Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Maharashtra Enviro Power Limited, Nagpur
(b)Name of the Company / Organisation M/S. MAHARASHTRA ENVIRO POWER LTD.
(c)Registered Address CHW-01, Butibori Industrial Area, Vil. Butibori-Hingna, Nagpur Maharashtra,,Nagpur,Maharashtra-441110
(d)Legal Status of the Company Others
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Kishore Rajaram Malviya
(b)Designation (Owner/ Partner/ CEO) GeneralManager
(c)Address CHW-01, Butibori Industrial Area, Vil. Butibori-Hingna, Nagpur Maharashtra,,Hingna,Nagpur,Maharashtra-441110
(d)Pin code 441110
(e)E-mail kishore20m@gmail.com
(f)STD Code. 712(f)Telephone No. 6665000
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity7(d) Common hazardous waste treatment, storage and disposal facilities (TSDFs)
Minor Activity
(b)Category A
(c)Proposal Number IA/MH/MIS/74850/2018
(d)Master Proposal Number(Single Window) SW/103389/2019
(e)EAC concerned (for category A Projects only) INFRA-2
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Plot No. CHW-01, MIDC Butibori, Mandwa, Butibori,
(b)Pincode 441122
(c)Bounded Latitudes (North)
From
Degree 20
Minutes
Second
From
Degree 20
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 78
Minutes
Second
From
Degree 78
Minutes
Second
(e)Survey of India Topo Sheet No. 55K16, 55L13, 55P1
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 293
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 2.1
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Maharashtra
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)KarnatakaBellarySandurIttanahalli / Taranagar
(2.)MaharashtraNagpurHingna
6.
Details of Terms of Reference (ToR):
(a)Whether TOR is mandatory for submitting application Yes
(b)MoEF&CC / SEIAA File Number 10-42/2018-IA-III
(c)Date of Apply of TOR 03 May 2018
(d)Date of Issue of TOR / Standard ToR 07 Aug 2018
(e)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason Public hearing was not applicable because project
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Common HWTSDF FacilityIncinerator 3T/Hr to 1T/HrDownsizing of Incinerator Capacity
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Secure Landfill60000Tons per AnnumRoad
(2.)Rotary Incinerator7200Tons per AnnumRoad
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 16 Jul 2015
(iv)Valid Upto 28 Feb 2020
(v)File No. BO/RO(HQ)/HWMD/EIC No.NG-12344-15/CR/CC-7904
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 8
(b) Funds Allocated for Environment Management (Capital) (in Crores) 0.58
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.08
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.41
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 4
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 4
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Hydrated Lime750Tons per AnnumMaharashtra and Other States of IndiaRoad0 Open MarketCopy of Linkage
(2.)Activated Carbon120Tons per AnnumMaharashtra and Other States of IndiaRoad0 Open MarketCopy of Linkage
(3.)Caustic Lye180Tons per AnnumMaharashtra and Other States of IndiaRoad0 Open MarketCopy of Linkage
(4.)Misc. Auxiliary Chemicals150Tons per AnnumMaharashtra and Other States of IndiaRoad0 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 07 Mar 2018 To 07 Jun 2018
(b)Season Pre-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 6
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)SO2Micro Gram per Meter Cube15.97.415.33480
(2.)OthersCOMili Gram per Meter Cube0.370.270.372
(3.)NOxMicro Gram per Meter Cube30.417.529.13480
(4.)PM10Micro Gram per Meter Cube66.446.965.092100
(5.)PM2.5Micro Gram per Meter Cube28.617.328.07860
    14.2.     No. of Ground Water monitoring locations : 6
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA8.036.978.58.5
(2.)Total Hardnessmg/l224.10127.68200600
(3.)Chloridesmg/l62.7623.932501000
(4.)Heavy MetalsZincmg/l1.70.1515
(5.)TSSmg/l0000
(6.)TDSmg/l285.1214.15002000
(7.)Fluoridemg/l0.240.1211.5
    14.3.     No. of Surface Water monitoring locations : 6
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)DOmg/l00A
(2.)BODmg/l00A
(3.)CODmg/l00A
(4.)pHNA8.217.93A
    14.4.     No. of Ambient Noise monitoring locations : 6
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))62.448.675
(2.)Leq(Night)A-weighted decibels(dB(A))47.638.370
    14.5.     No. of Soil Sample Monitored locations : 6
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)N(Nitrogen)Kilogram per hectare437.17356.27
(2.)P(Phosphorus)Kilogram per hectare14.5211.29
(3.)Electric ConductivityOthersµs/cm403.81239
(4.)K(Potassium)Kilogram per hectare36.1921.51
(5.)pH7.266.73
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 3 To 5
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 2 To 4
(c)Whether Ground Water Intersection will be there ? NA
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersMIDC Water Supply4230Copy of Permission LetterPipelineOthersMIDC Water supplyMIDC/Jt.CEO (Env)/51802 Jun 2004423
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Land fill leachate1717ETP Primary Treatment followed by incinerationOthersSent to Incineration for final discharge017
(2.)Industrial Waste Water2020ETP Primary TreatmentOthersUsed in gas quencher020
(3.)Domestic Waste Water1616To STPOthersUsed in Green belt development016
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 53
(b)Total Discharged Water (Kilolitre per Day) 53
(c)Total Reused Water (Kilolitre per Day) 0
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)ETP sludgeHazardous Waste (as per Hazardous and Other Waste Management rules 2016)25Tons0RoadOthersDisposal to secured landfill site
(2.)Used OilHazardous Waste (as per Hazardous and Other Waste Management rules 2016)0.05Kilolitre0RoadOthersSent to recycler/reuse as lubricant/Incineration
(3.)Used drums containers barrels bagsHazardous Waste (as per Hazardous and Other Waste Management rules 2016)0Tons0RoadOthersSell to Recycler/to CHTSDF site
(4.)Incineration AshHazardous Waste (as per Hazardous and Other Waste Management rules 2016)1000Tons0RoadOthersDisposal to secured landfill
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)Others(Specify)TSPMMicrogram per Meter Cube02.81.671.674150
(2.)SO2Microgram per Meter Cube11.442.86.8618.30340
(3.)PM10Microgram per Meter Cube00010
(4.)PM2.5Microgram per Meter Cube00010
(5.)NOxMicrogram per Meter Cube23.382.813.6437.02394.06
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)D.G. SetLDO100.150OthersPM SO2 NOxPartial
(2.)IncinerationLDO HSD451.2OthersPM HCl SO2 CO TOC HF Nox Dioxin and Furan MetalsPartial
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 1000
(b)Source Maharashtra State Electricity Distribution Company
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) One D.G. Set (320 KVA) for emergency power supply.
(e)Stack Height (in m) 10
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 0
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 30.89
    Total Land (ha.) 30.89
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 0
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 1868.31
(e)Settlements (ha.) 0
(f)Industrial (ha.) 0
(g)Forest (ha.) 3500
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : Fallow Land, Open Scurb, Open Jungle, Built Up, De 26029.7
    Total (ha.) 31398.010000000002
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Township0
(2.)Green belt7.0976
(3.)Ash Pond0
(4.)Quarry Area0
(5.)OB Dump Area0
(6.)Safety Zone0
(7.)Tailing Pond0
(8.)Water Reservoir0
(9.)Desalination Plant0
(10.)LandFill11.7158
(11.)Main Plant0.07Incineration facility
(12.)Area for Solid Waste Management0.432Haz. Waste Storage Area
(13.)Built Up Area0.074ETP Area
(14.)OthersRoad, Open To sky & Other area11.4972
Total (ha.) 30.8866
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)WLSNo WLS0-
(2.)ESAsno ESAs0-
(3.)CorridorsNo Corridors0-
(4.)Critically Polluted AreaNot Critically Polluted Area0-
(5.)ESZsNo ESZ0-
(6.)Wildlife CorridorsNo wildlife corridors0-
(7.)NPANo NPA0-
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Defence InstallationsNo Defense Installations sites present0-
(2.)Archaeological SitesNo Archaeological sites present0-
(3.)ForestNo Forest area is involved0-
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 0
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired NA
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Yet To Start
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? Yes
(i)Details of Water Bodies in Core Area Veena River
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Vyphadpitesur dam and reservoir
(ii)Direction of Water Bodies in Buffer Area North
(iii)Distance of Water Bodies in Buffer Area 7.40
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 10
(b)Permanent Employment-During Operation 5
(c)Temporary Employment- During Construction 5
(d)Temporary Employment- During Operation 0
(e)No. of working days 25
(f)Total Manpower 20
32.
Green Belt in Ha:
(a)Total Area of Green Belt 7.0976
(b)Percentage of Total Project Area 22.98
(c)No. of Plants to be Planted 3270
(d)Funds Allocated for Plantation 2035000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.       Project Benefits
S. No. Type of Project BenefitsDetails of Project Benefits
NIL
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For INFRA-2
S. No.Item Details
1.
Details of Building Construction:
(a)Maximum Height of the Building (Meters) 0
(b)Total No. of Flats to be Build 0
(c)No. of Buildings 0
(d)Total plot area (sqm) 0
(e)Total built up area (sqm) 0
2.
Foreshore Facilities and/or Marine Disposal:
(a)Whether Project Involves Foreshore Activities and/or marine Disposal? No
3.
Rain Water Harvesting:
(a)No. of Storage 0
(b)Capacity 0
(c)No. of Recharge Pits 0
(d)Capacity 0
4.
Parking:
(a)Details of 4 Wheeler/ 2 Wheeler Parking 2250 m2
5.
Energy Saving Measures:
(a)Source/Mode -
(b)Percentage 0
(c)Quantity 0
6.
Other details:
(a)Details of impact on Water Bodies and Drainage patters of catchment area Not Applicable
(b)Details of Traffic Density Impact Assessment and Modelling Study Copy of Details of Traffic Density Impact Assessment and Modelling Study
(c)In case Underground Tunnel Project below the Forest Land - Subsidence Impact Study report Copy of Underground Tunnel Project below the Forest Land - Subsidence Impact Study report
     7.       Type of Industries to be established with Industrial Estate as per their category A/B
S. No.Type of IndustryNo. of UnitsCategory A/B
NIL
8.
Length of the alignment N/A
9.
Details Bridges/ROB/Interchanges,Flyovers,Vehicle Underpass and Pedestrian Underpass
Details Not Applicable
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1922/RA 0122
(ii)Name of the EIA Consultant ENPRO Enviro Tech and Engineers Private Limited
(iii)Address 306, Royal Park, Nr. Deepa Complex, Adajan Road, Surat, Gujarat- 394230
(iv)Mobile No. 9181604837
(v)Landline No. 0261278613
(vi)Email Id enpro.eia@gmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation INFRA-2
(ix)Validity of Accreditation 12 Jan 2022
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File NA
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
      Essential Detail Sought : NIL
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantKishore Rajaram Malviya
DesignationGeneralManager
Name of Company (Applicant Name should not be given here)M/S. MAHARASHTRA ENVIRO POWER LTD.
AddressCHW-01, Butibori Industrial Area, Vil. Butibori-Hingna, Nagpur Maharashtra
Print