Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Increase Of Iron Ore Production From 1.25 To 1.50 MTPA, Bhadra Iron Ore Mine, M/S. JSW Steel Limited
(b)Name of the Company / Organisation JSW STEEL LIMITED
(c)Registered Address JSW Steel Limited, P.O. Vidyanagar, Toranagallu, Sandur Taluk, Ballari District, Karnataka,,Bellary,Karnataka-583275
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Sunil Kumar Singh
(b)Designation (Owner/ Partner/ CEO) GM Mines
(c)Address JSW Mining Office, Near Talur Cross, Toranagallu, Sandur Taluk, Ballari, Karnataka,,,Bellary,Karnataka-583275
(d)Pin code 583275
(e)E-mail jswminesenvironment@gmail.com
(f)STD Code. 8395(f)Telephone No. 250132
(g)Fax No. 08395250132
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity1(a) Mining of minerals
Minor Activity
(b)Category A
(c)Proposal Number IA/KA/MIN/7548/2008
(d)Master Proposal Number(Single Window) SW/101231/2019
(e)EAC concerned (for category A Projects only) Non-Coal Mining
(f)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. ML No. 2365,Forest Land of Donimalai range
(b)Pincode 583118
(c)Bounded Latitudes (North)
From
Degree 1667718.86
Minutes
Second
From
Degree 1671979.41
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 674874.25
Minutes
Second
From
Degree 676895.41
Minutes
Second
(e)Survey of India Topo Sheet No. 57 A/12
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 962
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 1.9
(j)Seismic Zone 2
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Karnataka
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number J-11015/16/2007- IA. II (M)
(c)Date of Issue of TOR
(f)Previous TOR Letter NA
(b)Date of Apply of EC 23 Feb 2008
(c)Date of Issue of EC 13 May 2008
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :29 Nov 2018
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :29 Dec 2018
Distance of Public Hearing Venue from the Proposed Project :0
Mine Site
State :Karnataka
District :Bellary
Tehsil :Sandur
Village :Ittanahalli / Taranagar village
6001. Job opportunity to the local people (priority to the workers who were working in earlier TML company during appointment) and protect the local environment. 2. Adopt the Taranagara and surroundingDeputy Commissioner
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Bangalore
(iii)Letter No. EP/12.1/673/KAR2222
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit Mar 16 2017 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Iron Ore12500002500001500000Tons per Annum(TPA)Road,Pipe Conveyor
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)Iron Ore Mine12500002500001500000Tons per Annum(TPA)
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception Copy of Consent to Operate
(iii)Date of Issue 30 Oct 2017
(iv)Valid Upto 01 Nov 2017
(v)File No. Not Applicable, CTO Yet to Apply
(vi)Application No. Not Applicable, CTO Yet to Apply
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 110
(b) Funds Allocated for Environment Management (Capital) (in Crores) 7.63
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.5
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.6
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 152
(b)Existing quantity of raw material/fuel 608
(c)Total quantity of raw material/fuel 760
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)ANFO & Booster760Tons per AnnumLicensed VendorsRoad50 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Dec 2017 To 28 Feb 2018
(b)Season Winter
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)SO2Micro Gram per Meter Cube14.68.014.480
(2.)NOxMicro Gram per Meter Cube168.815.980
(3.)PM2.5Micro Gram per Meter Cube39.520.437.560
(4.)PM10Micro Gram per Meter Cube64.444.263.9100
    14.2.     No. of Ground Water monitoring locations : 7
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)Fluoridemg/l1.450.51.01.5
(2.)Heavy Metalszincmg/l0.190.02510
(3.)pHNA8.166.986.58.5
(4.)TSSmg/l0000
(5.)TDSmg/l12167815002000
(6.)Total Hardnessmg/l587383200600
(7.)Chloridesmg/l2671132501000
    14.3.     No. of Surface Water monitoring locations : 1
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHmg/l7.797.79C
(2.)BODmg/l33C
(3.)CODmg/l1818C
(4.)DOmg/l5.85.8C
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))54.148.855
(2.)Leq(Night)A-weighted decibels(dB(A))42.737.445
    14.5.     No. of Soil Sample Monitored locations : 6
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pH8.117.46
(2.)N(Nitrogen)Kilogram per hectare407232
(3.)P(Phosphorus)Kilogram per hectare11733
(4.)K(Potassium)Kilogram per hectare632280
(5.)Electric ConductivityMillisiemens per Centimetre523189
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 40 To 50
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 35 To 40
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater2500Copy of Permission LetterPipelineTube Well2018-19/4624 Jul 201830
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic48Septic Tank Followed by Soak PitOthersSeptic Tank Followed by Soak Pit04
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 4
(b)Total Discharged Water (Kilolitre per Day) 4
(c)Total Reused Water (Kilolitre per Day) 0
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Waste RockOthersMining6000000Tons0RoadOthersDumps and Backfilling
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM2.5Microgram per Meter Cube360.513860
(2.)NOxMicrogram per Meter Cube150.511780
(3.)PM10Microgram per Meter Cube630.51377100
(4.)SO2Microgram per Meter Cube13011580
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)Not Applicable000OthersNone0
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 2000
(b)Source Grid of GESCOM
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 500 KVA and 63.5 KVA
(e)Stack Height (in m) 7
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 133.58
(b)Private Land (ha.) 0
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 133.58
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 0
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 0
(e)Settlements (ha.) 0
(f)Industrial (ha.) 0
(g)Forest (ha.) 130.53
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : none 0
    Total (ha.) 130.53
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Quarry Area57.89-
(2.)Green belt7.38-
(3.)Built Up Area0.30-
(4.)OB Dump Area34.57-
(5.)OthersVirgin/ Unbroken - 28.89 Ha. & Roads - 1.5 Ha.30.39-
Total (ha.) 130.53
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaNone0-
(2.)WLSNone0-
(3.)ESZsNone0-
(4.)Wildlife CorridorsNone0-
(5.)NPANone0-
(6.)CorridorsNone0-
(7.)ESAsNone0-
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Archaeological SitesNone0-
(2.)Defence InstallationsNone0-
(3.)ForestDonimalai RF0Mine is part of Donimalai RF
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? Yes
(a)Forests Clearance Status Final(Stage-II) Approval Obtained
(i)MoEFCC file number FP/KA/MIN/25219/2017
(ii)Date of final approval 15 May 2019
(iii)Date of In-Principle Approval 15 May 2019
(iv)Area diverted 133.58
(v)Uploaded FC Letter Copy of FC Letter
(b)Legal Status of Forest Land Reserved
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 130.53
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired Stage-II Clearance obtained
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? Yes
(i)Details of Schedule-I Species Blackbuck (Antelope cervicarpa), Indian Wolf (Canis Lupus) Indian Leopard (Panthera Pardus) Sloth Bear (Melursus Ursinus) Indian Peafowl (Pavo Cristatus) Monitor Lizard (Varanus Bengalensis) Python
(b)Whether conservation plan for Schedule-I Species has been prepared ? Yes
(i)Uploaded copy of conservation plan Copy of conservation plan
(ii)Fund Provision made 64 Lakhs
(iii)Period of Implementation 3 years
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? Yes
(i)Uploaded copy of approval Copy of approval
(ii)Letter No. PCCF/WLD/CR-41/2018-19
(iii)Date of issue 19 Sep 2018
(iv)Recommendation Conservation Measures are recommended
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Narihalla Dam & Reservoir
(ii)Direction of Water Bodies in Buffer Area West
(iii)Distance of Water Bodies in Buffer Area 1.9
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 14000
(b)Permanent Employment-During Operation 264
(c)Temporary Employment- During Construction 840
(d)Temporary Employment- During Operation 100
(e)No. of working days 300
(f)Total Manpower 15204
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt07.387.38
(2.)Percentage of Total Project Area05.655.65
(3.)No. of Plants01845018450
(4.)Funds Allocated018.9718.97
    33.       Project Benefits
S. No. Type of Project BenefitsDetails of Project Benefits
NIL
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For Non-Coal Mining
S. No.Item Details
     1.       No. of Mineral(s) to be Mined : 1
S. No.Mineral(s) to be Mined Major or Minor Mineral
(1.)Iron OreMajor
2.
Mine Capacity in ROM (Run of Mine) 1.5
3.
Uploaded 500 meters Cluster Certificate from State Mines and Geology in case of minor minerals Copy of 500 meters Cluster Certificate from State Mines and Geology
4.
Mining Plan:
(a)Approval Letter No. 279/1093/2017/BNG/453
(b)Date of Approval 06 Jul 2017
(c)Approved Letter Copy of Approved Letter
(d)Approved By State Mining and Geology Department IBM
(e)Approved Mining Lease Area 130.53
(f)Approved Capacity 1.5
5.
Technical Details:
(a)Total Geological Reserves (Million Ton) 28.82
(b)Mineable Reserves (Million Ton) 27.50
(c)Extractable Reserves(Million Ton) 27.50
(d)Percent(%) of Extraction 95
(e)Grade of Coal /Ore /Mineral 45 - 65 % of Fe Content
(f)Stripping Ratio 1 : 4.06
(g)Category of Gaseousness (Only for Coal Mining, Others may Write NA) NA
(h)Average Gradient(Degree) 62
(i)Mining Method Opencast
(j)Life of Mine (Years) 20
6.
Details of Beneficiations:
(a)Whether it is proposed to install beneficiation plant/Coal washery within the mining lease area No
(b)Whether it is proposed to install crusher within the mining lease area Yes
(c)No. of crushers 1
     6.1.    Details of crusher:
S. No.Crusher ID Capacity (in PH)Remarks
(1.)1250 Mobile Crushing Plant
7.
Details of Seams:
(a)Whether details of seam applicable No
8.
Details of Mining Lease:
(a)Mining Lease Area (in Hectare) 130.53
(b)Whether obtained Letter of Intent (LOI) from the state government ? Yes
(i)Copy of Letter of Intent Copy of Letter of Intent
(ii)Date of issue of LOI 26 Oct 2016
(iii)Validity of LOI 3
(iv)Reference No. of LOI DMG/MLS/CCA/12/2365/2016-17
(c)Whether Lease Deed Executed ? No
(i)Reason thereof The present proposal is a new mine. LOI granted un
(d)Whether Lease Deed Renewed ? No
(i)Reason thereof LOI granted under E-Auction
9.
OB (Over Burden) Management:
(a) Details of External Dumps:
(i)No. of OB Dumps 0
(ii)Total Area (in Hectare) 0
(iii)Height (in meter) 0
(iv)Quantity (in Million Cubic meter) 0
(v)No. of year back fill up 0
(b) Details of Internal Dumps:
(i)No. of Internal Dumps 2
(ii)Total Area (in Hectare) 34.57
(iii)Height (in meter) 196
(iv)Quantity (in Million Cubic meter) 22
10.
Details of Topsoil Management:
(a)Quantity of Topsoil excavated during the entire life of the mine (in Million Cubic metre) 0
(b)Quantity of Topsoil proposed for utilization for reclamation during the entire life of the mine (in Million Cubic metre) 0
(c)Quantity of Topsoil proposed for utilization for other activities during the entire life of the mine (in Million Cubic metre) 0
11.
Details of Final Mine Void:
(a)Area (in Hectare) 57.89
(b)Depth (in meter) 116
(c)Volume (in Million Cubic meter) 67.15
12.
Details of Quarry:
(a)Final Void of 57.89 (hectare) at a Depth of 0 meter which is Proposed to be Converted into a Water Body.
(b)Total Quarry Area (ha) 130.53
13.
Details of Transportation:
(a)In Pit/Underground to Surface Dumpers
(b)Surface to Siding/Loading Dumpers
(c)Transportation / Conveyor Details Proposed DTH
     14.      Details of Land Usage (Pre-Mining)
S. No.LAND USE Other LAND USEWITHIN ML AREA (Hectare)OUTSIDE ML AREA (Hectare)TOTAL (Hectare)
(1.)FOREST LAND130.530130.53
(2.)WASTE LAND000
(3.)SURFACE WATER BODIES000
(4.)AGRICULTURE LAND000
(5.)SETTLEMENTS000
(6.)GRAZING LAND000
TOTAL130.530130.53
     15.      Details of Land Usage (Post-Mining)
S. No.LAND USE Other LAND USEPlantation (ha)Water Body (ha)Public Use (ha)Undisturbed (ha)Total
(1.)TOP SOIL STORAGE0000
(2.)EXTERNAL OB DUMPS0000
(3.)ROADS001.501.5
(4.)EXCAVATION/QUARRY57.890057.89
(5.)INTERNAL OB DUMPS34.570034.57
(6.)BUILT UP AREA (COLONY/OFFICE)000.300.3
(7.)GREEN BELT7.38007.38
(8.)VIRGIN AREA28.890028.89
TOTAL128.7301.80130.53
16.
Details of Reclamation:
Total Afforestation Plan shall be Implemented Covering of Mining.
This will Include:
(a)External OB Dump(in hectare) 0
(b)Internal Dump(in hectare) 34.57
(c)Quarry(in hectare) 130.53
(d)Safety Zone(in hectare) 7.38
(e)Final Void of 57.89 (hectare) at a Depth of 116 meter which is Proposed to be Converted into a Water Body.
(f)Density of Tree Plantation per ha (in no.) 2500
(g)Others in ha (such as Excavation Area along ML Boundary, along Roads and Infrastructure, Embankment Area and in Township Located Outside the Lease etc) 30.69
(h)Total afforestation plant (in hectare) 7.38
17.
Status of progressive Mining Closure Plan:
Copy of Implementation of Various Activities as per Approved Progressive Mine Closure Plan Copy of Implementation of Various Activities as per Approved Progressive Mine Closure Plan
Any Deviation from the Approved Progressive Mine Closure Plan No
Total Area Excavated (in hectare) 0
Total Area Backfilled after Excavation (in hectare) 0
Total Area Reclaimed (in hectare) 0
     18.      Details of Actual Coal/ ORE Production vis-a-vis Sanctioned Capacity since the Inception:
S. No.Financial Year Sanctioned Capacity as per EC (MTPA)Sanctioned Capacity as per CTOSanctioned Capacity as per approved mining planActual Production Excess Production Beyond the EC / CTO/ Mining Plan Sanctioned Capacity (MTPA)
(1.)2017181.2501.500
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1619/SA064
(ii)Name of the EIA Consultant B. S. Envi-Tech Pvt. Ltd
(iii)Address 12-13-1270/71/73, Amity Ville, 4th Floor, Beside Spencer Super Market, St. Ann’s Road, Tarnaka, Secunderabad-500017
(iv)Mobile No. 9848053012
(v)Landline No. 4049783062
(vi)Email Id info@bsenvitech.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Non-Coal Mining
(ix)Validity of Accreditation 12 Nov 2019
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAPlease submit the following:- 1. Copy of EC and TOR documents. 2. Copy of forest clearance document 3. Details of past production of mine since its inception, duly authenticated by Department of Mines & Geology, State Government. 4. Copy of affidavit needs to be submitted by PP in compliance of the Ministry’s OM no. 3-50/2017-IA.III (Pt.), dated 30th May 2018. 5. Compliance of order dated 02.8.2017 in CWP No. 114/2014 of Hon'ble Supreme court (Common Cause Vs Union of India &Ors.) 6. Details of demand if any raised by Department of Mining and Geology 7. Details of payment, if any made to Department of Mines & Geology 8. Validity of mine lease and copy of valid lease document. 9. Status of mine whether working or not. 10. The company name mentioned as M/s Tungabhadra Minerals (P) Ltd in the PARIVESH PORTAL, however, the application submitted by M/s. JSW Steel Limited. Please correct the same in the parivesh portal. 11. The total mine lease area in the Form 2 is not the same as LOI/Lease document. Please correct the same. 08 May 2019
2.NAThe correction have been made as per the instruction received 21 May 2019
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1. ADS Reply LetterWe are herewith submitting the replies to ADS points. We request MOEFCC to grant Environmental Clearance. 21 Dec 2019
2. ADS Raise LetterADS 19 Dec 2019
3. ADS Reply LetterNA 26 Aug 2019
4.NABased on the presentation made by PP and the discussion held, the Committee deferred the proposals and asked the PP to submit following requisite information for further consideration. (i). PP needs to carry out the 3D modeling for PM2.5 and PM10 taking it as point at top of mine and assess impacts on nearby village, habitation, vegetation and agriculture land. (ii). PP needs to submit the provisions of control of dust at the source be made to prevent the impacts on environment. (iii). PP requires to carry out direction particle size analysis for upwind and downwind direction of dust. (iv). PP requires to submit the socio-economic survey for affected people (quantity needs to be specified) and measures for protection with timeline and budgetary provisions. (v). PP submitted that the total cost of project is 43.39 Crores, however, in Form 2, it is mentioned that 110 Crores. The Committee asked the PP for confirmation and PP confirmed that the total cost of the project is 110 Crores. Accordingly, the PP has to revise the CER,Wildlife conservation and EMP budget. (vi). PP needs to submit the approved revised wildlife conservation plans (details of species and their protection plans). (vii). PP needs to submit the revised year wise budgetary provision for monitoring and pollution measurement of the mining activities. (viii). PP requires to submit the details of ore transport mode and the issues arises due to transportation and the mitigation plans planned for protecting the environment. (ix). PP submitted that the ore will be dispatched to JSW steel plant by tippers/dumpers. PP needs to submit the locations of the plant as well as distance between the plant and mine. Also submit the details of mitigation measures to be implemented for minimizing the environmental impact. (x). PP needs to submit the capacity of crushers and flow chart for crusher and screening unit and also their working time and impact on the environment. (xi). PP needs to submit the details of total excavation including total waste generation. (xii). PP submitted the action plans for public hearing issues which are generic and PP needs to submit the revised detailed actions plans with revised budgetary provisions for the public hearing issues. (xiii). PP has mentioned in the EIA report that the waste dump areais decreasing over period of time. It is not clear that whether the dumping is also being used or not. Accordingly, PP needs to submit the necessaryclarifications for the same. (xiv). PP submitted that the written suggestions/objections/queries raised during public hearing are in local language. PP needs to submit the authenticated translated copy in English for the same. 17 Jul 2019
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantSunil Kumar Singh
DesignationGM Mines
Name of Company (Applicant Name should not be given here)JSW STEEL LIMITED
AddressJSW Steel Limited, P.O. Vidyanagar, Toranagallu, Sandur Taluk, Ballari District, Karnataka
Print