Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Expansion of Grain Based Distillery Unit with 3.75 MW Co-generation Power Plant from 59 KLD to 70 KLD as per Para 7(ii)
(b)Name of the Company / Organisation KHEMANI DISTILLERIES PVT LTD
(c)Registered Address Ringanwada, Kachigam Road, Daman,,Daman,Daman and Diu-396210
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Hinchhalal Dwivedi
(b)Designation (Owner/ Partner/ CEO) EHSHead
(c)Address Ringanwada, Kachigam Road, Daman,,Daman,Daman,Daman and Diu-396210
(d)Pin code 396210
(e)E-mail ehs@khemanigroup.com
(f)STD Code. 224(f)Telephone No. 2672
(g)Fax No. 2673
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity5(g) Distilleries
Minor Activity1(d) Thermal Power Plants
(b)Category A
(c)Proposal Number IA/DD/IND2/105696/2019
(d)Master Proposal Number(Single Window) SW/105694/2019
(e)EAC concerned (for category A Projects only) NIL
(f)Project Type Expansion under para 7(ii)
4.
Location of the Project:
(a)Plot/Survey/Khasra No. 50/1-A (1), 50/1-g, 50/2, 53/1, 53/2, 53/4, 58, 59
(b)Pincode 396210
(c)Bounded Latitudes (North)
From
Degree 2256728.33
Minutes
Second
From
Degree 2257258.23
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 277762.01
Minutes
Second
From
Degree 278439.94
Minutes
Second
(e)Survey of India Topo Sheet No. F43S15 (46D/15)
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 17
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 042
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Daman and Diu
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR)/EC: Not Applicable
4.
Whether the Project Exempted from Public Hearing? Details Not Applicable
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Bhopal
(iii)Letter No. 18-E-2/2019(ENV)/197
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit Feb 28 2019 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Product- ENA591170Kilo Litre per Day(KLD)Road,OthersSold to Market and captive consumption for IMFL
(2.)By-product- CO229.56.536OthersTPDOthersShall be captured & sold commercially
(3.)Product- IMFL/CL/RS660000006600000Otherscases/annumRoad,Otherssold to Market
(4.)Cogeneration Power3.7503.75Mega Watt(MW)Road,OthersCaptive
(5.)By-Product - DWGS811495OthersTPDRoad,OthersSold as cattle feed
(6.)By - Product - DDGS27633OthersTPDRoad,OthersSold as cattle feed
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)Grain Unloading Facility101Existing Facilities will be used
(2.)Evaporation Facility202Existing Facility will be used
(3.)Decantation & Dryer Facility101Existing facility will be used
(4.)Effluent Treatment Plant with RO Facility101Existing Facility Will be Used
(5.)WTP & Waste Water Recovery Facility101Existing Facility will be used
(6.)Steam Boiler - Stand-by12 TPH012 TPH
(7.)DG Sets2 x 1000 KVA & 1 x 500 KVA02 x 1000 KVA & 1 x 500 KVA
(8.)Liquefaction & Fermentation Facility101Existing Facility will be used
(9.)Steam Boiler- 27.5 TPH & Turbine 3.75 MW101Existing Facility will be used
(10.)Multi Pressure Distillation Facility202Existing Facility will be used
(11.)Grain Silo Facility202Existing Facility will be used
(12.)Grain Milling Facility101Existing Facility will be used
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 01 Oct 2018
(iv)Valid Upto 30 Sep 2021
(v)File No. PCC/DDD/R-34-WA/AA/RW/94-95/192669/262
(vi)Application No. PCC/DDD/R-34-WA/AA/RW/94-95/192669/262
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 100
(b) Funds Allocated for Environment Management (Capital) (in Crores) 27
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 2.65
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? Yes
b)Critically polluted areas as notified by the Central Pollution Control Board(CPCB) from time to time Yes
d)Inter-State boundaries and international boundaries Yes
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 0
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 0
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Grains – Maize, jowar, broken rice165OthersTPDopen MarketRoad700 Open MarketCopy of Linkage
(2.)Sodium hydroxide80OthersKg/dayLocal market from Daman and VapiRoad15 Open MarketCopy of Linkage
(3.)Anti-foam Agent34.5OthersKg/dayLocal market from Daman and VapiRoad15 Open MarketCopy of Linkage
(4.)Nutrient23OthersKg/dayLocal market from Daman and VapiRoad15 Open MarketCopy of Linkage
(5.)Enzymes96.6OthersKg/dayLocal market from Daman and VapiRoad15 Open MarketCopy of Linkage
(6.)Yeast27.6OthersKg/dayLocal market from Daman and VapiRoad15 Open MarketCopy of Linkage
(7.)bio fuel as rice husk/bagasse150OthersTPDLocal MarketRoad500 Open MarketCopy of Linkage
16.
Baseline Data Not Applicable
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 4.08 To 8.40
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 0.98 To 5.38
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater4170.1Copy of Permission LetterPipelineOthersBore Well21-4/65/DD/IND/2017-45418 Mar 2019417
(2.)OthersCanal1370.42Copy of Permission LetterCanalOthers-41195824 Aug 2018137
(3.)GroundWater4720.1Copy of Permission LetterPipelineOthersBore Well21-4/77/DD/IND/201911 Apr 20191067
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Process waste560600ETP (including RO), Decantation, MEE, DryerReuse within the Plant & Recycling,OthersGreen area5600
(2.)Domestic1620Septic Tank & Soak PitOthersSoak Pit160
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 576
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 576
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)ETP - SludgeOthersETP- SLUDGE109.5Tons0OthersTROLLYOthersused as Bio- Manure within the Plant
(2.)Grain wasteOthersGrain waste565.75Tons200RoadOthersSold as cattle Feed
(3.)RecyclablesMunicipal Solid Waste7.3Tons10RoadOthersApproved Recycler
(4.)e-wasteE Waste0.144Tons10RoadAuthorized Recyclers
(5.)OrganicsMunicipal Solid Waste3.7Tons0Others-Othersorganic as manure & incinerable to boiler
(6.)Used OilHazardous Waste (as per Hazardous and Other Waste Management rules 2016)5Kilolitre10RoadAuthorized Recyclers
(7.)Ash - (Bio-Fuels)Fly Ash4380Tons200RoadOthersBrick Manufacturer & Bio-Manure Manufacturer
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)SO2Microgram per Meter Cube14.700.90.8515.5580
(2.)NOxMicrogram per Meter Cube14.80.9519.980
(3.)PM10Microgram per Meter Cube62.100.90.562.61100
(4.)PM2.5Microgram per Meter Cube18.80.9018.960
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)Steam Boiler 12 TPH (Stand by)Furnace Oil321.15OthersPM0.5
(2.)2 x 1000 KVA existing DG setsLow Sulphur Diesel300.25SO20.0017
(3.)Steam Boiler 27.5 TPHAgro Based fuel501.2OthersPM0.5
(4.)1 x 500 KVA existing DG setLow sulphur Diesel100.123SO20.0017
(5.)1 x 500 KVA existing DG setLow sulphur Diesel100.123NOx0.8
(6.)Steam Boiler 12 TPH (Stand by)Furnace Oil321.15SO21.3
(7.)1 x 500 KVA existing DG SetsLow sulphur Diesel100.123OthersPM0.04
(8.)2 x 1000 KVA existing DG SetsLow sulphur Diesel300.25OthersPM0.04
(9.)2 x 1000 KVA existing DG setsLow Sulphur Diesel300.25NOx0.5
(10.)Steam Boiler 27.5 TPHAgro based fuel501.2NOx0.5
(11.)Steam Boiler 12 TPH (Stand By)Furnace Oil321.15NOx0.5
(12.)Steam Boiler 27.5 TPHAgro based fuel501.2SO21.3
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 2700
(b)Source Inhouse power generation
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 1 x 500 & 2 x 1000 KVA
(e)Stack Height (in m) 30
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 9.7473
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 9.7473
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 10
(b)Waste/Barren Land (ha.) 20
(c)Grazing/ Community Land (ha.) 10
(d)Surface Water Bodies (ha.) 0
(e)Settlements (ha.) 0
(f)Industrial (ha.) 10
(g)Forest (ha.) 20
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 1
(j)Others (ha.) : 0 200
    Total (ha.) 271
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Main Plant9.7473
Total (ha.) 9.7473
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaIndustrial cluster of Vapi4.0SE direction
(2.)WLSNone0None
(3.)ESZsNone0None
(4.)CorridorsNone0None
(5.)Wildlife CorridorsNone0None
(6.)NPANone0None
(7.)ESAsNone0None
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Defence InstallationsCoast Guard Air Station4.81NW direction
(2.)ForestReserve Forest near Balitha2.82NEE direction
(3.)Archaeological SitesHoly Jesus Church4.13NWW Direction
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 9.7473
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired Acquired
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? Yes
(i)Details of Schedule-I Species Indian Peafowl
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Canal near Project Site
(ii)Direction of Water Bodies in Buffer Area South West
(iii)Distance of Water Bodies in Buffer Area 0.42
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 110
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 210
(e)No. of working days 365
(f)Total Manpower 320
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt32200032200
(2.)Percentage of Total Project Area33033
(3.)No. of Plants170015343234
(4.)Funds Allocated10000000010000000
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)EnvironmentalZero liquid discharge complex
(2.)SocialDirect and Indirect employment generation
(3.)FinancialRevenue Generation
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. Rev 76, 06th May 2019/sr no. 119
(ii)Name of the EIA Consultant Perfact Enviro Solutions PVt Ltd
(iii)Address 5th Floor, NN Mall, Sector-3, Rohini
(iv)Mobile No. 9818362330
(v)Landline No. 0114928136
(vi)Email Id info@perfactgroup.in
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 27 May 2019
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NA- There being no increase in pollution load due to the proposed expansion (from 59 to 70 KLPD), proposal may be first examined in terms of the Ministry's Notification dated 23/11/2016 for the requirement of EC and/or amendment in the existing EC dated 27/8/2018. - Earlier EC was granted on 27/8/2018 and the project was operational in October, 2018 i.e. within a month. This needs to be suitably clarified. - Entries against items 20&21 of Form-2 can not be the same. - As mentioned at item 11, how the general conditions are applicable and its relevance in the present context. 25 May 2019
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantHinchhalal Dwivedi
DesignationEHSHead
Name of Company (Applicant Name should not be given here)KHEMANI DISTILLERIES PVT LTD
AddressRinganwada, Kachigam Road, Daman
Print