Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Shree Chhatrapati Shahu Sahakari Sakhar Karkhana Ltd
(b)Name of the Company / Organisation SHREE CHHATRAPATI SHAHU SAHAKARI SAKHAR KARKHANA LTD., KAGAL
(c)Registered Address Kagal, Taluka : Kagal, District : Kolapur,,Kolhapur,Maharashtra-416216
(d)Legal Status of the Company Others
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Jitendra Anandrao Chavan
(b)Designation (Owner/ Partner/ CEO) Managing Director
(c)Address Shree Chatrapati Shahu S.S.K. Tdt., Kagal Shrimant Jayshingrao Ghatge Bhavan, Kagal, Taluka : Kagal, District : Kolhapur,,Kagal,Kolhapur,Maharashtra-416216
(d)Pin code 416216
(e)E-mail enveng@shahusugar.com
(f)STD Code. 2325(f)Telephone No. 244211
(g)Fax No. 02325244241
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity5(g) Distilleries
5(j) Sugar Industry
Minor Activity1(d) Thermal Power Plants
(b)Category A
(c)Proposal Number IA/MH/IND2/30200/2015
(d)Master Proposal Number(Single Window) SW/78609/2018
(e)EAC concerned (for category A Projects only) Industrial Projects - 2
(f)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. 144/1/B, 144/2, 148-151, 153-157, 159-161, 164-172
(b)Pincode 416216
(c)Bounded Latitudes (North)
From
Degree 16.291267
Minutes
Second
From
Degree 16.596367
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 74.294981
Minutes
Second
From
Degree 74.296822
Minutes
Second
(e)Survey of India Topo Sheet No. 47L2, 47L6
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 553
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 2.5
(j)Seismic Zone 4
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Maharashtra
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)MaharashtraKolhapurKagal
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number J-11011/225/2015-IA II (I)
(c)Date of Issue of TOR 01 Jan 1900
(f)Previous TOR Letter NA
(b)Date of Apply of EC 22 Dec 2016
(c)Date of Issue of EC 28 Mar 2017
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason Public Hearing exempted as per OM dated 29.08.2017
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Nagpur
(iii)Letter No. EC-334/RON/2017-NGP/5139
(iv)Status of Compliance Partially Complied
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit Feb 7 2019 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Sugar16338070620234000Tons per Annum(TPA)Road
(2.)Ethanol303060Kilo Litre per Day(KLD)Road
(3.)Refined Sugar0234000234000Tons per Annum(TPA)Road
(4.)Bagasse378000162000540000Tons per Annum(TPA)Conveyor Belt
(5.)pressmud504002160072000Tons per Annum(TPA)Road
(6.)Rectified spirit (RS)/ENA603090Kilo Litre per Day(KLD)RoadTo grid
(7.)Electricity281038Mega Watt(MW)OthersTo grid
(8.)Molasses504002160072000Tons per Annum(TPA)Road
(9.)Rectified spirit (RS)/ENA603090Kilo Litre per Day(KLD)Road
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)Sugar7000 TCD3000 TCD10000 TCD
(2.)Co-generation28 MW10 MW38 MW
(3.)Distillery60 KLD30 KLD90 KLD
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 01 Aug 2018
(iv)Valid Upto 31 Jul 2019
(v)File No. Format 1.0/BO/CAC-CELL/UAN
(vi)Application No. 1902000375
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 110
(b) Funds Allocated for Environment Management (Capital) (in Crores) 19.45
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 2.77
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 5.10
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? Yes
d)Inter-State boundaries and international boundaries Yes
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 3000
(b)Existing quantity of raw material/fuel 7000
(c)Total quantity of raw material/fuel 10000
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Sugar cane1800000Tons per AnnumNear by farmRoad40 Open MarketCopy of Linkage
(2.)Molasses90000Tons per AnnumOpen MarketRoad40 Open MarketCopy of Linkage
(3.)Bagasse324000Tons per AnnumWon Sugar FactoryConveyor Belt0 CaptiveCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Dec 2018 To 28 Feb 2019
(b)Season Post-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube80.5052.0079.92100
(2.)PM2.5Micro Gram per Meter Cube42.7016.3042.0760
(3.)NOxMicro Gram per Meter Cube45.6019.0044.2280
(4.)SO2Micro Gram per Meter Cube31.4013.0030.3880
    14.2.     No. of Ground Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)Total Hardnessmg/l291.54134.13200200
(2.)Chloridesmg/l305.4357.09250250
(3.)pHNA7.387.006.58.5
(4.)TDSmg/l761.62228.30500500
(5.)Fluoridemg/l2.320.1411
(6.)TSSmg/l27.4611.96100100
    14.3.     No. of Surface Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA8.207.47E
(2.)BODmg/l85.687.15E
(3.)CODmg/l180.8624.17E
(4.)DOmg/l3.110.55E
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))51.340.170
(2.)Leq(Day)A-weighted decibels(dB(A))70.950.575
    14.5.     No. of Soil Sample Monitored locations : 8
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)N(Nitrogen)Milligram per Kilogram918.76412.38
(2.)P(Phosphorus)Milligram per Kilogram136.3841.59
(3.)K(Potassium)Milligram per Kilogram297.41100.26
(4.)Electric ConductivityMillisiemens per Centimetre3127.501325.30
(5.)pH8.167.52
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 0.00 To 16.28
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 1.5 To 10
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)Surface3513.0Copy of Permission LetterPipelineIntake WellD81810 Oct 20072196
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic Effluent73.280Proposed STP to be upgraded under expansionGreen Belt Renewal Plant73.2
(2.)Industrial Effluent (Distillery-Other)599700treated in CPUReuse within the Plant & Recycling599
(3.)Industrial Effluent (Distillery- Spent wash)667700Concentration in mEE followed by compostingOthersComposting6670
(4.)Industrial Effluent (Sugar & Co-gen)867900Full fledge ETP to be upgraded under expansionOtherstreated water-for crop cultivation8670
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 2206.2
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 2206.2
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Fermentation ResiduesIndustrial Waste405Tons5.0RoadOthersMixed in composting process
(2.)boiler AshBottom Ash15454.8Tons20RoadOthersComposting/ send to brick manufacturer
(3.)ETP SludgeIndustrial Waste45Tons0RoadOthersUse as mannure in own farm
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)NOxMicrogram per Meter Cube19.14000019.1580
(2.)SO2Microgram per Meter Cube30.382.530.0530.4480
(3.)PM10Microgram per Meter Cube79.822.530.1080.02100
(4.)PM2.5Microgram per Meter Cube42.072.530.03342.1360
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)BoilerBiogas/Bagasse402.93SO25.12
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 20000
(b)Source Own Co-gen
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 500 KVA (2 Nos.), 300 KVA (2 Nos.)
(e)Stack Height (in m) 5
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 140
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 140
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 13720
(b)Waste/Barren Land (ha.) 4512
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 342
(e)Settlements (ha.) 3970
(f)Industrial (ha.) 0
(g)Forest (ha.) 25
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : Scrub Land, Mining Area, Fallow Land 8846
    Total (ha.) 31415
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Green belt46.2
(2.)Built Up Area17.40
Total (ha.) 63.6
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)WLSNil0There is no presence of any CPA, NPA, ESAs, ESZs, Corridors & wildlife corridors in 10 Km radius of project
(2.)ESZsNil0There is no presence of any CPA, NPA, ESAs, ESZs, Corridors & wildlife corridors in 10 Km radius of project
(3.)Critically Polluted AreaNil0There is no presence of any CPA, NPA, ESAs, ESZs, Corridors & wildlife corridors in 10 Km radius of project
(4.)ESAsNil0There is no presence of any CPA, NPA, ESAs, ESZs, Corridors & wildlife corridors in 10 Km radius of project
(5.)NPANil0There is no presence of any CPA, NPA, ESAs, ESZs, Corridors & wildlife corridors in 10 Km radius of project
(6.)CorridorsNil0There is no presence of any CPA, NPA, ESAs, ESZs, Corridors & wildlife corridors in 10 Km radius of project
(7.)Wildlife CorridorsNil0There is no presence of any CPA, NPA, ESAs, ESZs, Corridors & wildlife corridors in 10 Km radius of project
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Archaeological SitesNA0There are no archealogical sites within 10 km from project site
(2.)Defence InstallationsNA0There are no any defence installations within 10 km from project site
(3.)ForestNA0There is no forest land within 10 km from project site
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 0
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired Nil
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? Yes
(i)Details of Water Bodies in Core Area Doodhaganga river, Jayshingrao Lake,
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Kaneri Lake
(ii)Direction of Water Bodies in Buffer Area North West
(iii)Distance of Water Bodies in Buffer Area 5.10
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 50
(b)Permanent Employment-During Operation 100
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 50
(e)No. of working days 270
(f)Total Manpower 200
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt37000092000462000
(2.)Percentage of Total Project Area26.436.5733
(3.)No. of Plants179797000087979
(4.)Funds Allocated60000032000003800000
    33.       Project Benefits
S. No. Type of Project BenefitsDetails of Project Benefits
NIL
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? Yes
(b)Name of the Court Districts Courts
(c)Name of the Sub Court kolhapur
(d)Case No. Crim.Misc.Appln.No 1117
(e)Orders/Directions of the court ,if any and its relevance with the proposed project No
(f)Case Details Increased number of days for distillery operation
(g)Uploaded Court Order Copy of Court Order
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1518/SA063
(ii)Name of the EIA Consultant M/s. Equinox Environments (I) Pvt. Ltd., (EEIPL)
(iii)Address F-11, Namdev Nest 1160ā€“B, ā€˜Eā€™ Ward Sykes Extension opp. of Kamala College, Kolhapur 416 001
(iv)Mobile No. 9657865122
(v)Landline No. 0231253123
(vi)Email Id projects@equinoxenvi.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 21 Oct 2018
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NA- Please submit copy of the EC dated 28/3/2017. - Whether EIA Consultant was having NABET accreditation while preparation of EIA/EMP report and submission of the proposal for EC. Please clarify. 02 Jun 2019
2.NAThe correction have been made as per the instruction received 06 Jun 2019
3.NAAs per the Ministry's Notification dated 13/6/2019, the said project/activity has been listed under category B and thus requires appraisal/approval at State level by the concerned SEAC/SEIAA. 14 Jun 2019
4.NAThe correction have been made as per the instruction received 17 Jun 2019
5.NAPlease see our observations dated 2/6/2019 for the needful. 07 Jul 2019
6.NAThe correction have been made as per the instruction received 08 Jul 2019
7.NAPlease see our observations dated 14/6/2019 for the needful. 04 Aug 2019
8.NAThe correction have been made as per the instruction received 06 Aug 2019
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantJitendra Anandrao Chavan
DesignationManaging Director
Name of Company (Applicant Name should not be given here)SHREE CHHATRAPATI SHAHU SAHAKARI SAKHAR KARKHANA LTD., KAGAL
AddressKagal, Taluka : Kagal, District : Kolapur