Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Redevelopment of campus for national school of drama
(b)Name of the Company / Organisation CENTRAL PUBLIC WORKS DEPARTMENT DELHI
(c)Registered Address GVBPD, CPWD,,Central,Delhi-110011
(d)Legal Status of the Company Central Government
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Nilabh Gupta
(b)Designation (Owner/ Partner/ CEO) EE
(c)Address GVBPD, CPWD,,Darya Ganj,Central,Delhi-110011
(d)Pin code 110011
(e)E-mail nsddelhi01@gmail.com
(f)STD Code. 120(f)Telephone No. 4352889
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity8(a) Building and Construction projects
Minor Activity1(a) Mining of minerals
(b)Category B2
   Reason for Applying at Ministry SEIAA
(c)Proposal Number IA/DL/MIS/102396/2019
(d)Master Proposal Number(Single Window) SW/102395/2019
(e)EAC concerned (for category A Projects only) INFRA-2
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. bhawalpur house bhagwandas road
(b)Pincode 110001
(c)Bounded Latitudes (North)
From
Degree 28373145
Minutes
Second
From
Degree 28373446
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 7714327
Minutes
Second
From
Degree 7714329
Minutes
Second
(e)Survey of India Topo Sheet No. 53N
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 400
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 1
(j)Seismic Zone 4
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Delhi
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR):
(a)Whether TOR is mandatory for submitting application No
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason it is building construction project
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)no0no
(2.)no0no
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)no product0Tons per AnnumRoad
(2.)no0Tons per AnnumRoad
(3.)no0Tons per AnnumRoad
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 14 Mar 2019
(iv)Valid Upto 02 Feb 2021
(v)File No. 123
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 212.36
(b) Funds Allocated for Environment Management (Capital) (in Crores) 2.1
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 1.59
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.53
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 0
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 0
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)cement5889Tons per AnnumindiaRoad1 Open MarketCopy of Linkage
(2.)cement5789Tons per AnnumindiaRoad5 Open MarketCopy of Linkage
(3.)Water1Million Liters per DayindiaPipe Conveyor1 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Mar 2019 To 31 Mar 2019
(b)Season Summer
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 1
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube26014398100
(2.)PM2.5Micro Gram per Meter Cube109495660
(3.)SO2Micro Gram per Meter Cube22.319.517.580
(4.)NOxMicro Gram per Meter Cube69.748.25280
    14.2.     No. of Ground Water monitoring locations : 1
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA7.627.628.58.5
(2.)Total Hardnessmg/l490489200600
(3.)Chloridesmg/l3103072501000
(4.)Fluoridemg/l0.90.811.5
(5.)Heavy Metalsasmg/l0.0030.0010.010.05
(6.)TDSmg/l112011005002000
(7.)TSSmg/l120010855002000
    14.3.     No. of Surface Water monitoring locations : 1
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)DOmg/l86B
(2.)pHmg/l7.897.65B
(3.)CODmg/l358350C
(4.)BODmg/l205202C
    14.4.     No. of Ambient Noise monitoring locations : 1
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))42.640.155
(2.)Leq(Day)A-weighted decibels(dB(A))54.45265
    14.5.     No. of Soil Sample Monitored locations : 1
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pH7.86.2
(2.)Electric ConductivityMilligram per Litre123112
(3.)N(Nitrogen)Kilogram per hectare2315
(4.)P(Phosphorus)Kilogram per hectare1211
(5.)K(Potassium)Milligram per Kilogram210208
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 18 To 20
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 14 To 16
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersDJB1835Copy of Permission LetterPipelineOthersDJB connection12305 Feb 2019183
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)wastewater83100STPReuse within the Plant & Recycling83
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 83
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 83
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)domesticMunicipal Solid Waste0.3Tons2RoadAuthorized Recyclers
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube143298290100
(2.)PM2.5Microgram per Meter Cube11228531160
(3.)SO2Microgram per Meter Cube122204580
(4.)NOxMicrogram per Meter Cube10252080
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)dg setdiesel230.3PM100.5
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 1974
(b)Source BSES
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 2520
(e)Stack Height (in m) 40
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 0
(c)Government Land (ha.) 2.75
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 2.75
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 0
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 0
(e)Settlements (ha.) 0
(f)Industrial (ha.) 0
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : Govt. land 2.75
    Total (ha.) 2.75
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Othersplot area2.75
Total (ha.) 2.75
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)NPAnone100none
(2.)Wildlife Corridorsnone60none
(3.)ESZsnone50none
(4.)WLSnone16none
(5.)Critically Polluted AreaKirti Nagar Industrial Area9none
(6.)ESAsnone70none
(7.)Corridorsnone60none
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestCentral Ridge Forest5.47none
(2.)Defence Installationsnone0none
(3.)Archaeological Sitesred fort3.5none
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 82
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 0
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired 0
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? No
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 50
(b)Permanent Employment-During Operation 190
(c)Temporary Employment- During Construction 50
(d)Temporary Employment- During Operation 100
(e)No. of working days 265
(f)Total Manpower 390
32.
Green Belt in Ha:
(a)Total Area of Green Belt 1.22
(b)Percentage of Total Project Area 44.36
(c)No. of Plants to be Planted 450
(d)Funds Allocated for Plantation 200000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)Environmentalgreen building, wastewater treatment, groundwater recharge
(2.)Socialcultural activity
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For INFRA-2
S. No.Item Details
1.
Details of Building Construction:
(a)Maximum Height of the Building (Meters) 40
(b)Total No. of Flats to be Build 80
(c)No. of Buildings 6
(d)Total plot area (sqm) 27592.58
(e)Total built up area (sqm) 37665.23
2.
Foreshore Facilities and/or Marine Disposal:
(a)Whether Project Involves Foreshore Activities and/or marine Disposal? No
3.
Rain Water Harvesting:
(a)No. of Storage 0
(b)Capacity 0
(c)No. of Recharge Pits 6
(d)Capacity 25.12
4.
Parking:
(a)Details of 4 Wheeler/ 2 Wheeler Parking 400
5.
Energy Saving Measures:
(a)Source/Mode solar
(b)Percentage 1
(c)Quantity 19.72
6.
Other details:
(a)Details of impact on Water Bodies and Drainage patters of catchment area no
(b)Details of Traffic Density Impact Assessment and Modelling Study Copy of Details of Traffic Density Impact Assessment and Modelling Study
(c)In case Underground Tunnel Project below the Forest Land - Subsidence Impact Study report Copy of Underground Tunnel Project below the Forest Land - Subsidence Impact Study report
     7.       Type of Industries to be established with Industrial Estate as per their category A/B
S. No.Type of IndustryNo. of UnitsCategory A/B
NIL
8.
Length of the alignment N/A
9.
Details Bridges/ROB/Interchanges,Flyovers,Vehicle Underpass and Pedestrian Underpass
Details Not Applicable
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1518-III A
(ii)Name of the EIA Consultant Amaltas Enviro Industrial consultant
(iii)Address Noida
(iv)Mobile No. 9810085736
(v)Landline No. 0120435288
(vi)Email Id gilbertmervyn@gmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation INFRA-2
(ix)Validity of Accreditation 27 Dec 2019
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAKindly submit the following: (i) Upload Form-1, 1-A and Conceptual plan altogether in a single pdf file. (ii) Plan for Corporate Environment Responsibility (CER) as specified under Ministry’s Office Memorandum vide F.No. 22-65/2017-IA.III dated 1st May 2018. (iii) Details of the Consultant and Certificate of Accreditation issued by QCI. 02 May 2019
2.NAThe correction have been made as per the instruction received 09 May 2019
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantNilabh Gupta