Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Proposed Dolomite and Limestone Mining Project, Kanubenahalli (V), Hodadurga (T), Chitradurga (D), Karnataka state
(b)Name of the Company / Organisation T K CHANDRAPPA
(c)Registered Address Part of Survey no 37 & 43, Kanubenahalli (V), Hosadurga(T), Chitradurga (D), Karnataka.,,Chitradurga,Karnataka-577527
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Chandrappa T K
(b)Designation (Owner/ Partner/ CEO) Mining Engineer
(c)Address 737, 4th main, 4th cross, Srinivasa Block, BEML layout, Rajarajeshwari Nagar, Bangalore, Karnataka,,Bangalore South,Bangalore Urban,Karnataka-560072
(d)Pin code 560072
(e)E-mail tkchandrappa@gmail.com
(f)STD Code. 80(f)Telephone No. 25444999
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity1(a) Mining of minerals
Minor Activity1(a) Mining of minerals
(b)Category A
(c)Proposal Number IA/KA/MIN/51650/2016
(d)Master Proposal Number(Single Window) SW/103115/2019
(e)EAC concerned (for category A Projects only) Non-Coal Mining
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Survey No 37 and 43
(b)Pincode 577533
(c)Bounded Latitudes (North)
From
Degree 13.7314
Minutes
Second
From
Degree 13.7583
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 76.4905
Minutes
Second
From
Degree 76.5058
Minutes
Second
(e)Survey of India Topo Sheet No. D43Q5, D43Q6, D43Q9, D43Q10
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 701
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 9.6
(j)Seismic Zone 2
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Karnataka
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)KarnatakaChitradurgaHosdurga
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number J-11015/121/2016-IA.II(M)
(b)Date of Apply of TOR 15 Mar 2016
(c)Date of Issue of TOR / Standard ToR 20 May 2016
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :08 Nov 2017
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :08 Dec 2017
Distance of Public Hearing Venue from the Proposed Project :3
Govt. Primary School, Kanubenahalli
State :Karnataka
District :Chitradurga
Tehsil :Hosdurga
Village :Kanubenahalli
50All the issues raised during Public hearing and action plan for the same is given in Annexure 3 and Annexure 4Deputy Commissioner
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Mining Activity174.02 haarea
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Limestone100000Tons per AnnumRoad
(2.)Dolomite50000Tons per AnnumRoad
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 60
(b) Funds Allocated for Environment Management (Capital) (in Crores) 9
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 1.2
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.12
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 1
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 1
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Iron Ore400OthersLitres per dayLocal MarketRoad5 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Oct 2016 To 28 Dec 2016
(b)Season Post-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 10
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM2.5Micro Gram per Meter Cube26.716.526.760
(2.)NOxMicro Gram per Meter Cube24.415.624.480
(3.)PM10Micro Gram per Meter Cube53.936.853.9100
(4.)SO2Micro Gram per Meter Cube15.96.815.980
(5.)OthersCOMicro Gram per Meter Cube5942855942000
    14.2.     No. of Ground Water monitoring locations : 10
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)TDSmg/l20835435002000
(2.)Total Hardnessmg/l684241200600
(3.)Chloridesmg/l380772501000
(4.)Fluoridemg/l1.200.511.01.5
(5.)Heavy MetalsIronmg/l0.250.20.30.3
(6.)OthersLeadmg/l0.010.010.010.01
(7.)TSSmg/l0000
(8.)pHNA8.17.16.58.5
    14.3.     No. of Surface Water monitoring locations : 02
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA7.87.8A
(2.)OthersTDSmg/l1264412C
(3.)BODmg/l123D
(4.)CODmg/l5218D
(5.)DOmg/l5.94.8B
    14.4.     No. of Ambient Noise monitoring locations : 10
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))53.451.8Industrial - 65, Residential - 55
(2.)Leq(Night)A-weighted decibels(dB(A))42.941.4Industrial - 65, Residential - 55
    14.5.     No. of Soil Sample Monitored locations : 10
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)N(Nitrogen)Kilogram per hectare320285
(2.)K(Potassium)Kilogram per hectare480287
(3.)Electric ConductivityOthersMicrosiemens per Centimeter17773
(4.)pH7.37.1
(5.)P(Phosphorus)Kilogram per hectare18.110.3
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 27 To 6
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 20 To 8
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersTankers112.25 Not Appliacble modeOthersWater TankersOthersTankers023 Apr 20190
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic44Soakpit/Septic tankGreen Belt Renewal Plant4
(2.)Vehicle Wash1010Oil and Grease Trap and Sedimentation TankGreen Belt Renewal Plant10
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 14
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 14
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Top Soil and Over burdenOthersTop soil and Over burder54104Tons0RoadOthersWill be used within the site
(2.)Domestic WasteMunicipal Solid Waste45Tons5RoadOthersMunicipal Bins
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM2.5Microgram per Meter Cube26.715.432.260
(2.)PM10Microgram per Meter Cube53.915.459.4100
(3.)NOxMicrogram per Meter Cube23.913.827.7180
(4.)SO2Microgram per Meter Cube15.910.1716.180
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)DG setHSD70.2SO20.01 g/s
(2.)DG SetHSD70.2PM100
(3.)DG setHSD70.2NOx0.22 g/s
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 250
(b)Source DG set
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 250 KVA DG Set
(e)Stack Height (in m) 7
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 0
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 174.02
(e)Other Land (ha.) 0
    Total Land (ha.) 174.02
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 0
(b)Waste/Barren Land (ha.) 173.7
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 0
(e)Settlements (ha.) 0
(f)Industrial (ha.) 0
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : Roads 0.32
    Total (ha.) 174.01999999999998
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Quarry Area77.35Mining Area
(2.)OB Dump Area10.10Dumping Area
(3.)Main Plant1.69Crushing and Screening plant
(4.)Built Up Area7.61Buildings and other utilities Area
(5.)Green belt3.27
(6.)OthersUnutilized/Unused Land74Balance area
Total (ha.) 174.02
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaNill10None in 10 km radius
(2.)WLSNill10None in 10 km radius
(3.)NPANill10None in 10 km radius
(4.)ESZsNill10None in 10 km radius
(5.)Wildlife CorridorsNill10None in 10 km radius
(6.)ESAsNill10None in 10 km radius
(7.)CorridorsNill10None in 10 km radius
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestMarikanava RF0.5Reserve Forest
(2.)Defence InstallationsNill10None in 10 km radius
(3.)Archaeological SitesNill10None in 10 km radius
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) Not Applicable
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 174.02
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired Acquired
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Kaggalakatte Lake
(ii)Direction of Water Bodies in Buffer Area West
(iii)Distance of Water Bodies in Buffer Area 1.5
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 20
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 79
(e)No. of working days 300
(f)Total Manpower 99
32.
Green Belt in Ha:
(a)Total Area of Green Belt 6.22
(b)Percentage of Total Project Area 3.57
(c)No. of Plants to be Planted 6000
(d)Funds Allocated for Plantation 2500000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)EnvironmentalOpening up new areas will reduce the stress/impact on existing mining leases and will lead to exploring mineral bodies. Proper exploration of mineral resources will delineate the quality/quantity and help to wrap up at the most suitable exploitation strategy for conserving the mineral and reducing waste handling. Limestone and Dolomite will be supplied to the steel plants and cement industries located in Karnataka
(2.)SocialHigher employment potential of the area. Higher infrastructure facilities in and around the project site. Better health care for the locality, as facilities available with the mine can become available to the community including special camps to be arranged. Better admixture of cultures will result in preservation of the cultural heritage of the area and also will result in better appreciation of different cultures of the people from such diverse areas/localities. The company in the field of s
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For Non-Coal Mining
S. No.Item Details
     1.       No. of Mineral(s) to be Mined : 2
S. No.Mineral(s) to be Mined Major or Minor Mineral
(1.)DolomiteMinor
(2.)LimestoneMajor
2.
Mine Capacity in ROM (Run of Mine) 1.5 Lakhs TPA
3.
Uploaded 500 meters Cluster Certificate from State Mines and Geology in case of minor minerals Copy of 500 meters Cluster Certificate from State Mines and Geology
4.
Mining Plan:
(a)Approval Letter No. 279/1053/2011/BNG
(b)Date of Approval 29 Nov 2010
(c)Approved Letter Copy of Approved Letter
(d)Approved By State Mining and Geology Department IBM
(e)Approved Mining Lease Area 174.02
(f)Approved Capacity 150000
5.
Technical Details:
(a)Total Geological Reserves (Million Ton) 9085568
(b)Mineable Reserves (Million Ton) 8770432
(c)Extractable Reserves(Million Ton) 8770432
(d)Percent(%) of Extraction 100
(e)Grade of Coal /Ore /Mineral Limestone and Dolomite
(f)Stripping Ratio 1 : 0.35
(g)Category of Gaseousness (Only for Coal Mining, Others may Write NA) NA
(h)Average Gradient(Degree) NA
(i)Mining Method Opencast
(j)Life of Mine (Years) 63
6.
Details of Beneficiations:
(a)Whether it is proposed to install beneficiation plant/Coal washery within the mining lease area Yes
(b)Beneficiation / Washing Technology Benefication
(c)Capacity 100
(d)Whether it is proposed to install crusher within the mining lease area Yes
(e)No. of crushers 1
     6.1.    Details of crusher:
S. No.Crusher ID Capacity (in PH)Remarks
(1.)1100 Tons/hr
7.
Details of Seams:
(a)Whether details of seam applicable No
8.
Details of Mining Lease:
(a)Mining Lease Area (in Hectare) 174.02
(b)Whether obtained Letter of Intent (LOI) from the state government ? Yes
(i)Copy of Letter of Intent Copy of Letter of Intent
(ii)Date of issue of LOI 14 Jun 2010
(iii)Validity of LOI 20
(iv)Reference No. of LOI DMG:MLS:22 AML 2009/3888
(c)Whether Lease Deed Executed ? Yes
(i)Copy of Executed Lease deed valid as on Date Copy of Executed Lease deed
(ii)Provide area in Hectare as per executed lease deed (initial) document 174.02
(iii)Validity of the lease deed From : 13 Dec 2006 To : 14 Dec 2008
(iv)Date of Execution of Mining Lese 12 Jan 2009
(v)Reference Number DGM 22/AML/2009/12566
(d)Whether Lease Deed Renewed ? No
(i)Reason thereof NA
9.
OB (Over Burden) Management:
(a) Details of External Dumps:
(i)No. of OB Dumps 0
(ii)Total Area (in Hectare) 0
(iii)Height (in meter) 0
(iv)Quantity (in Million Cubic meter) 0
(v)No. of year back fill up 0
(b) Details of Internal Dumps:
(i)No. of Internal Dumps 2
(ii)Total Area (in Hectare) 10.10
(iii)Height (in meter) 20
(iv)Quantity (in Million Cubic meter) 2.014
10.
Details of Topsoil Management:
(a)Quantity of Topsoil excavated during the entire life of the mine (in Million Cubic metre) 0.02
(b)Quantity of Topsoil proposed for utilization for reclamation during the entire life of the mine (in Million Cubic metre) 0.02
(c)Quantity of Topsoil proposed for utilization for other activities during the entire life of the mine (in Million Cubic metre) 0
11.
Details of Final Mine Void:
(a)Area (in Hectare) 77.35
(b)Depth (in meter) 10
(c)Volume (in Million Cubic meter) 0.42
12.
Details of Quarry:
(a)Final Void of 0 (hectare) at a Depth of 0 meter which is Proposed to be Converted into a Water Body.
(b)Total Quarry Area (ha) 0
13.
Details of Transportation:
(a)In Pit/Underground to Surface NA
(b)Surface to Siding/Loading NA
(c)Transportation / Conveyor Details Transportation via Trucks
     14.      Details of Land Usage (Pre-Mining)
S. No.LAND USE Other LAND USEWITHIN ML AREA (Hectare)OUTSIDE ML AREA (Hectare)TOTAL (Hectare)
(1.)AGRICULTURE LAND000
(2.)FOREST LAND000
(3.)WASTE LAND000
(4.)GRAZING LAND000
(5.)SETTLEMENTS000
(6.)OTHERS(Specify)Revenue Land174.020174.02
(7.)SURFACE WATER BODIES000
TOTAL174.020174.02
     15.      Details of Land Usage (Post-Mining)
S. No.LAND USE Other LAND USEPlantation (ha)Water Body (ha)Public Use (ha)Undisturbed (ha)Total
(1.)EXCAVATION/QUARRY77.350077.35
(2.)TOP SOIL STORAGE1.09001.09
(3.)ROADS0.48000.48
(4.)GREEN BELT3.27003.27
(5.)BUILT UP AREA (COLONY/OFFICE)7.73007.73
(6.)EXTERNAL OB DUMPS0000
(7.)INTERNAL OB DUMPS10.100010.1
(8.)VIRGIN AREA740074
TOTAL174.02000174.02
16.
Details of Reclamation:
Total Afforestation Plan shall be Implemented Covering of Mining.
This will Include:
(a)External OB Dump(in hectare) 0
(b)Internal Dump(in hectare) 10.10
(c)Quarry(in hectare) 77.35
(d)Safety Zone(in hectare) 0
(e)Final Void of 77.35 (hectare) at a Depth of 10 meter which is Proposed to be Converted into a Water Body.
(f)Density of Tree Plantation per ha (in no.) 2000
(g)Others in ha (such as Excavation Area along ML Boundary, along Roads and Infrastructure, Embankment Area and in Township Located Outside the Lease etc) 0
(h)Total afforestation plant (in hectare) 3.27
17.
Status of progressive Mining Closure Plan:
Details Not Applicable
     18.      Details of Actual Coal/ ORE Production vis-a-vis Sanctioned Capacity since the Inception:
S. No.Financial Year Sanctioned Capacity as per EC (MTPA)Sanctioned Capacity as per CTOSanctioned Capacity as per approved mining planActual Production Excess Production Beyond the EC / CTO/ Mining Plan Sanctioned Capacity (MTPA)
(1.)000000
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1518/SA 061
(ii)Name of the EIA Consultant Ramky Enviro Services Private Limited
(iii)Address Ramky Grandiose, Ramky Towers complex, Gachibowli, Hyderabad
(iv)Mobile No. 9949991029
(v)Landline No. 0402301535
(vi)Email Id vvijaykumar@ramky.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Non-Coal Mining
(ix)Validity of Accreditation 20 May 2019
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Copy of District Survey Report Copy of District Survey Report
(h)Uploaded Copy of Replenishment Study Report & Baseline Survey Data Copy of Replenishment Study Report & Baseline Survey Data
(i)Uploaded Additional File Copy of Additional File
(j)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAPlease submit the following: 1) Upload the full Mining Plan 2) Copy of affidavit needs to be submitted by PP in compliance of the Ministry’s OM no. 3-50/2017-IA.III (Pt.), dated 30th May 2018. 08 May 2019
2.NAThe correction have been made as per the instruction received 13 May 2019
3.NAYou are requested to submit the following documents 1. Kindly submit the District Survey Report for Dolomite minor mineral as per Ministry Notification S. O. No. 3611 (E) dated 25th July 2018. 2. Mining plan for 174.20 ha, however, lease deed for 174.02 ha. Please submit the mining plan for 174.02 ha. 10 Jun 2019
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantChandrappa T K
DesignationMining Engineer
Name of Company (Applicant Name should not be given here)T K CHANDRAPPA
AddressPart of Survey no 37 & 43, Kanubenahalli (V), Hosadurga(T), Chitradurga (D), Karnataka.
Print