Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Establishment of Molasses / Grain based distillery having capacity 160.0 KLD molasses based or 120.0 KLD molasses based + 40.0 KLD Grain based distillery (unit – 2) at village: Bhikki, Dhandheda, Sikh
(b)Name of the Company / Organisation TRIVENI ENGINEERING AND INDUSTRIES LTD
(c)Registered Address 8th Floor, Express Trade Towers, 15 - 16, Sector - 16 - A, Noida, Distt : GB Nagar (UP),,Bulandshahr,Uttar Pradesh-201301
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Ashish Awasthi
(b)Designation (Owner/ Partner/ CEO) Generalmanager
(c)Address Vill.-Sabitgarh, PO - Karora, Teh.- Khurja, Distt - Bulandshahr,,Khurja,Bulandshahr,Uttar Pradesh-203129
(d)Pin code 203129
(e)E-mail aksinghal@ho.trivenigroup.com
(f)STD Code. 120(f)Telephone No. 4308000
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity5(g) Distilleries
Minor Activity
(b)Category A
(c)Proposal Number IA/UP/IND2/72081/2018
(d)Master Proposal Number(Single Window) SW/102403/2019
(e)EAC concerned (for category A Projects only) Industrial Projects - 2
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Village Bhikki : 1, 7, 8, 9, 10, 11, 12, 13, 14, 1
(b)Pincode 251203
(c)Bounded Latitudes (North)
From
Degree 29.25
Minutes
Second
From
Degree 29.26
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 77.46
Minutes
Second
From
Degree 77.46
Minutes
Second
(e)Survey of India Topo Sheet No. 53G/10, 53G/11, 53G/15 and 53G/14
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 251
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 18.31
(j)Seismic Zone 4
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Uttar Pradesh
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)Uttar PradeshMuzaffarnagarMuzaffarnagar
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number IA-J-11011/14/2018-IA-II(I)
(b)Date of Apply of TOR 05 Jan 2018
(c)Date of Issue of TOR / Standard ToR 10 Feb 2018
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :24 Nov 2018
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :27 Dec 2018
Distance of Public Hearing Venue from the Proposed Project :0.1
Project Site
State :Uttar Pradesh
District :Muzaffarnagar
Tehsil :Muzaffarnagar
Village :Bhikki, Dhandheda, Sikhreda
89People ask question about water pollution, air pollution related to the proposed project. Employment Opportunities.OthersAdditional District Magistrate
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)CO gen Power Plant7.0 MW
(2.)Fermentation and Distillation Unit160.0 KLDBased on Molasses and grain
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)RS/ENA/AA160.0Kilo Litre per DayRoad
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 200
(b) Funds Allocated for Environment Management (Capital) (in Crores) 56.0
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 5
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 3.2
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 252000.0
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 252000
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Molasses as raw material for distillery252000Tons per Annumfrom nearby sugar millsRoad50 OthersNACopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Jan 2018 To 31 Mar 2018
(b)Season Winter
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 08
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube89.056.488.8100
(2.)PM2.5Micro Gram per Meter Cube51.432.450.960
(3.)NOxMicro Gram per Meter Cube27.314.026.180
(4.)SO2Micro Gram per Meter Cube24.810.423.480
    14.2.     No. of Ground Water monitoring locations : 08
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA7.67.17.58.5
(2.)TDSmg/l492.8344.75002000
(3.)Total Hardnessmg/l316.0248.0200600
(4.)OthersAlkalinitymg/l332.0264.0200600
(5.)Fluoridemg/l0.520.281.01.5
(6.)TSSmg/l0000
(7.)Chloridesmg/l48.0526.022501000
(8.)Heavy MetalsIron as Femg/l0.190.130.30.3
    14.3.     No. of Surface Water monitoring locations : 08
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA7.77.2C
(2.)DOmg/l5.24.7C
(3.)CODmg/l60.217.4D
(4.)BODmg/l16.45.7D
    14.4.     No. of Ambient Noise monitoring locations : 08
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))52.451.065.0
(2.)Leq(Night)A-weighted decibels(dB(A))44.443.355
    14.5.     No. of Soil Sample Monitored locations : 08
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pH7.87.4
(2.)N(Nitrogen)Milligram per Kilogram28.7623.24
(3.)P(Phosphorus)Milligram per Kilogram154.0109.9
(4.)K(Potassium)Milligram per Kilogram89.355.2
(5.)Electric ConductivityOthersMicro Seimens308248
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 7.5 To 9.5
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 6.5 To 7.6
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater9600.1Copy of Permission LetterPipelineTube Well21-4/6640/UP/IND/2018-39012 Mar 20191172
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Fermentation and Distillation (Mode - 1)10801400Spent wash will be concentrated in MEE then concentrate from MEE will be incinerated in slop fired boiler along with BagasseOthersIncineration588492
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 1080
(b)Total Discharged Water (Kilolitre per Day) 492
(c)Total Reused Water (Kilolitre per Day) 588
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Fly ash (mode - 2)Fly Ash59.3Tons0.5Pipe ConveyorOthersDue to high potash content, used as manure.
(2.)Yeast SludgeIndustrial Waste16.0Tons0..2OthersPipeOthersUsed as Manure
(3.)Fly ash ( Mode - 1)Fly Ash67.5Tons0.5Pipe ConveyorOthersDue to high potash content, used as manure.
(4.)Cattle Feed DDGS (Mode - 2 Only)Industrial Waste18.0Tons0.3OthersPipeOthersUsed as Cattle feed
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube88.86432.2391.04100
(2.)SO2Microgram per Meter Cube26.47511.2327.6480
(3.)NOxMicrogram per Meter Cube26.16031.0427.1580
(4.)PM2.5Microgram per Meter Cube50.98000.4851.3860
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)60.0 TPH Boiler Slop firedSlop + Bagasse604.2PM103.89
(2.)60.0 Boiler Slop firedSlop + bagasse604.2NOx3.8
(3.)60.0 TPH boiler Slop firedSlop + Bagasse604.2SO29.54
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 2250.0
(b)Source Inhouse
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 1000 KVA ( 01 No) and 500 KVA ( 01 No)
(e)Stack Height (in m) 16
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0.0
(b)Private Land (ha.) 12.47
(c)Government Land (ha.) 0.0
(d)Revenue Land (ha.) 0.0
(e)Other Land (ha.) 0.0
    Total Land (ha.) 12.47
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 25800
(b)Waste/Barren Land (ha.) 1000.0
(c)Grazing/ Community Land (ha.) 320.0
(d)Surface Water Bodies (ha.) 54
(e)Settlements (ha.) 3500.0
(f)Industrial (ha.) 30.5
(g)Forest (ha.) 305.0
(h)Mangroves (ha.) 0.0
(i)Marine Area (ha.) 0.0
(j)Others (ha.) : Decidious 139
    Total (ha.) 31148.5
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Green belt4.12
(2.)Ash Pond0.5
(3.)Safety Zone0.4
(4.)Main Plant4.5
(5.)Area for Solid Waste Management1.4
(6.)Othersparking1.2
(7.)Township0.35
Total (ha.) 12.47
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaNo0No any
(2.)WLSNo0No any
(3.)ESAsNo0No Any
(4.)CorridorsNo0No Any
(5.)NPANo0No Any
(6.)ESZsNo0No Any
(7.)Wildlife Corridorsno0No Any
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestNo0No Any
(2.)Archaeological SitesNo0No Any
(3.)Defence InstallationsNo0No Any
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 12.47
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired 0
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Kaali River
(ii)Direction of Water Bodies in Buffer Area West
(iii)Distance of Water Bodies in Buffer Area 9.90
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 20
(b)Permanent Employment-During Operation 60
(c)Temporary Employment- During Construction 40
(d)Temporary Employment- During Operation 28
(e)No. of working days 365
(f)Total Manpower 148
32.
Green Belt in Ha:
(a)Total Area of Green Belt 4.11
(b)Percentage of Total Project Area 32.96
(c)No. of Plants to be Planted 6150
(d)Funds Allocated for Plantation 1500000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)Environmental1. Out of the total project area of 12.47 Hectare, 4.11 Hectare (33%) will be utilized for green belt development. Green belt development in and around the project site will help to attenuate the pollution level. 2. Native species will be given priority for Avenue plantation.
(2.)Social1 Self-Employment Training Programs. 2. Covering all nearby eligible village youths. 3. Assistance for self-employment. 4. Assistance through social forestry programme. 5. Active participation in renovation of school, temple, community centre as per requirement in nearby areas of Project site. 6. Support in infrastructure development of Hospitals of nearby areas. 7. Active participation in facilitating drinking water in summer season.
(3.)FinancialTriveni Engineering & Industries Ltd, will actively contribute to improve the economic conditions of the area by providing direct and indirect employment for local persons preferable from the nearby villages. Also because of the increasing market demand, the proposed project would contribute to the excise and revenue of the country.
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1619/SA - 056
(ii)Name of the EIA Consultant Ascenso Enviro Pvt Limited
(iii)Address D - 79, Sector - 6, Noida
(iv)Mobile No. 9897674227
(v)Landline No. 9897674227
(vi)Email Id ETRCLTH@yahoo.in
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 03 Oct 2019
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NA- Please check ambient air quality values mentioned in column 14.1 of Form-2, and also the projected ones in column 18.1 of Form-2. - Permission required for ground water withdrawal of 960 cum/day, and also 183 cum/day from DJB. 20 Apr 2019
2.NAThe correction have been made as per the instruction received 21 Apr 2019
3.NAStill no prediction for PM2.5 to be reflected in column 18.1 of Form-2. 28 Apr 2019
4.NAThe correction have been made as per the instruction received 04 May 2019
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantAshish Awasthi
DesignationGeneralmanager
Name of Company (Applicant Name should not be given here)TRIVENI ENGINEERING AND INDUSTRIES LTD
Address8th Floor, Express Trade Towers, 15 - 16, Sector - 16 - A, Noida, Distt : GB Nagar (UP)