Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Proposed Limestone Mine (M.L. Area- 499.641 ha) with Production Capacity of 4.0 million TPA with installation of crusher 1600 TPH At Village- Kol Karhiya, Tehsil- Pawai, District- Panna (Madhya Prades
(b)Name of the Company / Organisation SPRINGWAY MINING PRIVATE LIMITED
(c)Registered Address Coromandel Towers,93, Santhome High RoadKarpagam Avenue, R.A. Puram, Chennai Pin Code - 600028,,Chennai,Lakshadweep-600028
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Mr. Vinayak Nayak
(b)Designation (Owner/ Partner/ CEO) VicePresident
(c)Address Coromondel Towers,93, Santhome High Road, Karpagam Avenue, R.A. Puram, Chennai Pin - 600028,,Mylapore Triplicane,Chennai,Tamil Nadu-600028
(d)Pin code 600028
(e)E-mail projects@springwaymining.co.in
(f)STD Code. 2962(f)Telephone No. 301503
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity1(a) Mining of minerals
Minor Activity
(b)Category A
(c)Proposal Number IA/MP/MIN/27304/2015
(d)Master Proposal Number(Single Window) SW/106197/2019
(e)EAC concerned (for category A Projects only) Non-Coal Mining
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Khasra Map is enclosed with EIA/EMP Report
(b)Pincode 488446
(c)Bounded Latitudes (North)
From
Degree 241529.02
Minutes
Second
From
Degree 241709.55
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 794824.91
Minutes
Second
From
Degree 795021.15
Minutes
Second
(e)Survey of India Topo Sheet No. 54P15
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 322
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 0.5
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Madhya Pradesh
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)Madhya PradeshPannaPawai
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number J-11015/114/2015-IA-II(M)
(b)Date of Apply of TOR 01 Apr 2015
(c)Date of Issue of TOR / Standard ToR 08 Jun 2015
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :24 Mar 2019
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :26 Apr 2019
Distance of Public Hearing Venue from the Proposed Project :0
Premises of Government Panchayat Bhavan, Village Kol Karhiya
State :Madhya Pradesh
District :Panna
Tehsil :Pawai
Village :Kol Karhaiya
65Issues raised during public hearing were about land compensation, employment, Health, Environemnt Management, Impact on river, Road and water facility etcOthersAddl District Collector
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Crawler mounted Bulldozer02305 HP
(2.)Grader1135 hp
(3.)Grader1135 hp
(4.)Explosive Van15 tonnes
(5.)Water sprinkler0110 KL
(6.)Water sprinkler0110 KL
(7.)Portable Tower Light01-
(8.)Limestone Crusher011600
(9.)DTH Hydraulic Drills with onboard compressor4
(10.)Limestone Crusher011600
(11.)Hydraulic Excavator55.5 m3 bucket capacity
(12.)Rear Dump Trucks1250 ton payload capacity
(13.)Wheel Loader15.4 m3 bucket capacity
(14.)Hydraulic Excavator with Rock Breaker1Siutable for 1.9 m3 bucket capacity excavator
(15.)Mobile service van01.
(16.)Jeeps02.
(17.)Fuel Bowser035 KL
(18.)Pump with accessories04500 m3/hr
(19.)Limestone Crusher011600
(20.)Limestone Crusher011600
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Mining lease area499.641HectaresOthers.
(2.)Limestone4.0OthersMillion TPAConveyor Belt
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 109
(b) Funds Allocated for Environment Management (Capital) (in Crores) 2.0
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 2.18
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.50
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel .
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel NaN
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)HSD37.60OthersLakh KLOpen marketRoadTanker and Diesel Browser. LinkageMOU with supplier wil be madeCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Mar 2018 To 29 May 2018
(b)Season Summer
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)NOxMicro Gram per Meter Cube27.615.427.5780
(2.)SO2Micro Gram per Meter Cube10.85.310.6880
(3.)PM2.5Micro Gram per Meter Cube39.621.039.2760
(4.)PM10Micro Gram per Meter Cube79.757.279.34100
    14.2.     No. of Ground Water monitoring locations : 7
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA7.417.246.58.5
(2.)TSSNA....
(3.)Total Hardnessmg/l548316200600
(4.)TDSmg/l9205105002000
(5.)Others.NA....
(6.)Fluoridemg/l0.660.351.01.5
(7.)Heavy Metals.NA....
(8.)Chloridesmg/l167.5538.852501000
    14.3.     No. of Surface Water monitoring locations : 2
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)DOmg/l7.206.80D
(2.)BODmg/l6.04.80D
(3.)CODmg/l18.8014.34D
(4.)pHNA7.327.32D
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))43.539.8I-70-75, C-55-65, R-45-55, S-40-50
(2.)Leq(Day)A-weighted decibels(dB(A))54.350I-70-75, C-55-65, R-45-55, S-40-50
    14.5.     No. of Soil Sample Monitored locations : 7
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)P(Phosphorus)Kilogram per hectare18.2515.76
(2.)Electric Conductivity0.260.19
(3.)N(Nitrogen)Kilogram per hectare341.46286.32
(4.)K(Potassium)Kilogram per hectare537.60344.96
(5.)pHOthersNA7.597.06
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 08 To 13
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 05 To 9
(c)Whether Ground Water Intersection will be there ? Yes
(d)Upload Copy of Central Ground Water Authority Letter Copy of Central Ground Water Authority Letter
(e)Letter No. 21-4/854/OR/MIN/2019
(f)Date of Issue 27 May 2019
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)Surface1000.1Copy of Permission LetterPipelineIntake Wellletterno/ ??.?.??.?./ 31/??/??.???. 440/2014/18304 Mar 20152800
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Workshop35ETPReuse within the Plant & Recycling3
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 3
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 3
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)SoilOthersMine waste870000Tons0RoadOthersWill be used for Greenbelt/Plantation
(2.)Mineral RejectOthersMine waste480000Tons0RoadOthersUtilized for cementmanufacturing after blending
(3.)Mineral RejectOthersMine waste950000Tons0RoadOthersFor stacking in sub grade yard
(4.)Over BurdenOthersMine waste3340000Tons0RoadOthersWill be used for backfilling the excavated area
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube78.50.94.382.9100
(2.)PM2.5Microgram per Meter Cube39.60.90.7840.3960
(3.)NOxMicrogram per Meter Cube27.60.71.8529.4680
(4.)SO2Microgram per Meter Cube10.080.91.0211.8280
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)None...Others..
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 3600
(b)Source Captive Power Plant in the Proposed Cement Plant
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) CPP/Grid
(e)Stack Height (in m) .
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 488.088
(c)Government Land (ha.) 11.553
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 499.641
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 488.088
(b)Waste/Barren Land (ha.) 11.553
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 0
(e)Settlements (ha.) 0
(f)Industrial (ha.) 0
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : 0 0
    Total (ha.) 499.641
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Quarry Area340.63207.99haplantation&agriculture use3.85haenchslope
(2.)Green belt103.69On lease periphery, road side, & along the pits
(3.)Built Up Area2.65Road Workshop crusher admn. Building magazine etc
(4.)Othersundisturbed area (Check dams and undisturbed area)52.671
Total (ha.) 499.641
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)WLSNone.None
(2.)ESAsNone.None
(3.)CorridorsNone.None
(4.)Critically Polluted AreaNone.None
(5.)ESZsNone.None
(6.)NPANone.None
(7.)Wildlife CorridorsNone.None
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Forest1 RF And 2 PF10.
(2.)Archaeological SitesNone.None
(3.)Defence InstallationsNone.None
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) .
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 101.300
(b)Land yet to be acquired(Ha) 398.341
(c)Status of Land acquisition if not acquired Under Process
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 1
(b)No. of Households 320
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 430
(e)Funds Allocated for R&R(in INR) (in Lacs) 104.36
(f)Status of R&R In-Progress
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Bearma River
(ii)Direction of Water Bodies in Buffer Area West
(iii)Distance of Water Bodies in Buffer Area 0.5
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 86
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 0
(e)No. of working days 300
(f)Total Manpower 86
32.
Green Belt in Ha:
(a)Total Area of Green Belt 178.64
(b)Percentage of Total Project Area 35.75
(c)No. of Plants to be Planted 267960
(d)Funds Allocated for Plantation 18800000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)FinancialThe Project will contribute additional revenue to the State and Central Govt. in the form of royalty, cess and other taxes etc. Job opportunities to the local people will improve the earning and spending capacity of the people.
(2.)EnvironmentalAt the conceptual stage, out of the total mining lease area (i.e. 499.641 ha), total mined-out area will be around 340.63 ha; out of which, 241.84 ha will be backfilled in which 207.99 ha area will be rehabilitated by plantation & agriculture use, 3.85 ha area will be rehabilitated by bench slope palntation and remaining 94.94 ha will be developed as water reservoir. 178.64 ha area will be covered under greenbelt/plantation. 1.65 ha area will be covered under road, 1.0 ha area will be utilized u
(3.)SocialProposed project will result in growth of the surrounding areas by increased direct and indirect employment opportunities in the region including ancillary development and supporting infrastructure. Besides this, Royalty and other taxes would be additional benefit and it will be utilized by local administration for the development of socio-economic infrastructure and well being of the local population. The various activities proposed through CER (Corporate Environment Responsibility) would help
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For Non-Coal Mining
S. No.Item Details
     1.       No. of Mineral(s) to be Mined : 1
S. No.Mineral(s) to be Mined Major or Minor Mineral
(1.)LimestoneMajor
2.
Mine Capacity in ROM (Run of Mine) 4.0
3.
Uploaded 500 meters Cluster Certificate from State Mines and Geology in case of minor minerals Copy of 500 meters Cluster Certificate from State Mines and Geology
4.
Mining Plan:
(a)Approval Letter No. MP/ Panna/ Limestone/ MPLN/ G- 22/ 2014- 15
(b)Date of Approval 27 May 2015
(c)Approved Letter Copy of Approved Letter
(d)Approved By State Mining and Geology Department IBM
(e)Approved Mining Lease Area 499.641
(f)Approved Capacity 4.0
5.
Technical Details:
(a)Total Geological Reserves (Million Ton) 160.10
(b)Mineable Reserves (Million Ton) 121.7
(c)Extractable Reserves(Million Ton) 121.7
(d)Percent(%) of Extraction 100
(e)Grade of Coal /Ore /Mineral Cement Grade
(f)Stripping Ratio 1 : 1.08
(g)Category of Gaseousness (Only for Coal Mining, Others may Write NA) None
(h)Average Gradient(Degree) gently dipping deposit at 2 to 5 degree
(i)Mining Method Opencast
(j)Life of Mine (Years) 31.5
6.
Details of Beneficiations:
(a)Whether it is proposed to install beneficiation plant/Coal washery within the mining lease area No
(b)Whether it is proposed to install crusher within the mining lease area Yes
(c)No. of crushers 1
     6.1.    Details of crusher:
S. No.Crusher ID Capacity (in PH)Remarks
(1.)11600 .
7.
Details of Seams:
(a)Whether details of seam applicable No
8.
Details of Mining Lease:
(a)Mining Lease Area (in Hectare) 499.641
(b)Whether obtained Letter of Intent (LOI) from the state government ? Yes
(i)Copy of Letter of Intent Copy of Letter of Intent
(ii)Date of issue of LOI 09 Dec 2014
(iii)Validity of LOI 30
(iv)Reference No. of LOI F 2-40/2013/12-1
(c)Whether Lease Deed Executed ? Yes
(i)Copy of Executed Lease deed valid as on Date Copy of Executed Lease deed
(ii)Provide area in Hectare as per executed lease deed (initial) document 499.641
(iii)Validity of the lease deed From : 13 Oct 2015 To : 12 Oct 2065
(iv)Date of Execution of Mining Lese 13 Oct 2015
(v)Reference Number MP283052015A1122303
(d)Whether Lease Deed Renewed ? No
(i)Reason thereof Lease is valid till 12.10.2065
9.
OB (Over Burden) Management:
(a) Details of External Dumps:
(i)No. of OB Dumps 0
(ii)Total Area (in Hectare) 0
(iii)Height (in meter) 0
(iv)Quantity (in Million Cubic meter) 0
(v)No. of year back fill up 0
(b) Details of Internal Dumps:
(i)No. of Internal Dumps 0
(ii)Total Area (in Hectare) 0
(iii)Height (in meter) 0
(iv)Quantity (in Million Cubic meter) 0
10.
Details of Topsoil Management:
(a)Quantity of Topsoil excavated during the entire life of the mine (in Million Cubic metre) 15.16
(b)Quantity of Topsoil proposed for utilization for reclamation during the entire life of the mine (in Million Cubic metre) 15.16
(c)Quantity of Topsoil proposed for utilization for other activities during the entire life of the mine (in Million Cubic metre) 0
11.
Details of Final Mine Void:
(a)Area (in Hectare) 94.94
(b)Depth (in meter) 58
(c)Volume (in Million Cubic meter) 55.065
12.
Details of Quarry:
(a)Final Void of 94.94 (hectare) at a Depth of 58 meter which is Proposed to be Converted into a Water Body.
(b)Total Quarry Area (ha) 340.63
13.
Details of Transportation:
(a)In Pit/Underground to Surface From working face to crusher hopper will be transp
(b)Surface to Siding/Loading Loading will be done by Hydraulic Excavators
(c)Transportation / Conveyor Details Crusher to Cement Plant by Covered Conveyor Belt
     14.      Details of Land Usage (Pre-Mining)
S. No.LAND USE Other LAND USEWITHIN ML AREA (Hectare)OUTSIDE ML AREA (Hectare)TOTAL (Hectare)
(1.)SURFACE WATER BODIES000
(2.)SETTLEMENTS000
(3.)GRAZING LAND000
(4.)AGRICULTURE LAND488.0880488.088
(5.)WASTE LAND11.553011.553
(6.)FOREST LAND000
TOTAL499.6410499.641
     15.      Details of Land Usage (Post-Mining)
S. No.LAND USE Other LAND USEPlantation (ha)Water Body (ha)Public Use (ha)Undisturbed (ha)Total
(1.)EXCAVATION/QUARRY245.6994.940340.63
(2.)ROADS001.651.65
(3.)BUILT UP AREA (COLONY/OFFICE)001.01
(4.)GREEN BELT103.6900103.69
(5.)EXTERNAL OB DUMPS0000
(6.)Othercheck dams & other protective measures001.501.5
(7.)TOP SOIL STORAGE0000
(8.)INTERNAL OB DUMPS0000
(9.)VIRGIN AREA0051.17151.171
TOTAL349.3894.9455.3210499.641
16.
Details of Reclamation:
Total Afforestation Plan shall be Implemented Covering of Mining.
This will Include:
(a)External OB Dump(in hectare) 0
(b)Internal Dump(in hectare) 0
(c)Quarry(in hectare) 340.63
(d)Safety Zone(in hectare) .
(e)Final Void of 94.94 (hectare) at a Depth of 58 meter which is Proposed to be Converted into a Water Body.
(f)Density of Tree Plantation per ha (in no.) 1500
(g)Others in ha (such as Excavation Area along ML Boundary, along Roads and Infrastructure, Embankment Area and in Township Located Outside the Lease etc) 4.15
(h)Total afforestation plant (in hectare) 178.64
17.
Status of progressive Mining Closure Plan:
Details Not Applicable
     18.      Details of Actual Coal/ ORE Production vis-a-vis Sanctioned Capacity since the Inception:
S. No.Financial Year Sanctioned Capacity as per EC (MTPA)Sanctioned Capacity as per CTOSanctioned Capacity as per approved mining planActual Production Excess Production Beyond the EC / CTO/ Mining Plan Sanctioned Capacity (MTPA)
(1.)000000
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1619/RA 0069
(ii)Name of the EIA Consultant JM EnviroNet Pvt Ltd
(iii)Address J.M EnviroNet Pvt. Ltd., 202-A, ABW Tower, M.G. Road, Near IFFCO Chowk,, Gurugram - 122 001 (Haryana)
(iv)Mobile No. 9509267011
(v)Landline No. 9509267011
(vi)Email Id jmenviron@hotmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Non-Coal Mining
(ix)Validity of Accreditation 07 Feb 2020
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAYour requested to kindly submit the following: (i)provide the details of total excavation, Inter burden, Over burden, Waste generation., e.t.c in the Form-I. (ii) Kindly submit the Risk assessment plan In Form-II at Point no 39 of (b) instead of mine plan. (iii) kindly submit the english translate letters where PP had submitted the other than english along with. (iv) Kindly submit the proper documents at Form-II, Point no 39 of (c) (v) Copy of affidavit needs to be submitted by PP in compliance of the Ministry’s OM no. 3-50/2017-IA.III (Pt.), dated 30th May 2018. (vi) Status of CGWA approval 10 Jun 2019
2.NAThe correction have been made as per the instruction received 17 Jun 2019
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1. ADS Reply LetterWe are herewith submitting ADS Reply 20 Aug 2021
2.NA

deferred

12 Jul 2021
3. ADS Reply LetterWe are herewith submitting ADS Reply 17 Jun 2021
4.NA

deferred

21 Aug 2019
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantMr. Vinayak Nayak
DesignationVicePresident
Name of Company (Applicant Name should not be given here)SPRINGWAY MINING PRIVATE LIMITED
AddressCoromandel Towers,93, Santhome High RoadKarpagam Avenue, R.A. Puram, Chennai Pin Code - 600028
Print