Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Proposed Installation of Sponge Iron Plant (4x100 TPD Kilns), Induction Furnaces (3x20 T), 1,40,000 TPA capacity Rolling Mill along with 16 MW capacity Captive Power and 1,00,000 TPA Cement Grinding U
(b)Name of the Company / Organisation BRGD SPONGE AND IRON PRIVATE LIMITED
(c)Registered Address 4, Chowringhee Lane, Diamond Chamber, Block - 1, 7th Floor,,Kolkata,West Bengal-700016
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Rajeev Kanodia
(b)Designation (Owner/ Partner/ CEO) Director
(c)Address 4, Chowringhee Lane, Diamond Chamber, Block - 1, 7th Floor,,Kolkata,Kolkata,West Bengal-700016
(d)Pin code 700016
(e)E-mail brgd2008@gmail.com
(f)STD Code. 33(f)Telephone No. 22521464
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity3(a) Metallurgical industries (ferrous & non ferrous)
3(b) Cement plants
Minor Activity1(d) Thermal Power Plants
(b)Category A
(c)Proposal Number IA/WB/IND/72262/2018
(d)Master Proposal Number(Single Window) SW/101611/2019
(e)EAC concerned (for category A Projects only) Industrial Projects - 1
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. -
(b)Pincode 723121
(c)Bounded Latitudes (North)
From
Degree 23.608880
Minutes
Second
From
Degree 23.611366
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 86.786476
Minutes
Second
From
Degree 86.789555
Minutes
Second
(e)Survey of India Topo Sheet No. .
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 147
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area .
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project West Bengal
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)West BengalPurulia
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number NIL
(b)Date of Apply of TOR NIL
(c)Date of Issue of TOR / Standard ToR NIL
(d)Previous TOR Letter NIL
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
NIL
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)DRI & IF4X100 TPD.
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)TMT Bars, Strips & Structural140000Tons per AnnumRoad,Rail
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 12 Jul 2017
(iv)Valid Upto 27 Feb 2020
(v)File No. -
(vi)Application No. -
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 150
(b) Funds Allocated for Environment Management (Capital) (in Crores) 7.5
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 1.5
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.75
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 615950
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 615950
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)ALL Raw materials615950Tons per AnnumMARKETRoad,Rail50 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Mar 2018 To 31 May 2018
(b)Season Summer
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube934592.9100
(2.)NOxMicro Gram per Meter Cube301028.980
(3.)SO2Micro Gram per Meter Cube16415.380
(4.)PM2.5Micro Gram per Meter Cube441343.260
    14.2.     No. of Ground Water monitoring locations : 9
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)TSSmg/l....
(2.)TDSmg/l546325..
(3.)Total Hardnessmg/l245165..
(4.)Chloridesmg/l17768..
(5.)Heavy MetalsFemg/l0.420.28..
(6.)Fluoridemg/l0.50.3..
(7.)pHNA7.86.9..
    14.3.     No. of Surface Water monitoring locations : 10
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)DOmg/l7.16.8C
(2.)pHNA7.37.2C
(3.)CODmg/l..C
(4.)OthersFemg/l0.230.22C
(5.)BODmg/l53C
    14.4.     No. of Ambient Noise monitoring locations : 10
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))62.152.9.
(2.)Leq(Night)A-weighted decibels(dB(A))54.442.9.
    14.5.     No. of Soil Sample Monitored locations : 4
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pH6.45.9
(2.)N(Nitrogen)Kilogram per hectare471422
(3.)K(Potassium)Kilogram per hectare283266
(4.)P(Phosphorus)Kilogram per hectare..
(5.)Electric ConductivityMillisiemens per Centimetre261247
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From . To .
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From . To .
(c)Whether Ground Water Intersection will be there ? Yes
(d)Upload Copy of Central Ground Water Authority Letter Copy of Central Ground Water Authority Letter
(e)Letter No. -
(f)Date of Issue 02 Jan 2019
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater414.Copy of Permission LetterPipelineTube Well-02 Jan 2019.
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Industrial8080ETPReuse within the Plant & Recycling80
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 80
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 80
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)IndustrialIndustrial Waste17000Tons.RoadAuthorized Recyclers
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM2.5Microgram per Meter Cube.....
(2.)SO2Microgram per Meter Cube8.70.82.3611.0680
(3.)PM10Microgram per Meter Cube68.60.53.51772.117100
(4.)NOxMicrogram per Meter Cube19.00.82.3621.3780
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)IFELECTRIC302.0PM10.
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 29000
(b)Source DVC & 16 MW CPP
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) .
(e)Stack Height (in m) .
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0.0
(b)Private Land (ha.) 0.0
(c)Government Land (ha.) 0.0
(d)Revenue Land (ha.) 0.0
(e)Other Land (ha.) 14.16
    Total Land (ha.) 14.16
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 0.0
(b)Waste/Barren Land (ha.) 0.0
(c)Grazing/ Community Land (ha.) 0.0
(d)Surface Water Bodies (ha.) 0.0
(e)Settlements (ha.) 0.0
(f)Industrial (ha.) 14.16
(g)Forest (ha.) 0.0
(h)Mangroves (ha.) 0.0
(i)Marine Area (ha.) 0.0
(j)Others (ha.) : - 0.0
    Total (ha.) 14.16
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Main Plant9.49-
(2.)Township0.0-
(3.)Green belt4.67-
Total (ha.) 14.16
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted Area-.-
(2.)NPANO.-
(3.)CorridorsNO.-
(4.)Wildlife CorridorsNo.-
(5.)ESAsNo.-
(6.)WLS-.-
(7.)ESZsNo.-
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Defence InstallationsNo0.0-
(2.)ForestPanchet Reserve Forest1.5-
(3.)Archaeological SitesNo0.0-
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0.0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 14.16
(b)Land yet to be acquired(Ha) 0.0
(c)Status of Land acquisition if not acquired 0.0
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0.0
(b)No. of Households 0.0
(c)No. of PDFs (Project Displaced Families) 0.0
(d)No. of PAFs (Project Affected Families) 0.0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0.0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? No
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0.0
(b)Permanent Employment-During Operation 400
(c)Temporary Employment- During Construction 0.0
(d)Temporary Employment- During Operation 0.0
(e)No. of working days 300
(f)Total Manpower 400
32.
Green Belt in Ha:
(a)Total Area of Green Belt 4.67
(b)Percentage of Total Project Area 32.98
(c)No. of Plants to be Planted 7000
(d)Funds Allocated for Plantation 0.3
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialEmployment & Infrastructure Development
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 1
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1011/010
(ii)Name of the EIA Consultant ENVIROTECH EAST PVT LIMITED
(iii)Address Bengal Ambuja Commercial Complex UN F13, 1050/1, Survey Park, Kolkata-700 075
(iv)Mobile No. 9331026867
(v)Landline No. 0332418812
(vi)Email Id eeplkol@gmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 1
(ix)Validity of Accreditation 13 Mar 2021
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NA1. Certified compliance report from Regional Office of the Ministry shall be submitted. 2. Social Impact Assessment shall be furnished 3. Plot plan do not have legend,land-use details, scale etc. 4. Mixing height data needs to be rechecked (table 4.3 of EIA report) and accordingly the modeling aspects shall be redrawn 5. HIRA specific to project shall be furnished 6. Public Hearing (PH) issues in verbatim along with action plan for addressing the same shall be incorporated. Further, written representations along with response given shall be also included. 7. Action plan for CER related activities shall be according to the issues raised during the PH and need based assessment in EIA study. 8.Feasibility to use railway siding for transportation of materials shall be furnished. 9. Water abstraction permission shall be furnished and feasibility to draw surface water shall be furnished. 16 Apr 2019
2.NAThe correction have been made as per the instruction received 25 Apr 2019
3.NAThe below EDS was raised on 16/04/2019. However, it is observed that reply to the following EDS has not been furnished again. • Social Impact Assessment report has not been submitted. • Water abstraction permission from the competent authority shall be furnished for the proposed project. 18 May 2019
4.NAThe correction have been made as per the instruction received 02 Dec 2019
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1. ADS Reply LetterADS Reply (with 12 Annexures) of M/s BRGD Sponge & Iron Pvt. Ltd., Purulia, West Bengal. 31 Jul 2020
2.NA

Proposal deferred for want of additional information

09 Jan 2020
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantRajeev Kanodia
DesignationDirector
Name of Company (Applicant Name should not be given here)BRGD SPONGE AND IRON PRIVATE LIMITED
Address4, Chowringhee Lane, Diamond Chamber, Block - 1, 7th Floor