1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | Establishment of new Distillery (Molasses / Grain Based) - 120 KLD (RS/ENA/ETHANOL) alongwith Co - Generation Power – 4 MW at village : Fatehpur Roshnai, Tehsil: Akbarpur & Distt.: Kanpur Dehat (UP) | (b)Name of the Company / Organisation | ORANGE DISTILLERY AND BEVERAGE PVT LTD | (c)Registered Address | E - 35, Panki Mandir Road, Panki, Kanpur Nagar,,Kanpur Dehat,Uttar Pradesh-208020 | (d)Legal Status of the Company | Private | (e)Joint Venture | No | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | Amit Narain | (b)Designation (Owner/ Partner/ CEO) | Director | (c)Address | Village - Fatehpur Roshanai, Rania, Tehsil Akbarpur, Distt Kanpur Dehat,,Akbarpur,Kanpur Dehat,Uttar Pradesh-209304 | (d)Pin code | 209304 | (e)E-mail | amit.narain1410@gmail.com | (f)STD Code. | 512(f)Telephone No. | 9918402 | (g)Fax No. | | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a.I)Project/Activity | 5(g) Distilleries
| Minor Activity | | (b)Category | A | (c)Proposal Number | IA/UP/IND2/75365/2018 | (d)Master Proposal Number(Single Window) | SW/104943/2019 | (e)EAC concerned (for category A Projects only) | Industrial Projects - 2 | (f)Project Type | Fresh EC |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | Khasra No - 490, 491, 496, 497, 531 & 533, | (b)Pincode | 209304 | (c)Bounded Latitudes (North) | | From | | Degree | 26.4132 | Minutes | | Second | | From | | Degree | 26.4157 | Minutes | | Second | | (d)Bounded Longitudes (East) | | From | | Degree | 80.1115 | Minutes | | Second | | From | | Degree | 80.1116 | Minutes | | Second | | (e)Survey of India Topo Sheet No. | 63B/1, 63B/2, 54N/12, 54N/15 | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 128 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 26.26 | (j)Seismic Zone | 3 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Uttar Pradesh | |
|
|
Details of State(s) of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
(1.) | Maharashtra | Kolhapur | Kagal | Kagal | (2.) | Uttar Pradesh | Kanpur Dehat | Akbarpur | | |
|
6. | Details of Terms of Reference (ToR): | (a)MoEF&CC / SEIAA File Number | IA-J-11011/195/2018-IA-II(I) | (b)Date of Apply of TOR | 11 Jun 2018 | (c)Date of Issue of TOR / Standard ToR | 13 Jul 2018 | (d)Previous TOR Letter | Copy of Previous TOR letter | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | No | (b)Whether details of Public Hearing available? | Yes | (c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above | Yes | |
|
7.1. Details of Public Hearing |
---|
|
S. No. | Details of Advertisement | Details of Public Hearing | Venue | Location Details | No. of People Attended | Issues Raised | Designation of Presiding Officer | Other Designation of Presiding Officer |
---|
(1.) | | Copy of Public Hearing : | Copy of Public Hearing | Date : | 25 Mar 2019 | Distance of Public Hearing Venue from the Proposed Project : | 0.0 |
| Project Site | State : | Uttar Pradesh | District : | Kanpur Dehat | Tehsil : | Akbarpur | Village : | Fatehpur Roshnai |
| 84 | Issue related to Employment to the local people, CSR activity, Ground water level related | District Magistrate | | |
8. | Details of Project Configuration/Product: | |
|
8.1. Project Configuration |
---|
S. No. | Plant/Equipment/Facility | Configuration | Remarks |
---|
(1.) | Fermentation and Distillation Unit | 120 KLD | Based on Molasses and grain | (2.) | Co gen power plant | 4 MW | | |
8.2. Product |
---|
S. No. | Product/Activity (Capacity/Area) | Quantity | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | RS /ENA/ Ethanol | 120 | Kilo Litre per Day | | Road | | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | Details Not Applicable | |
|
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | N/A | (iv)Valid Upto | N/A | (v)File No. | NA | (vi)Application No. | NA | (vii)Copy of Consent to operate valid as on date | NA | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in Crores) | 170.58 | (b) Funds Allocated for Environment Management (Capital) (in Crores) | 34.70 | (c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) | 2.56 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) | 1.75 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | No | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 189000 | (b)Existing quantity of raw material/fuel | N/A | (c)Total quantity of raw material/fuel | 189000 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | Molasses | 189000 | Tons per Annum | | Sugar Mills nearby | Road | | 400 | Open Market | | Copy of Linkage | (2.) | Grains – Maize, jowar, broken rice | 108500 | Tons per Annum | | Local Vendors | Road | | 0 | MoU | | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 01 Oct 2018 To 31 Dec 2018 | (b)Season | Post-Monsoon | |
|
14.1. No. of ambient Air Quality (AAQ) monitoring locations : 08 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | PM10 | | Micro Gram per Meter Cube | 95 | 71.3 | 94.3 | 100 | (2.) | PM2.5 | | Micro Gram per Meter Cube | 56.3 | 41.7 | 56 | 60 | (3.) | NOx | | Micro Gram per Meter Cube | 27.3 | 14.0 | 26.1 | 80 | (4.) | SO2 | | Micro Gram per Meter Cube | 21.9 | 11.0 | 21.3 | 80 | |
14.2. No. of Ground Water monitoring locations : 08 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | pH | | | NA | | 7.7 | 6.9 | 7.5 | 8.5 | (2.) | TDS | | | mg/l | | 763.4 | 337.4 | 500 | 2000 | (3.) | Total Hardness | | | mg/l | | 448 | 220 | 200 | 600 | (4.) | Chlorides | | | mg/l | | 80.08 | 14.11 | 250 | 1000 | (5.) | Fluoride | | | mg/l | | 0.42 | 0.17 | 1.0 | 1.5 | (6.) | Others | Alkalinity | | mg/l | | 472. | 272 | 200 | 600 | (7.) | TSS | | | mg/l | | 0 | 0 | 0 | 0 | (8.) | Heavy Metals | | Fe | mg/l | | 0.24 | 0.0 | 0.3 | 0.3 | |
14.3. No. of Surface Water monitoring locations : 08 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | COD | | mg/l | | 184.1 | 68.6 | D | (2.) | Others | TH | mg/l | | 424.0 | 236 | D | (3.) | BOD | | mg/l | | 40.6 | 20.8 | D | (4.) | DO | | mg/l | | 5.1 | 4.6 | D | (5.) | pH | | NA | | 8.0 | 7.3 | D | |
14.4. No. of Ambient Noise monitoring locations : 08 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Day) | A-weighted decibels(dB(A)) | 65.5 | 47.5 | 65 | (2.) | Leq(Night) | A-weighted decibels(dB(A)) | 49.9 | 41.7 | 55 | |
14.5. No. of Soil Sample Monitored locations : 08 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | K(Potassium) | Milligram per Kilogram | | 89.3 | 68.2 | (2.) | P(Phosphorus) | Milligram per Kilogram | | 254.6 | 220.4 | (3.) | Electric Conductivity | Others | Micro Siemens / Centimeter | 306 | 152 | (4.) | pH | | | 7.9 | 7.6 | (5.) | N(Nitrogen) | Milligram per Kilogram | | 18.76 | 13.24 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 6.14 To 8.97 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 10.99 To 7.95 | (c)Whether Ground Water Intersection will be there ? | No | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity (Kilolitre per Day (Kld)) | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | GroundWater | | 720 | 0.0 | Copy of Permission Letter | Pipeline | | Tube Well | | Applied and under process | 27 May 2019 | 720 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | Fermentation and Distillation | 864 | 1000.0 | Spent wash will be concentrate in MEE and then concentrate from MEE will be used as fuel in Boiler along with Bagasse | Others | Zero Liquid Discharge | 566 | 298 | |
|
16.1. | (a)Total Waste Water Generation (Kilolitre per Day) | 864 | (b)Total Discharged Water (Kilolitre per Day) | 298 | (c)Total Reused Water (Kilolitre per Day) | 566 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | Fermenter Sludge | Others | Process | 3240 | Tons | 0.0 | Road | | Others | Used as Manure. | (2.) | Molasses based Operation | Fly Ash | | 18468 | Tons | 0.0 | Road,Conveyor Belt | | Others | Used as manure . | (3.) | Grain Residues (Only During Grain based operation) | Others | Process | 19440 | Tons | 0.0 | Road | | Others | Used as cattle feed. | (4.) | Only Grain Based Operation | Fly Ash | | 3402 | Tons | 0.0 | Road | | Others | will be provided to brick manufacturer. | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | PM2.5 | | Microgram per Meter Cube | 56.7 | 984 | 0.41 | 57.12 | 60 | (2.) | NOx | | Microgram per Meter Cube | 26.1 | 990 | 0.67 | 26.78 | 80 | (3.) | PM10 | | Microgram per Meter Cube | 94.6 | 994 | 0.78 | 95.4 | 100 | (4.) | SO2 | | Microgram per Meter Cube | 21.3 | 938 | 1.59 | 22.9 | 80 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | Stack 1 | Slop + Biomass | 60 | 3.5 | SO2 | | 9.69 | (2.) | Stack 1 | Slop + Biomass | 60 | 3.5 | NOx | | 4.1 | (3.) | Stack 1 | Slop + Biomass | 60 | 3.5 | PM10 | | 4.35 | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 2265 | (b)Source | Inhouse Co Gen Power Plant | (c)Uploaded Copy of Agreement | Copy of Agreement | (d)Standby Arrangement (Details of DG Sets) | 1000 KVA ( 01 No ) & 500 KVA ( 01 No) | (e)Stack Height (in m) | 16.3 | |
|
20. | Land Ownership Pattern: | (a)Forest Land (ha.) | 0.0 | (b)Private Land (ha.) | 4.7298 | (c)Government Land (ha.) | 0.0 | (d)Revenue Land (ha.) | 0.0 | (e)Other Land (ha.) | 0.0 | Total Land (ha.) | 4.7298 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area (ha.) | 17879.8 | (b)Waste/Barren Land (ha.) | 1371.8 | (c)Grazing/ Community Land (ha.) | 0 | (d)Surface Water Bodies (ha.) | 530.3 | (e)Settlements (ha.) | 1191.8 | (f)Industrial (ha.) | 0 | (g)Forest (ha.) | 78.3 | (h)Mangroves (ha.) | 0.0 | (i)Marine Area (ha.) | 0 | (j)Others (ha.) : Fallow land, Scrub land , Gullied, Decidious land | 10412 | Total (ha.) | 31463.999999999996 | |
|
22. Land requirement for various activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement (ha.) | Remarks |
---|
(1.) | Green belt | | 1.5608 | 33 % of total land | (2.) | Others | Open Area | 1.3896 | Open Area | (3.) | Main Plant | | 0.9872 | Roof Top | (4.) | Built Up Area | | 0.7922 | Road and Paved | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | WLS | NA | 0 | 0 | (2.) | Wildlife Corridors | NA | 0 | 0 | (3.) | NPA | NA | 0 | 0 | (4.) | Critically Polluted Area | NA | 0 | 0 | (5.) | ESAs | NA | 0 | 0 | (6.) | ESZs | NA | 0 | 0 | (7.) | Corridors | NA | 0 | 0 | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Defence Installations | | NA | 0 | No any | (2.) | Archaeological Sites | | NA | 0 | No any | (3.) | Forest | | NA | 0 | No any | |
|
23.3. | (a)Whether Noc / Permission from the competent authority is required? | No | (b)Whether NBWL recommendation is required? | No | |
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
25. | Tree Cutting: | (a)No. of Trees Cut for the Project (if Forest Land not Involved) | 0.0 | (b)Details of Tree Cutting and Planting of Trees | Not Applicable | |
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 4.7298 | (b)Land yet to be acquired(Ha) | 0 | (c)Status of Land acquisition if not acquired | 0 | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | 0 | (b)No. of Households | 0 | (c)No. of PDFs (Project Displaced Families) | 0 | (d)No. of PAFs (Project Affected Families) | 0 | (e)Funds Allocated for R&R(in INR) (in Lacs) | 0 | (f)Status of R&R | Completed | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | No | (b)Whether conservation plan for Schedule-I Species has been prepared ? | No | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | No | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | No | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | Yes | (i)Details of Water Bodies in Buffer Area | River Rind | (ii)Direction of Water Bodies in Buffer Area | East | (iii)Distance of Water Bodies in Buffer Area | 2.86 | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 30 | (b)Permanent Employment-During Operation | 25 | (c)Temporary Employment- During Construction | 30 | (d)Temporary Employment- During Operation | 50 | (e)No. of working days | 360 | (f)Total Manpower | 135 | |
|
32. | Green Belt in Ha: | (a)Total Area of Green Belt | 1.56 | (b)Percentage of Total Project Area | 32.98 | (c)No. of Plants to be Planted | 3900 | (d)Funds Allocated for Plantation | 5000000 | (e)Uploaded Green Belt plan | Copy of Green Belt Plan | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Financial | Orange Distillery and Beverages Pvt Ltd will actively contribute to improve the economic conditions of the area by providing direct and indirect employment for local persons preferable from the nearby villages. Also because of the increasing market demand, the proposed project would contribute to the excise and revenue of the country. | (2.) | Environmental | 1. Out of the total project area of 4.7298 Hectare, 1.56 Hectare (33%) will be utilized for green belt development. Green belt development in and around the project site will help to attenuate the pollution level.
2. Native species will be given priority for Avenue plantation. | (3.) | Social | 1 Self-Employment Training Programs.
2. Covering all nearby eligible village youths.
3. Assistance for self-employment.
4. Assistance through social forestry
programme.
5. Active participation in renovation of school, temple, community centre as per
requirement in nearby areas of Project site.
6. Support in infrastructure development of Hospitals of nearby areas.
7. Active participation in facilitating drinking water in summer season. | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details : NOT APPLICABLE |
35. Sector Specific Details For Industrial Projects - 2 |
|
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | No | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | No | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | QCI/NABET/ENV/ACO/17/0344 | (ii)Name of the EIA Consultant | Ascenso Environ Pvt Ltd | (iii)Address | D- 79, Sector - 6, Noida | (iv)Mobile No. | 9897674227 | (v)Landline No. | 9897674227 | (vi)Email Id | ETRCLTH@yahoo.in | (vii)Category of Accreditation | A | (viii)Sector of Accreditation | Industrial Projects - 2 | (ix)Validity of Accreditation | 03 Oct 2019 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Detail Sought: |
---|
Sno. | EDS Letter | Remarks | Date of EDS |
---|
1. | NA | Please inform/clarify the following:-
- Whether the proposed industrial operations are in conformity with permitted land use of the area. That needs to be confirmed along with supporting documents.
- Whether SPCB has given any in-principle approval for setting up the proposed distillery at the given site.
- Formal proposal to be submitted to CGWA/CGWB for ground water withdrawal of 720 cum/day.
- Proposal to be submitted to PESO for approval of the site layout and the storage facilities. | 15 May 2019 | 2. | NA | The correction have been made as per the instruction received | 27 May 2019 | 3. | NA | In case of grain to be used as raw material, the relevant details along with the procurement, need to be mentioned appropriately in column 13.1 of Form-2. | 01 Jun 2019 | 4. | NA | The correction have been made as per the instruction received | 27 Jun 2019 | |
Additional Detail Sought : NIL |
| Undertaking |
| I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. |
| Name of Applicant | Amit Narain | Designation | Director | Name of Company (Applicant Name should not be given here) | ORANGE DISTILLERY AND BEVERAGE PVT LTD | Address | E - 35, Panki Mandir Road, Panki, Kanpur Nagar |
|