunicipal Solid Waste32.49Tons00OthersWithin PremisesOthersVermicomposting
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)SO2Microgram per Meter Cube00000000180
(2.)PM10Microgram per Meter Cube62.221.563.8100
(3.)NOxMicrogram per Meter Cube000000000180
(4.)PM2.5Microgram per Meter Cube0000000000160
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)DG SetHSD 42 Lit/hr10.1SO20.62
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 200
(b)Source MSEB
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 250kVA
(e)Stack Height (in m) 4.5
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 00
(b)Private Land (ha.) 2.9
(c)Government Land (ha.) 00
(d)Revenue Land (ha.) 00
(e)Other Land (ha.) 00
    Total Land (ha.) 2.9
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 11271
(b)Waste/Barren Land (ha.) 10859
(c)Grazing/ Community Land (ha.) 00
(d)Surface Water Bodies (ha.) 6194
(e)Settlements (ha.) 1886
(f)Industrial (ha.) 00
(g)Forest (ha.) 675
(h)Mangroves (ha.) 15.73
(i)Marine Area (ha.) 48
(j)Others (ha.) : Fallow Land 1131
    Total (ha.) 32079.73
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Main Plant2.9No
Total (ha.) 2.9
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)WLSNo00NA
(2.)ESAsNo00NA
(3.)Critically Polluted AreaNo00NA
(4.)NPANo00NA
(5.)CorridorsNo00NA
(6.)ESZsNo00NA
(7.)Wildlife CorridorsNo00NA
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestNo00NA
(2.)Defence InstallationsNo00NA
(3.)Archaeological SitesNo00NA
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 00
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 2.9
(b)Land yet to be acquired(Ha) 00
(c)Status of Land acquisition if not acquired NA
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 00
(b)No. of Households 00
(c)No. of PDFs (Project Displaced Families) 00
(d)No. of PAFs (Project Affected Families) 00
(e)Funds Allocated for R&R(in INR) (in Lacs) 00
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? Yes
(i)Details of Schedule-I Species 3 birds species and 1 butterfly species recorded in study area
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Kalzondi reservoir
(ii)Direction of Water Bodies in Buffer Area South
(iii)Distance of Water Bodies in Buffer Area 9.4
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 15
(b)Permanent Employment-During Operation 65
(c)Temporary Employment- During Construction 00
(d)Temporary Employment- During Operation 00
(e)No. of working days 150
(f)Total Manpower 80
32.
Green Belt in Ha:
(a)Total Area of Green Belt 1
(b)Percentage of Total Project Area 34.48
(c)No. of Plants to be Planted 350
(d)Funds Allocated for Plantation 350000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.       Project Benefits
S. No. Type of Project BenefitsDetails of Project Benefits
NIL
   34.   CRZ Specific Details
S. No.Item Details
1.
Project Details:
(a)CRZ Classification IB
(b)Location Type Non-Eroding Coast
(c)Details of Mangroves Land Involved, if Any There are no mangroves at the project site
(d)Area of Mangroves Land (hectare) 0
(e)EIA (Terrestrial) Studies Carried Out
(i)Summary Details of EIA (Terrestrial) Studies Included in EIA Report
(ii)Uploaded Recommendation made in EIAs Copy of Recommendation made in EIAs
(iii)Period of Study from (EIA Terrestrial) 01 Oct 2016
(iv)Period of Study To (EIA Terrestrial) 31 Dec 2016
(f)EIA (Marine) Studies Carried Out
(i)Summary Details of EIA (Marine) Studies Included in EIA
(ii)Uploaded Recommendation made in EIAs Copy of Recommendation made in EIAs
(iii)Period of Study from (EIA Marine) 01 Oct 2016
(iv)Period of Study to (EIA Marine) 24 Dec 2016
(g)Disaster Management Plan/National Oil Spill Disaster Contigency Plan Included in EIA Report
2.
Description of the Project Under Consideration:
(a)Type of Project Others
(i)Agency Name for Preparing CRZ Maps Institute of Remote Sensing, Chennai
(ii)Please Specify with salient features It is a new project of ship breaking facility by M
(iii)Uploaded relevent Document Copy of relevent Document
3.
Distance of Project (in meters) from ltl/htl to be stated :
(a)Clause of CRZ Notification Under which the Project is a Permissible/Regulated Activity IB
(b)Whether CRZ Map Indicating HTL,LTL Demarcation in 1:4000 Scale Prepared? Yes
(i)Distance of Project (in meters) from HTL to be Stated Site is abutting to HTL
(ii)Uploaded Maps(Shape File) Copy of Maps
(iii)Distance of Project(in meters) from LTL to be Stated Site is abutting to HTL
(iv)Uploaded Maps(Shape File) Copy of Maps
(c)Whether Project Layout Superimposed on CRZ Map 1:4000 Scale ? Yes
(i)Uploaded Maps (Shape File) Copy of Maps
(d)Whether CRZ Map 1:25000 Covering 7 km Radius Around Project Site Prepared ? Yes
(i)Uploaded Maps (Shape File) Copy of Maps
(e)Whether CRZ Map Indicating CRZ-I,II,III and IV Including Other Notified ESAs Prepared Yes
(i)Uploaded Maps (kml File) Copy of Maps
(f)NOC from State Pollution Control Boards Obtained No
(g)Details of Rain Water Harvesting System
4.
Recommendation of State Coastal Zone Management Authority:
(a)Copy of CZMA Copy of CZMA
(b)State the Conditions Imposed NA
(c)Social and Environmental Issues and Mitigations Measures Suggested Including but not Limited to R&R, Water, Air, Hazardous Wastes, Ecological aspects, etc. (Brief Details to be Provided) NA
   35.   Sector Specific Details For INFRA-1
S. No.Item Details
1.
Details of Building Construction:
(a)Maximum Height of the Building (Meters) 6
(b)Total No. of Flats to be Build 00
(c)No. of Buildings 1
(d)Total plot area (sqm) 29030
(e)Total built up area (sqm) 400
2.
Foreshore Facilities and/or Marine Disposal:
(a)Whether Project Involves Foreshore Activities and/or marine Disposal? No
3.
Rain Water Harvesting:
(a)No. of Storage 1
(b)Capacity 15
(c)No. of Recharge Pits 00
(d)Capacity 00
4.
Parking:
(a)Details of 4 Wheeler/ 2 Wheeler Parking 2W: 16 Nos., 4W: 8 Nos, Truck: 3 nos
5.
Energy Saving Measures:
(a)Source/Mode LEDs, Energy efficient pumps, motors etc.
(b)Percentage 10
(c)Quantity 0
6.
Other details:
(a)Details of impact on Water Bodies and Drainage patters of catchment area -
(b)Details of Traffic Density Impact Assessment and Modelling Study Copy of Details of Traffic Density Impact Assessment and Modelling Study
(c)In case Underground Tunnel Project below the Forest Land - Subsidence Impact Study report Copy of Underground Tunnel Project below the Forest Land - Subsidence Impact Study report
     7.       Type of Industries to be established with Industrial Estate as per their category A/B
S. No.Type of IndustryNo. of UnitsCategory A/B
NIL
8.
Length of the alignment N/A
9.
Details Bridges/ROB/Interchanges,Flyovers,Vehicle Underpass and Pedestrian Underpass
Details Not Applicable
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. QCI/NABET/EIA/ACO/17/00427 dt 09.10.2017
(ii)Name of the EIA Consultant Mahabal Enviro Engineers Pvt. Ltd.
(iii)Address Plot No.F7, Road No.21, Wagle MIDC area, Near Ashida Electronics, Thane West 400604, Maharashtra
(iv)Mobile No. 9323058368
(v)Landline No. 0222171638
(vi)Email Id dap_24@hotmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation INFRA-1
(ix)Validity of Accreditation 08 Oct 2020
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAAs per ToR letter dated 12.11.2015 para 7 of the letter, consultants involved in preparation of EIA/EMP report after accreditation with Quality Council of India/National Accreditation Board of Education and Training (QCI/NABET) would need to include a certificate in this regard in the EIA/EMP reports prepared by them and data provided by, other Organization(s)/Laboratories including their status of approvals etc. vide notification of the MoEF dated 19.07.2013. However, no details regarding consultant has been given in Form-2. Kindly submit the same. Also clarify that whether the project is new or expansion. As per information submitted in Form-2 project is fresh while CER plan has been submitted for brown field project. In case project is expansion, Certified Compliance Report issued by the MoEF&CC, Regional Office or concerned regional office of Central Pollution Control Board or the Member Secretary of the respective State Pollution Control Board is required to be submit. 09 Sep 2019
2.NAThe correction have been made as per the instruction received 11 Sep 2019
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1. ADS Reply LetterMCZMA Recommendation letter is attached 14 Oct 2020
2.NAIn this context, it is to submit that the proposal was sent to CRZ Section of this Ministry to seek their comments prior to appraisal for grant of composite EC and CRZ Clearance. The CRZ section has returned the proposal with remarks that ‘Recommendation Letter from Maharashtra CZMA is required, which is a prerequisite as per the CRZ Notification’. It is requested to provide copy of recommendation letter of Maharashtra CZMA. 12 Jun 2020
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantDilip Bhatkar
DesignationDirector
Name of Company (Applicant Name should not be given here)MARINE SYNDICATE LTD
AddressNeelshri Thiba palace Read Ratnagiri
Print