Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) SUNDARAM ALLOYS LIMITED
(b)Name of the Company / Organisation SUNDARAM ALLOYS LIMITED
(c)Registered Address PLOT NO.13 & 13/A, APSEZ,,ATCHUTHAPURAM (Village & Mandal),Visakhapatnam,Andhra Pradesh-531011
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant KV RAO
(b)Designation (Owner/ Partner/ CEO) DIRECTOR
(c)Address PLOT NO.13, APSEZ, ATCHUTHAPURAM VILLAGE AND MANDAL,,Atchutapuram,Visakhapatnam,Andhra Pradesh-531011
(d)Pin code 531011
(e)E-mail kvrao@sundaramalloys.com
(f)STD Code. 0(f)Telephone No. 00000000
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity3(a) Metallurgical industries (ferrous & non ferrous)
Minor Activity
(b)Category A
(c)Proposal Number IA/AP/IND/107176/2019
(d)Master Proposal Number(Single Window) SW/107174/2019
(e)EAC concerned (for category A Projects only) NIL
(f)Project Type Change of Product Mix under para 7(ii)
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Plot No.13 & 13A, APSEZ
(b)Pincode 531011
(c)Bounded Latitudes (North)
From
Degree 17.516482
Minutes
Second
From
Degree 17.519497
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 82.957309
Minutes
Second
From
Degree 82.959850
Minutes
Second
(e)Survey of India Topo Sheet No. 65 K/14
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 13
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 5.6
(j)Seismic Zone 2
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Andhra Pradesh
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR)/EC: Not Applicable
4.
Whether the Project Exempted from Public Hearing? Details Not Applicable
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Chennai
(iii)Letter No. EP/12.1/2011-12/52/AP/0550
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit Feb 1 2019 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Fe-Cr07500075000Tons per Annum(TPA)Road
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)SEAF5x9 MVA05X9 MVARequest for permission to manufacture Ferro Chrome (Fe-Cr)
(2.)Sinter Plant90000 TPA090000 TPANo change
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 09 Mar 2019
(iv)Valid Upto 31 Jul 2019
(v)File No. APPCB/VSP/VSP/276/CFO/HO/2019
(vi)Application No. APPCB/VSP/VSP/276/CFO/HO/2019
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 0
(b) Funds Allocated for Environment Management (Capital) (in Crores) 0
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? Yes
8.(a) If any Industrial Estate/Complex / Export processing Zones /Special Economic Zones/Biotech Parks / Leather Complex with homogeneous type of industries such as Items 4(d), 4(f), 5(e), 5(f), or those Industrial estates with pre –defined set of activities (not necessarily homogeneous, obtains prior environmental clearance, individual industries including proposed industrial housing within such estates /complexes will not be required to take prior environmental clearance, so long as the Terms and Conditions for the industrial estate/complex are complied with (Such estates/complexes must have a clearly identified management with the legal responsibility of ensuring adherence to the Terms and Conditions of prior environmental clearance, who may be held responsible for violation of the same throughout the life of the complex/estate
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 150000
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 150000
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Chrome Ore150000Tons per AnnumIndigenousRoad,Rail650 Open MarketCopy of Linkage
16.
Baseline Data Not Applicable
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 2 To 5
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 2 To 4
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater2000Copy of Permission LetterPipelineTube WellSPZ/SAL/ATP/APIIC/200930 Mar 2011400
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Sanitary wastewater from Domestic Consumption1525STPOthersWill be utilized for Greenbelt development150
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 15
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 15
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Fe-Cr SlagHazardous Waste (as per Hazardous and Other Waste Management rules 2016)46000Tons0RoadOthersZigging plant for Chrome recovery
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube0000.1100
(2.)PM2.5Microgram per Meter Cube0000.160
(3.)SO2Microgram per Meter Cube0000.180
(4.)NOxMicrogram per Meter Cube0000.180
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)5x9 mva SEAFElectricity301.2PM100
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 40000
(b)Source State Grid
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 250 KVA
(e)Stack Height (in m) 7
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 0
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 8.094
    Total Land (ha.) 8.094
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 0
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 0
(e)Settlements (ha.) 0
(f)Industrial (ha.) 8.094
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : 0 0
    Total (ha.) 8.094
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Built Up Area3.035total plant Builtup area
(2.)Green belt2.671
(3.)Othersother areas2.388other areas
Total (ha.) 8.094
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaNil0None within 10 Kms. radius
(2.)WLSNil0None within 10 Kms. radius
(3.)ESAsNil0None within 10 Kms. radius
(4.)ESZsNil0None within 10 Kms. radius
(5.)CorridorsNil0None within 10 Kms. radius
(6.)Wildlife CorridorsNil0None within 10 Kms. radius
(7.)NPANil0None within 10 Kms. radius
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestPudimadaka R.F5.5NA
(2.)Defence InstallationsNone0None within 10 Kms. radius
(3.)Archaeological SitesNone0None within 10 Kms. radius
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 8.094
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired Land has already been taken on lease from APIIC
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Sharada River
(ii)Direction of Water Bodies in Buffer Area West
(iii)Distance of Water Bodies in Buffer Area 5.7
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 0
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 0
(e)No. of working days 350
(f)Total Manpower 0
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt6.60.57.1
(2.)Percentage of Total Project Area332.535.5
(3.)No. of Plants55504005950
(4.)Funds Allocated12000001000001300000
    33.       Project Benefits
S. No. Type of Project BenefitsDetails of Project Benefits
NIL
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 1
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1619/RA 026
(ii)Name of the EIA Consultant PIONEER ENVIRO LABORATORIES & CONSULTANTS PVT. LTD
(iii)Address 6-3-652, Flat # 7-3, Dhruvatara Apartments, Amrutha Estates, Erramanjil, Somajiguda, Hyderabad- 500082
(iv)Mobile No. 9440677333
(v)Landline No. 0402311427
(vi)Email Id pelcpl@yahoo.co.in
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 1
(ix)Validity of Accreditation 22 Jun 2019
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan
(b)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(c)Uploaded Cover Letter Copy of Cover Letter
(d)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(e)Uploaded Additional File NA
(f)Uploaded Updated Form1 Copy of Updated Form1
(g)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAi. Certified compliance report of RO is not accessible. ii.Environmental Appraisal report inter-alia including Pollution load calculations (Air/Water/Solid & hazardous waste/traffic) vis-à-vis with granted Environmental Clearance, AAQ modelling predicting maximum Ground Level Concentration vis-à-vis with GLCmax for which Environmental Clearance was granted and Environmental Management Plan shall be furnished. 18 Jun 2019
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantKV RAO
DesignationDIRECTOR
Name of Company (Applicant Name should not be given here)SUNDARAM ALLOYS LIMITED
AddressPLOT NO.13 & 13/A, APSEZ,
Print