Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Proposed Treatment, Storage, Disposal Facility (Incineration only) for Hazardous waste proposed at Plot No. B-28 & 29, Industrial Area, Danewala, Malout-(Punjab) by M/s Sevrin Environ Management Co
(b)Name of the Company / Organisation SAVRIN ENVIRON MANAGEMENT CO
(c)Registered Address M/S Savrin Envirin Management Management Co. at plot No. B-28 &29,Industrial Area, Focal, Malout, Muktsar,152107 (Punjab),,Shri Muktsar Sahib,Punjab-152107
(d)Legal Status of the Company Others
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Abhimanyu Goyal
(b)Designation (Owner/ Partner/ CEO) PARTNER
(c)Address Plot no. B-03, Indusrial Area, VPO Danewala, Malout, Punjab.,,Malout,Shri Muktsar Sahib,Punjab-152107
(d)Pin code 152107
(e)E-mail abhishekgarg178@gmail.com
(f)STD Code. 98885(f)Telephone No. 45268
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity7(d) Common hazardous waste treatment, storage and disposal facilities (TSDFs)
Minor Activity
(b)Category A
(c)Proposal Number IA/PB/MIS/76992/2018
(d)Master Proposal Number(Single Window) SW/101126/2019
(e)EAC concerned (for category A Projects only) INFRA-2
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. B-28 & 29
(b)Pincode 152107
(c)Bounded Latitudes (North)
From
Degree 30.1645
Minutes
Second
From
Degree 30.16488
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 74.51349
Minutes
Second
From
Degree 74.5139
Minutes
Second
(e)Survey of India Topo Sheet No. 44J7,44J8,44J11,44J12
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 200
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 0
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Punjab
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)PunjabShri Muktsar SahibMalout
6.
Details of Terms of Reference (ToR):
(a)Whether TOR is mandatory for submitting application Yes
(b)MoEF&CC / SEIAA File Number 10-69/2018-IA-III
(c)Date of Apply of TOR 29 Aug 2018
(d)Date of Issue of TOR / Standard ToR 09 Oct 2018
(e)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason Project “Common Treatment, Storage, Disposal Facil
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)CHWTSDF1690.83 m2Total Area
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Liquid Waste1460OthersKilo Liters Per AnnumRoad
(2.)Solid Waste365Tons per AnnumRoad
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 0.78
(b) Funds Allocated for Environment Management (Capital) (in Crores) 0.185
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.02
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.028
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 5
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 5
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Liquid Waste1460OthersKilo Litres per AnnumNearby IndustriesRoad200 Open MarketCopy of Linkage
(2.)Solid Waste365Tons per AnnumNearby IndustriesRoad200 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Oct 2018 To 31 Dec 2018
(b)Season Post-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 7
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM2.5Micro Gram per Meter Cube763873.6160
(2.)OthersNH3Micro Gram per Meter Cube271426400
(3.)PM10Micro Gram per Meter Cube13071126100
(4.)NOxMicro Gram per Meter Cube30152980
(5.)SO2Micro Gram per Meter Cube1471380
    14.2.     No. of Ground Water monitoring locations : 7
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)Total Hardnessmg/l381145200600
(2.)pHNA7.9176.58.5
(3.)TSSNA0000
(4.)TDSmg/l12505305002000
(5.)Chloridesmg/l325852501000
(6.)Fluoridemg/l1.150.2411.5
(7.)Heavy MetalsZnmg/l0.050.05515
    14.3.     No. of Surface Water monitoring locations : 2
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA7.957.58B
(2.)CODmg/l1612B
(3.)DOmg/l6.66.3B
(4.)OthersTotal Hardnessmg/l131110B
(5.)BODmg/l53B
    14.4.     No. of Ambient Noise monitoring locations : 7
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))614355/65
(2.)Leq(Night)A-weighted decibels(dB(A))614350/60
    14.5.     No. of Soil Sample Monitored locations : 7
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pH8.437.83
(2.)N(Nitrogen)00
(3.)K(Potassium)Milligram per Kilogram61027.5
(4.)Electric ConductivityMillisiemens per Centimetre0.6840.143
(5.)P(Phosphorus)00
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 0.67 To 7.43
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 0.06 To 7.78
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersPSIEC Supply21Copy of Permission LetterPipelineOthersPipelinePSIEC/ESTA/EO/773527 Jun 20182
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic Waste0.81Septic Tank Followed by Soak PitOthersNA0.80
(2.)Industrial0.20.5Used for Wet &Quencher ScrubberReuse within the Plant & RecyclingR0.2
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 1
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 1
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Incinerator AshHazardous Waste (as per Hazardous and Other Waste Management rules 2016)30Tons230RoadTreatment, Storage and Disposal Facility(TSDF)
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube13000130.1100
(2.)PM2.5Microgram per Meter Cube760076.160
(3.)SO2Microgram per Meter Cube140014.180
(4.)NOxMicrogram per Meter Cube300030.180
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)IncineratorHazardous Waste300.4PM104.1
(2.)Propose DG SetDiesel50.3PM100.25
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 50
(b)Source PSIECL
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 63 KVA
(e)Stack Height (in m) 5
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 0
(c)Government Land (ha.) 0.1691
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 0.1691
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 26187
(b)Waste/Barren Land (ha.) 1989
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 245
(e)Settlements (ha.) 2994
(f)Industrial (ha.) 0
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : NA 0
    Total (ha.) 31415
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Main Plant0.1132Main Plant Area
(2.)Green belt0.0559Green Belt
Total (ha.) 0.1691
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaNA0NA
(2.)ESAsNA0NA
(3.)ESZsNA0NA
(4.)CorridorsNA0NA
(5.)WLSNA0NA
(6.)NPANA0NA
(7.)Wildlife CorridorsNA0NA
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestNA0NA
(2.)Defence InstallationsNA0NA
(3.)Archaeological SitesNA0NA
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 0.1691
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired 0
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in INR) (in Lacs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Rajasthan Canal
(ii)Direction of Water Bodies in Buffer Area East
(iii)Distance of Water Bodies in Buffer Area 8
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 4
(b)Permanent Employment-During Operation 6
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 0
(e)No. of working days 365
(f)Total Manpower 10
32.
Green Belt in Ha:
(a)Total Area of Green Belt 0.0559
(b)Percentage of Total Project Area 33.06
(c)No. of Plants to be Planted 110
(d)Funds Allocated for Plantation 100000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)EnvironmentalCommon Treatment Storage Facility shall be an important endeavor to mitigate the degradation of environment in the region.
(2.)SocialThe proposed project will provide direct employment to people of the area and business opportunity to feed the demand of project and the people working for the project. Small market will be developed to feed daily demand of the people working for the proposed project.
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For INFRA-2
S. No.Item Details
1.
Details of Building Construction:
(a)Maximum Height of the Building (Meters) 0
(b)Total No. of Flats to be Build 0
(c)No. of Buildings 0
(d)Total plot area (sqm) 1691
(e)Total built up area (sqm) 1132
2.
Foreshore Facilities and/or Marine Disposal:
(a)Whether Project Involves Foreshore Activities and/or marine Disposal? No
3.
Rain Water Harvesting:
(a)No. of Storage 0
(b)Capacity 0
(c)No. of Recharge Pits 0
(d)Capacity 0
4.
Parking:
(a)Details of 4 Wheeler/ 2 Wheeler Parking 5
5.
Energy Saving Measures:
(a)Source/Mode NA
(b)Percentage 0
(c)Quantity 0
6.
Other details:
(a)Details of impact on Water Bodies and Drainage patters of catchment area NA
(b)Details of Traffic Density Impact Assessment and Modelling Study Copy of Details of Traffic Density Impact Assessment and Modelling Study
(c)In case Underground Tunnel Project below the Forest Land - Subsidence Impact Study report Copy of Underground Tunnel Project below the Forest Land - Subsidence Impact Study report
     7.       Type of Industries to be established with Industrial Estate as per their category A/B
S. No.Type of IndustryNo. of UnitsCategory A/B
NIL
8.
Length of the alignment N/A
9.
Details Bridges/ROB/Interchanges,Flyovers,Vehicle Underpass and Pedestrian Underpass
Details Not Applicable
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1619/RA 0040
(ii)Name of the EIA Consultant Shivalik Solid Waste Management Limited
(iii)Address Ist Floor,sco 20-21, Near Dolphin Dhakoli, Zirakpur, Punjab 140604
(iv)Mobile No. 8288079360
(v)Landline No. 0176250949
(vi)Email Id s.brahma@beil.co.in
(vii)Category of Accreditation A
(viii)Sector of Accreditation INFRA-2
(ix)Validity of Accreditation 16 Aug 2019
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File NA
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
      Essential Detail Sought : NIL
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantAbhimanyu Goyal
DesignationPARTNER
Name of Company (Applicant Name should not be given here)SAVRIN ENVIRON MANAGEMENT CO
AddressM/S Savrin Envirin Management Management Co. at plot No. B-28 &29,Industrial Area, Focal, Malout, Muktsar,152107 (Punjab)