1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | Maruti Ferrous Pvt Ltd: Change in Product mix with Modernization and Optimization of production Capacity under para 7(ii) of EIA Notification. | (b)Name of the Company / Organisation | MARUTI FERROUS PRIVATE LIMITED | (c)Registered Address | VILLAGE SONDRA TAHSIL AND DISCTRICT RAIPUR,,Raipur,Chhattisgarh-493221 | (d)Legal Status of the Company | Private | (e)Joint Venture | No | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | RAJESH KUMAR TOLA | (b)Designation (Owner/ Partner/ CEO) | DIRECTOR | (c)Address | VILLAGE SONDRA BLOCK DHARSIWA TAHSIL AND DISTRICT RAIPUR,,Raipur,Raipur,Chhattisgarh-493221 | (d)Pin code | 493221 | (e)E-mail | marutiferrous@rediffmail.com | (f)STD Code. | 8966(f)Telephone No. | 80000 | (g)Fax No. | | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a.I)Project/Activity | 3(a) Metallurgical industries (ferrous & non ferrous)
| Minor Activity | | (b)Category | A | (c)Proposal Number | IA/CG/IND/105366/2019 | (d)Master Proposal Number(Single Window) | SW/105365/2019 | (e)EAC concerned (for category A Projects only) | NIL | (f)Project Type | Change of Product Mix under para 7(ii) |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | Kh. No: 428/1, 428/2, 428/3, 416/2, 416/8, 428/4, | (b)Pincode | 493221 | (c)Bounded Latitudes (North) | | From | | Degree | 21.370435 | Minutes | | Second | | From | | Degree | 22.372478 | Minutes | | Second | | (d)Bounded Longitudes (East) | | From | | Degree | 81.642125 | Minutes | | Second | | From | | Degree | 81.644516 | Minutes | | Second | | (e)Survey of India Topo Sheet No. | F44P11 | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 273 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 3 | (j)Seismic Zone | 2 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Chhattisgarh | |
|
|
Details of State of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
NIL | |
|
6. | Details of Terms of Reference (ToR)/EC: | Not Applicable | |
|
4. | Whether the Project Exempted from Public Hearing? | Details Not Applicable | |
|
8. | Details of Project Configuration/Product: | Details Not Applicable | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | (a)Details of certified report on compliance of earlier environmental clearance condition | (i)Certified Compliance By | Regional | (ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on | Nagpur | (iii)Letter No. | 5-24/2008(env)/3395 | (iv)Status of Compliance | Compiled | (v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) | Copy of Certified Compliance Report | (vi)Date of site visit | Jul 22 2018 12:00AM | (b)Details of Capacity Expansion | |
|
S. No. | Product/Activity (Capacity/Area) | Quantity From | Quantity To | Total | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | MS Billet/Rerolled Product through Hot Charging | 96000 | 0 | 96000 | Tons per Annum(TPA) | | Road | | (2.) | Rerolled Product through Reheating Furnace | 60000 | 0 | 60000 | Tons per Annum(TPA) | | Road | | |
| (c)Details of Configuration | |
|
S. No. | Plant / Equipment / Facility | Existing Configuration | Proposed Configuration | Final configuration after expansion | Remarks |
---|
(1.) | Induction Furnace | 10MT X 2Nos and 6 MT X 2Nos with CCM | Hot Charging facility | 10MTX2Nos& 6MTX2Nos with CCM with Hot Charging | No new induction furnace will required to be installed | (2.) | Reheating Furnace | 1 | 0 | 1 | No new Reheating Furnace Required | |
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | 31 Dec 2018 | (iv)Valid Upto | 31 Jan 2021 | (v)File No. | 6895/TS/CECB/2018 | (vi)Application No. | 2000914 | (vii)Copy of Consent to operate valid as on date | Copy of Consent to Operate | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in Crores) | 36.72 | (b) Funds Allocated for Environment Management (Capital) (in Crores) | .6 | (c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) | 3 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) | 20 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | No | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 113233 | (b)Existing quantity of raw material/fuel | N/A | (c)Total quantity of raw material/fuel | 113233 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | Sponge Iron | 91535 | Tons per Annum | | Open Market | Road | | 25 | Open Market | | Copy of Linkage | (2.) | Ferro Alloy | 1015 | Tons per Annum | | Open Market | Road | | 25 | Open Market | | Copy of Linkage | (3.) | Ramming Mass etc | 394 | Tons per Annum | | Open Market | Road | | 50 | Open Market | | Copy of Linkage | (4.) | CI/PIG Iron/HM Scrap | 20289 | Tons per Annum | | Open Market | Road | | 50 | Open Market | | Copy of Linkage | |
|
16. | Baseline Data | Not Applicable | |
|
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 5.3 To 8.4 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 2.05 To 3.2 | (c)Whether Ground Water Intersection will be there ? | No | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity (Kilolitre per Day (Kld)) | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | Others | CIBL industtrial water supply | 247 | .5 | Copy of Permission Letter | Pipeline | | Others | Surface water | CIBL/2016-17/006 | 07 Apr 2018 | 450 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | domestic | 4 | 10 | Septic tank and soak pit | Green Belt Renewal Plant | | 4 | | |
|
16.1. | (a)Total Waste Water Generation (Kilolitre per Day) | 4 | (b)Total Discharged Water (Kilolitre per Day) | 0 | (c)Total Reused Water (Kilolitre per Day) | 4 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | Miss Cast/ Defective Billet | Industrial Waste | | 2880 | Tons | 0 | Others | Manual | Others | Reused in own Induction Furance | (2.) | Refractory Waste | Industrial Waste | | 192 | Tons | 25 | Road | | Others | Given to recyclers/land fill | (3.) | Mill Scale | Industrial Waste | | 3600 | Tons | 50 | Road | | Others | sold to Ferroy Alloy/ Pellet Plants | (4.) | End Cutting/Miss Roll etc | Industrial Waste | | 3200 | Tons | 0 | Others | Manual | Others | Reused in own Induction Furnace | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | SO2 | | Microgram per Meter Cube | 23 | 2.2 | .02 | 23.03 | 80 | (2.) | PM10 | | Microgram per Meter Cube | 76 | 2.2 | .1 | 76.2 | 100 | (3.) | PM2.5 | | Microgram per Meter Cube | 45 | 2.2 | .1 | 45.2 | 60 | (4.) | NOx | | Microgram per Meter Cube | 28 | 2.2 | .1 | 28.11 | 80 | (5.) | Others(Specify) | NO increase in pollution load | NA | 0 | 1 | .5 | 1 | 1 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | Induction Furnace | Electricity | 30 | .8 | PM10 | | 50 | (2.) | Reheating Furnace | Furnace Oil | 38 | .8 | PM10 | | 50 | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 17500 | (b)Source | CSPCL State Grid | (c)Uploaded Copy of Agreement | Not Applicable | (d)Standby Arrangement (Details of DG Sets) | 1200 | (e)Stack Height (in m) | 12 | |
|
20. | Land Ownership Pattern: | (a)Forest Land (ha.) | 0 | (b)Private Land (ha.) | 3.24 | (c)Government Land (ha.) | 0 | (d)Revenue Land (ha.) | 0 | (e)Other Land (ha.) | 0 | Total Land (ha.) | 3.24 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area (ha.) | 0 | (b)Waste/Barren Land (ha.) | 0 | (c)Grazing/ Community Land (ha.) | 0 | (d)Surface Water Bodies (ha.) | 0 | (e)Settlements (ha.) | 0 | (f)Industrial (ha.) | 0 | (g)Forest (ha.) | 0 | (h)Mangroves (ha.) | 0 | (i)Marine Area (ha.) | 0 | (j)Others (ha.) : Industrial Land | 3.24 | Total (ha.) | 3.24 | |
|
22. Land requirement for various activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement (ha.) | Remarks |
---|
(1.) | Green belt | | 1.20 | | (2.) | Built Up Area | | 1.21 | | (3.) | Others | Road and Open Area | .83 | | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | NPA | NO NPA in 10 KM | 100 | NOT APPLICABLE | (2.) | ESAs | NOT APPLICABLE | 100 | NO ESA in 10 KM | (3.) | Wildlife Corridors | NOT APPLICABLE | 100 | No Wild Corridors in 10 KM | (4.) | Critically Polluted Area | No critically pollut area in 10 KM | 100 | No critically pollut area in 10 KM | (5.) | WLS | NOT APPLICABLE | 100 | NO WLS in 10 KM AREA | (6.) | ESZs | NOT APPLICABLE | 100 | NO ESZ in 10 KM | (7.) | Corridors | NOT APPLICABLE | 100 | NO corridors in 10 KM | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Archaeological Sites | | NO archaelogical site in 10 KM | 100 | NO archaelogical site in 10 KM | (2.) | Forest | | Not in 10KM area | 100 | No forst in 10 KM area | (3.) | Defence Installations | | No defence installation in 10 KM | 100 | No defence installation in 10 KM | |
|
23.3. | (a)Whether Noc / Permission from the competent authority is required? | No | (b)Whether NBWL recommendation is required? | No | |
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
25. | Tree Cutting: | (a)No. of Trees Cut for the Project (if Forest Land not Involved) | 0 | (b)Details of Tree Cutting and Planting of Trees | Not Applicable | |
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 3.24 | (b)Land yet to be acquired(Ha) | 0 | (c)Status of Land acquisition if not acquired | NOT APPLICABLE | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | 0 | (b)No. of Households | 0 | (c)No. of PDFs (Project Displaced Families) | 0 | (d)No. of PAFs (Project Affected Families) | 0 | (e)Funds Allocated for R&R(in INR) (in Lacs) | 0 | (f)Status of R&R | Completed | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | No | (b)Whether conservation plan for Schedule-I Species has been prepared ? | No | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | No | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | No | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | Yes | (i)Details of Water Bodies in Buffer Area | Kharun River | (ii)Direction of Water Bodies in Buffer Area | West | (iii)Distance of Water Bodies in Buffer Area | 3 | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 5 | (b)Permanent Employment-During Operation | 175 | (c)Temporary Employment- During Construction | 10 | (d)Temporary Employment- During Operation | 10 | (e)No. of working days | 300 | (f)Total Manpower | 200 | |
|
|
S. No. | Description | Existing | Proposed | Total |
---|
(1.) | Total Area of Green Belt | 1.20 | 0 | 1.2 | (2.) | Percentage of Total Project Area | 37 | 0 | 37 | (3.) | No. of Plants | 1700 | 0 | 1700 | (4.) | Funds Allocated | 10 | 2 | 12 | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Environmental | AVOIDANCE OF GREEN HOUSE GAS EMISSION
REDUCTION IN FUEL CONSUMPTION RESULT IN REDUCTION IN PARTICULATE EMISSION | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details : NOT APPLICABLE |
35. Sector Specific Details For Industrial Projects - 1 |
|
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | No | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | No | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | No | (i)Reason for not Hiring the Consultant | The application is under 7(ii) for change in product mix, there is no change in production facility | |
|
|
Essential Detail Sought : NIL |
Additional Detail Sought: |
---|
Sno. | ADS Letter | Remarks | Date of ADS |
---|
1. | ADS Reply Letter | Kindly find attached informations as desired | 14 Aug 2019 | 2. | NA | In view of the aforesaid and after detailed deliberations,
the Committee deferred the consideration of the proposal cited above and sought
following additional information for further consideration of the proposal: Permission from the Competent Authority for existing
and additional withdrawal of water.
Print
|
|
|
|