Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Hatgacha-Jethia Black Stone Mines
(b)Name of the Company / Organisation WEST BENGAL MINERAL DEVELOPMENT AND TRADING CORPORATION LIMITED
(c)Registered Address 13, NELLIE SENGUPTA SARANI 2ND FLOOR, KOLKATA nlin,,Kolkata,West Bengal-700087
(d)Legal Status of the Company State PSU
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant KRISHNENDU SADHUKHAN
(b)Designation (Owner/ Partner/ CEO) MANAGING DIRECTOR
(c)Address 13, NELLIE SENGUPTA SARANI 2ND FLOOR, KOLKATA,,,Kolkata,West Bengal-700087
(d)Pin code 700087
(e)E-mail wbmdtcltd@gmail.com
(f)STD Code. 33(f)Telephone No. 22522170
(g)Fax No. 22521653
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity1(a) Mining of minerals
Minor Activity
(b)Category A
(c)Proposal Number IA/WB/MIN/62270/2015
(d)Master Proposal Number(Single Window) SW/102130/2019
(e)EAC concerned (for category A Projects only) Non-Coal Mining
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. 1506,1606,1607,1608,1609,1611,1613,1614 to 1623,16
(b)Pincode 731216
(c)Bounded Latitudes (North)
From
Degree 24.11515278
Minutes
Second
From
Degree 24.12132778
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 87.58888889
Minutes
Second
From
Degree 87.60027778
Minutes
Second
(e)Survey of India Topo Sheet No. 72 P/12
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 74
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 5
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project West Bengal
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)OrissaKendujharBarbilThakurani
(2.)West BengalBirbhumMohammad Bazar
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number J-11015/379/2015-IA.II(M)
(b)Date of Apply of TOR 11 May 2015
(c)Date of Issue of TOR / Standard ToR 30 Nov 2015
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :06 Aug 2016
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :09 Sep 2016
Distance of Public Hearing Venue from the Proposed Project :3.6
Premises of Barkata GP Office
State :West Bengal
District :Birbhum
Tehsil :Mohammad Bazar
Village :Barkata
200repairing of road, drinking water facility, construction of girls's hostel, installation of transformer, ,etcOthersAdditional District Magistrate (General)
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)MLarea 71.2 ha.0.8 miilion TPA (RoM)opencast semimechanized mining
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)blackstone800000Tons per AnnumRoad
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 14.36
(b) Funds Allocated for Environment Management (Capital) (in Crores) 1.8
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.29
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.44
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? Yes
d)Inter-State boundaries and international boundaries Yes
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 1.15
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 1.15
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Diesel1.15Kilo Litre per DayMollarpurRoad12 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Dec 2015 To 29 Feb 2016
(b)Season Winter
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube65.546.065.4100
(2.)NOxMicro Gram per Meter Cube18.29.018.280
(3.)PM2.5Micro Gram per Meter Cube33.123.533.060
(4.)SO2Micro Gram per Meter Cube14.44.014.280
    14.2.     No. of Ground Water monitoring locations : 4
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)TSSmg/l0000
(2.)pHNA7.16.76.56.5
(3.)TDSmg/l148825002000
(4.)Total Hardnessmg/l8448300600
(5.)Fluoridemg/l0.10.0511.5
(6.)Chloridesmg/l29.9916.992501000
    14.3.     No. of Surface Water monitoring locations : 4
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA7.86.9C
(2.)DOmg/l6.15.1C
(3.)BODmg/l2.82.4C
(4.)CODmg/l00C
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))53.249.555
(2.)Leq(Night)A-weighted decibels(dB(A))42.034.745
    14.5.     No. of Soil Sample Monitored locations : 4
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)N(Nitrogen)Kilogram per hectare450340
(2.)Electric ConductivityMillisiemens per Centimetre274161
(3.)P(Phosphorus)Kilogram per hectare4224
(4.)K(Potassium)Kilogram per hectare235166
(5.)pH6.56.2
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 37 To 39
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 32 To 34
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater20Copy of Permission LetterPipelineTube WellP0308004000000026401TSE20 Oct 20162
(2.)Otherssettling pond130 Not Appliacble PipelineOtherspumping from pondnil12 Apr 201913
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)sanitary waste water10soak pitOthersseptic tank01
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 1
(b)Total Discharged Water (Kilolitre per Day) 1
(c)Total Reused Water (Kilolitre per Day) 0
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Over BurdenOthersOB293400Tons0RoadOthersdump
(2.)crusher dustIndustrial Waste197900Tons0.2RoadCo-Processing
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM2.5Microgram per Meter Cube28.60.50.1728.7860
(2.)NOxMicrogram per Meter Cube14.60.50.2414.8580
(3.)PM10Microgram per Meter Cube57.80.50.2958.09100
(4.)SO2Microgram per Meter Cube10.40.5010.4180
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)not applicablenot applicable00Othersnot applcable0
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 285
(b)Source from state grid
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 500 KVA
(e)Stack Height (in m) 30
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 50.00
(c)Government Land (ha.) 21.20
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 71.2
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 50.00
(b)Waste/Barren Land (ha.) 12.11
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 1.56
(e)Settlements (ha.) 0
(f)Industrial (ha.) 0
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : road, plantation, etc 7.53
    Total (ha.) 71.2
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Quarry Area21.66
(2.)OB Dump Area5.05
(3.)Safety Zone2.6
(4.)Built Up Area0.35
(5.)Water Reservoir0.42
(6.)Otherstop soil, waste, rejects, road, etc41.12
Total (ha.) 71.2
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)NPANA0beyond 10km
(2.)ESAsNA0beyond 10km
(3.)ESZsNA0beyond 10km
(4.)CorridorsNA0beyond 10km
(5.)WLSBallavpur wildlife sanctuary48in SSE direction
(6.)Wildlife CorridorsNA0beyond 10km
(7.)Critically Polluted AreaNA0beyond 10km
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestMaubellia RF4.9in SE
(2.)Archaeological SitesNA0beyond 10km
(3.)Defence InstallationsNA0beyond 10km
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 0
(b)Land yet to be acquired(Ha) 71.2
(c)Status of Land acquisition if not acquired in progress
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 2
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 218
(e)Funds Allocated for R&R(in INR) (in Lacs) 13
(f)Status of R&R Yet To Start
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? Yes
(i)Details of Water Bodies in Core Area a perennial nala, which is flowing in the western part of the lease area from south to north along with one of its tributary and finally drains into Ghaghar nala
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Dwarka river
(ii)Direction of Water Bodies in Buffer Area South West
(iii)Distance of Water Bodies in Buffer Area 5.6
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 102
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 0
(e)No. of working days 210
(f)Total Manpower 102
32.
Green Belt in Ha:
(a)Total Area of Green Belt 34.1
(b)Percentage of Total Project Area 47.89
(c)No. of Plants to be Planted 54560
(d)Funds Allocated for Plantation 8800000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)FinancialRoyalty and taxes are to be paid to the State Govt.; waste materials for construction & maintenance road
(2.)EnvironmentalFor screening of dust and attenuation of noise, plantation shall be raised; rain water harvesting and ground water recharge by settling pond;
(3.)SocialDirect and indirect employment opportunity, positive and beneficial impacts by way of economic improvements, transportation, aesthetic environment and business generation,
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For Non-Coal Mining
S. No.Item Details
     1.       No. of Mineral(s) to be Mined : 1
S. No.Mineral(s) to be Mined Major or Minor Mineral
(1.)BlackstoneMinor
2.
Mine Capacity in ROM (Run of Mine) 0.8 million TPA
3.
Uploaded 500 meters Cluster Certificate from State Mines and Geology in case of minor minerals Copy of 500 meters Cluster Certificate from State Mines and Geology
4.
Mining Plan:
(a)Approval Letter No. 236/CMO/XVI/91(109)
(b)Date of Approval 28 Jul 2014
(c)Approved Letter Copy of Approved Letter
(d)Approved By State Mining and Geology Department State
(e)Approved Mining Lease Area 71.2
(f)Approved Capacity 800000
5.
Technical Details:
(a)Total Geological Reserves (Million Ton) 218.5128
(b)Mineable Reserves (Million Ton) 196.66152
(c)Extractable Reserves(Million Ton) 167.162292
(d)Percent(%) of Extraction 85
(e)Grade of Coal /Ore /Mineral Blackstone
(f)Stripping Ratio 1 : 0.18
(g)Category of Gaseousness (Only for Coal Mining, Others may Write NA) NA
(h)Average Gradient(Degree) 60
(i)Mining Method Opencast
(j)Life of Mine (Years) 208
6.
Details of Beneficiations:
(a)Whether it is proposed to install beneficiation plant/Coal washery within the mining lease area No
(b)Whether it is proposed to install crusher within the mining lease area Yes
(c)No. of crushers 1
     6.1.    Details of crusher:
S. No.Crusher ID Capacity (in PH)Remarks
(1.)1200
7.
Details of Seams:
(a)Whether details of seam applicable No
8.
Details of Mining Lease:
(a)Mining Lease Area (in Hectare) 71.2
(b)Whether obtained Letter of Intent (LOI) from the state government ? Yes
(i)Copy of Letter of Intent Copy of Letter of Intent
(ii)Date of issue of LOI 16 Dec 2010
(iii)Validity of LOI 20
(iv)Reference No. of LOI 1021-CI/O/MM/42/10/Mines
(c)Whether Lease Deed Executed ? No
(i)Reason thereof after EC
(d)Whether Lease Deed Renewed ? No
(i)Reason thereof NA
9.
OB (Over Burden) Management:
(a) Details of External Dumps:
(i)No. of OB Dumps 0
(ii)Total Area (in Hectare) 0
(iii)Height (in meter) 0
(iv)Quantity (in Million Cubic meter) 0
(v)No. of year back fill up 0
(b) Details of Internal Dumps:
(i)No. of Internal Dumps 1
(ii)Total Area (in Hectare) 5.05
(iii)Height (in meter) 30
(iv)Quantity (in Million Cubic meter) 1.08
10.
Details of Topsoil Management:
(a)Quantity of Topsoil excavated during the entire life of the mine (in Million Cubic metre) 0.21
(b)Quantity of Topsoil proposed for utilization for reclamation during the entire life of the mine (in Million Cubic metre) 0
(c)Quantity of Topsoil proposed for utilization for other activities during the entire life of the mine (in Million Cubic metre) 0.21
11.
Details of Final Mine Void:
(a)Area (in Hectare) 21.66
(b)Depth (in meter) 30
(c)Volume (in Million Cubic meter) 6498000
12.
Details of Quarry:
(a)Final Void of 21.66 (hectare) at a Depth of 30 meter which is Proposed to be Converted into a Water Body.
(b)Total Quarry Area (ha) 21.66
13.
Details of Transportation:
(a)In Pit/Underground to Surface 28 ton tippers & 20 ton dump trucks will bring the
(b)Surface to Siding/Loading The tippers & dumpers will transport the Blackston
(c)Transportation / Conveyor Details The dumpers will transport the Blackstone from sta
     14.      Details of Land Usage (Pre-Mining)
S. No.LAND USE Other LAND USEWITHIN ML AREA (Hectare)OUTSIDE ML AREA (Hectare)TOTAL (Hectare)
(1.)AGRICULTURE LAND50.00050
(2.)SURFACE WATER BODIES1.5601.56
(3.)OTHERS(Specify)road, plantation, etc7.5307.53
(4.)WASTE LAND12.11012.11
(5.)FOREST LAND000
(6.)SETTLEMENTS000
(7.)GRAZING LAND000
TOTAL71.2071.2
     15.      Details of Land Usage (Post-Mining)
S. No.LAND USE Other LAND USEPlantation (ha)Water Body (ha)Public Use (ha)Undisturbed (ha)Total
(1.)EXTERNAL OB DUMPS0000
(2.)ROADS0000
(3.)VIRGIN AREA28.51.56030.06
(4.)GREEN BELT2.6002.6
(5.)BUILT UP AREA (COLONY/OFFICE)0000
(6.)EXCAVATION/QUARRY0000
(7.)TOP SOIL STORAGE0000
(8.)INTERNAL OB DUMPS3003
TOTAL34.11.560035.66
16.
Details of Reclamation:
Total Afforestation Plan shall be Implemented Covering of Mining.
This will Include:
(a)External OB Dump(in hectare) 0
(b)Internal Dump(in hectare) 5.05
(c)Quarry(in hectare) 21.66
(d)Safety Zone(in hectare) 2.6
(e)Final Void of 21.66 (hectare) at a Depth of 30 meter which is Proposed to be Converted into a Water Body.
(f)Density of Tree Plantation per ha (in no.) 1600
(g)Others in ha (such as Excavation Area along ML Boundary, along Roads and Infrastructure, Embankment Area and in Township Located Outside the Lease etc) 0
(h)Total afforestation plant (in hectare) 34.1
17.
Status of progressive Mining Closure Plan:
Details Not Applicable
     18.      Details of Actual Coal/ ORE Production vis-a-vis Sanctioned Capacity since the Inception:
S. No.Financial Year Sanctioned Capacity as per EC (MTPA)Sanctioned Capacity as per CTOSanctioned Capacity as per approved mining planActual Production Excess Production Beyond the EC / CTO/ Mining Plan Sanctioned Capacity (MTPA)
(1.)20190.800.800
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. Sl. No. 23, as per 10th April, 2019 list of MoEF &
(ii)Name of the EIA Consultant Centre for Envotech and Management Consultancy Pri
(iii)Address Plot No-N5/305, IRC Village, Nayapalli, Bhubaneswar-751015
(iv)Mobile No. 0986103282
(v)Landline No. 0674255644
(vi)Email Id cemc_consultancy@yahoo.co.in
(vii)Category of Accreditation A
(viii)Sector of Accreditation Non-Coal Mining
(ix)Validity of Accreditation 16 Feb 2020
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Copy of District Survey Report Copy of District Survey Report
(h)Uploaded Copy of Replenishment Study Report & Baseline Survey Data Copy of Replenishment Study Report & Baseline Survey Data
(i)Uploaded Additional File Copy of Additional File
(j)Uploaded Proposal Presentation (To be given in EAC meeting) NA
      Essential Detail Sought : NIL
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1. ADS Reply LetterWith reference to the Minutes of the 11th meeting of the Expert Appraisal Committee for Environmental Appraisal of Mining projects (Non-Coal) -held during November 27-28, 2019, we are herewith submitting following documents as sought during the presentation for Environmental clearance of Hatgacha-Jethia Black stone Mines over an area of 71.20 ha. in Hatgacha & Jethia villages, P.S. Mohammad Bazar, Dist. Birbhum of West Bengal. I. District Survey Report (DSR) of Birbhum Dist. as per the Ministry notification S.O. 3611 (E) dated 25.07.2018. (Annexure-I) II. Revalidation of grant of Mining lease for Hatgacha- Jethia Black stone Mines which is further extended for a period of six (6) months w.e.f 15.11.2019. (Annexure-II) III. CER budget as per the provisions of OM No. F. No. 22-65/2017-IA-III dated 01 May 2018. (Annexure-III) Therefore, we request you to allow us to obtain Environmental Clearance for our aforementioned project at your earliest. 25 Feb 2020
2.NA

deferred

20 Dec 2019
3. ADS Reply LetterDistrict Survey Report 26 Oct 2019
4.NAPP submitted a copy of DSR as per S.O 141(E) dated 15.01.2016 and as per S.O. 3611(E) dated 25.07.2018 07 Oct 2019
5. ADS Reply LetterPoint Wise Compliance with Annexures_Hatgacha-Jethia Blackstone Mines_Proposal No. IA/WB/MIN/62270/2015 19 Sep 2019
6.NA

Deferred the proposal

24 Jun 2019
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantKRISHNENDU SADHUKHAN
DesignationMANAGING DIRECTOR
Name of Company (Applicant Name should not be given here)WEST BENGAL MINERAL DEVELOPMENT AND TRADING CORPORATION LIMITED
Address13, NELLIE SENGUPTA SARANI 2ND FLOOR, KOLKATA